Petten, 04 December 2014
CHALLENGES OF REPRESENTING ELECTRICITY SYSTEM FLEXIBILITY IN ENERGY SYSTEMS MODELS
Vera Silva, EDF R&D
Co-authors: Gregoire Prime, Timothee Hinchliffe, Dominique Lafond, François Rehulka, Miguel Lopez-Botet
CHALLENGES OF REPRESENTING ELECTRICITY SYSTEM FLEXIBILITY IN - - PowerPoint PPT Presentation
CHALLENGES OF REPRESENTING ELECTRICITY SYSTEM FLEXIBILITY IN ENERGY SYSTEMS MODELS Vera Silva, EDF R&D Co-authors: Gregoire Prime, Timothee Hinchliffe, Dominique Lafond, Franois Rehulka, Miguel Lopez-Botet Petten, 04 December 2014 T
Petten, 04 December 2014
Co-authors: Gregoire Prime, Timothee Hinchliffe, Dominique Lafond, François Rehulka, Miguel Lopez-Botet
| 2
| 3
Long term forecasts of demand, commodity prices, etc Reliability and flexibility requirements
Transmission expansion options and candidate generation technologies Generation and Transmission planning Production cost simulations and operation flexibility assessment
FlexAssessment Continental Model with Investment loop MADONE
| 4
| 5
with different levels of detail depending on the country
electricity and gaz, CO2
hydro (one lake per country + hydro-pumping), gaz, CO2
NordStream, Southstream, Nabucco, DESERTEC…
wind off-shore: km2(depth, wind speed, distance to coast) X
Capacity density; Wind on-shore km2 ( area potentially available) X Capacity density; solar PV: area available, roofs surfaces; CO2 storage; biomass resources
yearly from 2005 to 2010, every 10 years from 2010 to 2050 representation of each year with load curves eg: 24, 288 points
technology mix & detailed energy balances , energy dependency,
and environmental indicators, balance for electricity (including exchanges), association of energy uses and activities….
275 Mtep / 549 TWh 1339 Mtep / 2114 TWh 258 Mtep / 580 TWh
12/11/2005 EFESE/OSIRIS lot MADONE / Enerbat / EPI / MFEE/ EIFER 4
2/1. 8 0.8/0.7 0.08/0.02 0.65/0.65 1.2/0.47 1.9/0. 9 2.05/1.5 1.9/2.75 3/3.85 0.6/0.6 3.2/1.5 2.5/0.8 1.1/1.2 3.2/2.2 2.4/2.4 0.5/1.4 0.995/2.65 2.3/3.2 2/2 0.5/0.6 0.75/0.75 0.95/0.95 1.98/2.44 1.2/1.3 0.3/0 0.35/0.35 0.75/0.75 2.05/1.65 0.5/0.5 1.5/0.8 0.9/0.6 0.43/0.16 4.24/1.81 1.3/1.5 2.3/2.2 1.75/0.8 0.5/0.5 0.6/0.1 2/1
Capacités d’interconnexion en 2005 (enGW)
TO /FROM
Légende:
detailed interm. aggregated
| 6
description of different countries generation mix and key transmission corridors interconnection capacities between countries management of water reservoirs and pump storage a large number of scenarios of climate years represented by demand and variable
several scenarios of generation availability
hydro and storage flexibility optimization => stochastic problem generation scheduling needs to be performed across the whole Europe including
analysis of system static and dynamic security => hierarchical approach
| 7
Fixed costs include investment and O&M Variable costs include start-up and fuel costs
Load duration curve based heuristic to propose a
Validation of the heuristic solution solving the
Maximum of 3h/year with marginal price = VOLL
Investment loop Demand Variable generation profiles Interconnection constraints Storage Investment costs Commodity prices CO2 price
INPUT DATA Optimal thermal generation mix Production dispatch Production costs Market clearing prices CO2 emissions Hydro stock level paths Interconnection uses OUTPUT
| 8
Reference: Langrene, N., van Ackooij, W., Breant, F., « Dynamic Constraints for Aggregated Units: Formulation and Application », Power Systems, IEEE Transactions on , vol.26, no.3, Aug. 2011
Unit commitment and economic dispatch minimizes thermal and hydro generation cost over all the scenarios Constraints include primary, secondary and tertiary reserve and generation dynamic ratings Multi area optimization with interconnection constraints represented by NTC
Maximize the reduction in terms of generation costs using dynamic optimization to obtain the « water value » for each time step Define a set of strategies of the optimal use of hydro reservoirs in order to minimize the global generation cost
Scenarios data Water values
For each dispatch period and for each zone the dispatch solution and the market clearing prices are obtained to access the revenues of generation units
| 9
MADONE
European countries
limits detailed: Wind off-shore, wind on-shore, roof
for PV etc…
24 =Peak and Off-Peak for each month 288 = 2 representative day (Week/W-E, bi-
hourly)/month
With or without renewable contribution
Or multi-scenarios for one chosen year : testing
with 4 annual scenarios
Demand-generation balancing solved for one
year with hourly resolution
Interconnection constraints included Stochastic parameters: (T°, hydro, wind, PV and
generation outages)
max
| 10
89 90 89 90 90 91 90 91 91 67 63 65 40 68 71 68 70 63 77 90 106 125 90 86 92 88 96 50 100 150 200 250
Def 5k€_Seuil 5k€_200MW Def 10k€_Seuil 5k€_200MW Def 50k€_Seuil 5k€_200MW Def 10k€_Seuil 5k€_MC1pt Def 5k€_Seuil 5k€_MC2all Def 20k€_Seuil 20k€_200MW Def 20k€_Seuil 10k€_600MW Def 20k€_Seuil 10k€_200MW REF_Def 20k€_Seuil 5k€_200MW
Capacité installée globale : MAD Global (GW)
89 89 89 81 81 81 43 41 41 42 43 40 234 101 34 224 96 10
100 150 200 250 300 350
288p + peak ss EnR 288p + peak 288p 24p + peak ss EnR 24p + peak 24p
| 11
Choice of a (limited =4) set of scenario: how to select the right ones? Calibration of peak equation could be a solution… but largely dependent on the system
91 63 96
€ € € € € € € € € € ll € € € € € € REF_Def 20k€_Seuil 5k€_200MW
89 41 101
288p + peak
Madone
| 12
For instance, a peak equation imposes investment in back-up capacity, not its use.
« right »= least cost + meeting capacity adequacy & flexibility adequacy system requirements
Renewables mix per country: F (cost/potential) with sensitivity to interconnection
| 13
Location of VG Load factors (with resolution 1h or lower) VG forecast errors
Reserves and flexibility adequacy
Market prices and generation costs Generation load factors Interconnection load factors Generation mix Frequency stability VG curtailment Plant revenues
Investment loop Detailed description of VG Demand time series Investment costs Generation dynamic constraints Fuels costs CO2 price Network transfer capacities Input data
The model coupling can include multi-annual investment trajectories simulated with Times complemented with annual snapshot simulations with Continental Model
| 14
200 300 400 500 600 30 60 90 120 150 180 210 240 270 300 330 360
200 300 400 500 600 30 60 90 120 150 180 210 240 270 300 330 360
200 300 400 500 600 30 60 90 120 150 180 210 240 270 300 330 360
Net demand with 40 % VG penetration Net demand with 15 % VG penetration Demand
Difference between 31 weather years (Δmax= 25% daily net energy demand) Difference between 31 weather years (Δmax= 90% of daily net energy demand) Difference between 31 weather years (Δmax= 7% of daily energy demand)
200 300 400 500 30 60 90 120 150 180 210 240 270 300 330 360
20 30 40 50 60 70 80 90 100
1 year Scenario Week
For one single weather year daily variation of net demand and intra- day variation requires to take consider forecasting errors & margins Intra-day variation of net demand requires to take into account near term flexibilities
Solaire Eolien Fatal Hydraulique Demande DemandeRes
Solar Wind Biomas s Hydro Demand Net Demand
Close to 100 scenarios (1 year with hourly resolution) created from synthetic demand, wind and PV data for 31 weather years combined with generation availability
| 15
Variation compared to non VG ref case
GW
200 300 400 500 600 700 1000 2000 3000 4000 5000 6000 7000 8000
European net load duration curve European load duration curve
h
GW
200 300 400 500 600 700 1000 2000 3000 4000 5000 6000 7000 8000
Peak power needs increase
h
BASE PEAK BASE PEAK
Comparison of the Generation mix transformation with VG Load duration curve approach vs. optimized with the investment loop
Simulation of hourly scheduling leads to a mix with:
compared to a load duration curve investment approach
0% 50% 100% 150% 200% Base Mid Merit Peak Base generation decreases in the order of the energy provided by VG MID-MERIT MID-MERIT
With flexibility constraints Load duration curve
| 16
Different technologies are represented by clusters of identical units (nuclear, coal,CCGT, OCT) with aggregated dynamic constraints => MSG, Min-up and down times, ramp-rates, start and stop times,
The annual optimization is performed by successive optimizations using a sliding window with a perfect foresight of stochastic values (units failure, demand, wind and PV) are known for the duration
FlexAssessment – tests the robustness of the dispatch solutions considering all aspects of the stochastic behavior of demand and generation.
European synchronous system dynamic model–assessment of the dynamic frequency stability for every dispatch period
| 17
schedule
scenarios
for different lead times (eg: day- ahead,1h, 2h, 4h, etc)
margins for different lead times
different lead times represented as a Probability of Insufficient operation margin = f(direction, lead-time)
Lead time
| 18
Convolution: generation excess generation deficit
Example of distribution of each source of uncertainty for
Example of the distribution of demand- generation balance
e.g. n % risk used to define reserve requirements
Probability to need a margin lower than x MW
| 19
« spinning component» Start OCT (gaz or oil) Start Offline CCGT Start Offline Coal and nuclear Load shedding.
saturation flexSource t T way
1000 2000 3000 4000 5000 0.1 0.2 0.3 0.4 0.5 0.6
Power (MW) Upward Activation Probability by Technology, for lead time = 2 Head Room Margin OCT Margin CCGT Margin Load Shedding 1 h
| 20
flexibility source
annual indicators
number of period with insufficient flexibility mean hourly power deployment (MW) generation headroom 400,8 702,1 quick plant start 1 100,5 150,8 quick plant start 2 0,0 60,1 slow plant start 0,0 0,0 load shedding 0,0 0,0
Not deployable Insufficient 1H margin probability =0 Means that the probability of deployment
quick plant start 1-2 within in less than 1 h is 0 zero risk to run out to upward margin Annual utilization of different flexibility sources Average 1h upward flexibility deployment = 913 MW
During 400,8 h we need to resort to OCGT to manage 1h fluctuations
Not desired
| 21
development involves a necessary adaptation of the existing electrical and energy system and drives additional costs.
done to model the need for flexibility in planning models.
size systems. This notion is currently being extended to multi-energy systems.
system planning tool Continental Model. Similar type of work has been done by other institutions as :
Coupling PRIMES – Plexos - DSIM used in the DG study « Energy integration of renewable energy in
Europe « (Kema, Imperial College)
Coupling TIMES-Plexos (or other) envisaged by the JRC
electricity system but the solutions obtained are not necessarily optimal.
type of information exchanges between models if chains of models are used.
| 23
| 24
Time scale Domain Elements affected Flexibility sources Close to real time horizon
Seconds Frequency regulation:
Frequency containment reserves (FCR)
Dynamic frequency stability FCR reserve providers Minutes Frequency regulation:
Frequency restoration reserves (FRR)
Frequency FRR reserve providers
Scheduling and dispatch horizon
Minutes to hour Replacement reserves (RR) and balancing Economic dispatch Follow net load variation and FCR and FRR Observability and Forecasting Increase reserves Ramping capability Quick start plant Hours to days Generation scheduling Day-ahead and intra- day markets Generation dispatch Transmission and distribution operation Wind utilisation Observability and Forecasting Efficient market design Scheduling flexibility
Planning horizon
Years Expansion planning Generation adequacy Flexibility adequacy Transmission and distribution reinforcement Optimise generation mix Coordination between generation and network investment
| 25
| 26
Source: H. Holtinnent et all, « Flexibility in the 21 century power systems», 21st century Power Partnership project
| 27
Industry:
Residential sectors:
Service sectors:
Transport sectors:
Agriculture:
Oil & solid fuel supply Gas supply (Eurasian area)
Biomass-waste supply
Uranium supply Non energy uses:
FINAL ENERGY PRIMARY ENERGY
Wind, solar, hydro supply
(country + on/off shore + wind speed (9) + hours differenciation)
areas X capacity density hyp. Ex: wind off –shore: km2 available per country according to wind speed (9), distance to coast (2) and depth (3) Ex: solar PV: m2 of roofs available, land available…
Electricty & steam production:
Refineries Industrial transformations
( efficiency rates of direct consumption processes) TRANSFORMATION PROCESSES
Energy sector consumption:
= linked to production CO2 storage potentials:
Saline aquifers, DGOF on & off-shore
| 28
to synchronize (Ps). A capacity outage probability table (COPT) is built for each dispatch period.
factor
the hour of the day and the month of the year
and the month of the year
0.05 0.1 0.15 0.2 0.25 0.3 Actual - committed generation (MW) Probability
50 20 40 60 80 100 5 FLF (%IC) LF (%IC) Density
10 20 0.02 0.04 0.06 0.08
Deviation (%IC) Density
Hour PV Farms Roof-top PV