Ch Chie ief f Jo Joseph h Fis ish Ha Hatch chery ry Chief - - PowerPoint PPT Presentation

ch chie ief f jo joseph h fis ish ha hatch chery ry chief
SMART_READER_LITE
LIVE PREVIEW

Ch Chie ief f Jo Joseph h Fis ish Ha Hatch chery ry Chief - - PowerPoint PPT Presentation

Ch Chie ief f Jo Joseph h Fis ish Ha Hatch chery ry Chief Joseph Dam Bridgeport, WA 200 Miles ON COLUMBI MBIA RIVER, R, EAST T OF BRIDGEPORT IDGEPORT, , WA 2 ND ND LARGEST ST POWER R PROD ODUCI CING DAM M IN THE


slide-1
SLIDE 1

Ch Chie ief f Jo Joseph h Fis ish Ha Hatch chery ry

slide-2
SLIDE 2

Chief Joseph Dam – Bridgeport, WA

200 Miles

slide-3
SLIDE 3

ON COLUMBI MBIA RIVER, R, EAST T OF BRIDGEPORT IDGEPORT, , WA

2ND

ND LARGEST

ST POWER R PROD ODUCI CING DAM M IN THE U.S. S.

OPERA RATE TED BY US Army Corps s of Engin ineers ers, , Power er from Dam suppli lied to BPA

slide-4
SLIDE 4

 Owner – Bonneville Power Administration  Designer/Owner’s Representative – TetraTech  End User – Confederated Tribes of the Colville Reservation  Additional Stakeholders

  • US Army Corps of Engineers
  • Washington State Parks
  • Douglas County PUD
  • Grant County PUD
slide-5
SLIDE 5

 Promised to Colville Tribe when Dam System added

to Columbia River

 Confederated Tribes of the Colville Reservation will

use and operate the Hatchery after completion

 Hatchery intended to produce approx1.9 Million

salmon each year

slide-6
SLIDE 6

 Auxiliary Facilities includes:

  • 2 Acclimation Ponds (sites north of the Hatchery)
  • Employee Housing complex
  • Well field northeast of the Hatchery
  • Hatchery complex includes:

 Office Building, Hatchery Building, Storage Building, Head Box, Raceways, 3 Fish Rearing Ponds, and Fish Ladder/Spawning Facility

slide-7
SLIDE 7

 Preconstruction Start January, 2009; Finish June,

2010

 Separate contract for Well Fields

  • Start October, 2009; Finish March, 2010

 Phase I contract originally included Acclimation

Ponds and Housing

  • Start June, 2010; Finish February, 2011

 Phase II (Change Order) for Hatchery Facility

  • Start December, 2010; Finish April, 2013
slide-8
SLIDE 8

 Well Fields – $665,000  Preconstruction Services – $167,000  Hatchery Facility –

  • Orig Contract amount – $43 Million
  • Final Contract amount - $51 Million
slide-9
SLIDE 9

Actual Broodstock Schedule

slide-10
SLIDE 10

Precon Activities

slide-11
SLIDE 11

 PCL developed Bid Scope packages during

  • preconstruction. Worked with Owner on

Subcontractor selection

 TERO bid preferences – sliding scale  All trades hiring through TERO office

slide-12
SLIDE 12
slide-13
SLIDE 13
slide-14
SLIDE 14
slide-15
SLIDE 15
slide-16
SLIDE 16
slide-17
SLIDE 17

 3 Sided Cofferdam w/Brace Frame – Water

Elevation 784’

  • Costs - $517K, Schedule – 2 Week impact
  • Assume no ground water migration

 4 Sided Cofferdam w/Brace Frame and Work

Tressle – Water Elevation 795’

  • Costs - $2M ($1.2M cofferdam & $900K Schedule)
  • Schedule – 14 Week impact
  • Seal slab and uplift piles required
slide-18
SLIDE 18
slide-19
SLIDE 19
slide-20
SLIDE 20

 PCL used conventional Peri panelized forms  Engaged Hatchery Manager late in the process –

Discovered wall finish was susceptible to spreading bacteria between sections

 Result was extensive sacking and patching of

Raceway walls

slide-21
SLIDE 21
slide-22
SLIDE 22

Raceway Wall Finish Option # 1A

Formwork rmwork Type / Summary: mary:

Steel Forms

Rental of two bays of formwork for duration

Assume 75% crane support for activities

Schedule/manpower limited by labor available in remote area

Fini nish h Type / Level el of Fini nish sh Expected ected:

Sack and Patch walls after stripping

Allows 24 cure required by specifications

Bug holes and joints filled to prevent areas for disease to build-up

Eliminates ridges/sharp transitions for fish

Engine ineeri ering/C ng/Cons

  • nstr

truct uctab abili lity ty Consi sidera deratio tions ns:

Fewer and smoother joint transitions than most panelized systems

Forms more susceptible to heat during hot summers

Less adaptable to changes

Heavy crane useage

Maintenance required long term for finish/cement that eventually will flake off at joints

Cost st*: See Atta tached hed

slide-23
SLIDE 23
slide-24
SLIDE 24
slide-25
SLIDE 25
slide-26
SLIDE 26
slide-27
SLIDE 27
slide-28
SLIDE 28
slide-29
SLIDE 29
slide-30
SLIDE 30
slide-31
SLIDE 31
slide-32
SLIDE 32
slide-33
SLIDE 33
slide-34
SLIDE 34
slide-35
SLIDE 35
slide-36
SLIDE 36
slide-37
SLIDE 37
slide-38
SLIDE 38
slide-39
SLIDE 39
slide-40
SLIDE 40
slide-41
SLIDE 41
slide-42
SLIDE 42
slide-43
SLIDE 43
slide-44
SLIDE 44
slide-45
SLIDE 45
slide-46
SLIDE 46
slide-47
SLIDE 47
slide-48
SLIDE 48
slide-49
SLIDE 49
slide-50
SLIDE 50
slide-51
SLIDE 51
slide-52
SLIDE 52
slide-53
SLIDE 53
slide-54
SLIDE 54
slide-55
SLIDE 55
slide-56
SLIDE 56

Questions?