CenterPoint Energy Super Bowl LI Coordination and Hurricane Harvey - - PowerPoint PPT Presentation

centerpoint energy super bowl li coordination and
SMART_READER_LITE
LIVE PREVIEW

CenterPoint Energy Super Bowl LI Coordination and Hurricane Harvey - - PowerPoint PPT Presentation

CenterPoint Energy Super Bowl LI Coordination and Hurricane Harvey Operational Efforts David Mercado, P.E Real Time Operations Engineering Manager CenterPoint Energy SEPTEMBER 5 - 7, 2018 CenterPoint Energy Overview and Background T&D


slide-1
SLIDE 1

SEPTEMBER 5 - 7, 2018

CenterPoint Energy Super Bowl LI Coordination and Hurricane Harvey Operational Efforts

David Mercado, P.E Real Time Operations Engineering Manager CenterPoint Energy

slide-2
SLIDE 2

SEPTEMBER 5 - 7, 2018

CenterPoint Energy Overview and Background

  • T&D business serves 5,000 square mile Greater Houston area
  • Fourth largest city in US
  • Over 2.4 million meter customers
  • Two challenges will be addressed
  • Preparation efforts prior to Super Bowl LI
  • Hurricane Harvey Operational Efforts
slide-3
SLIDE 3

SEPTEMBER 5 - 7, 2018

Super Bowl XLVII 2013 Power Outage

slide-4
SLIDE 4

SEPTEMBER 5 - 7, 2018

Super Bowl LI Coordination

  • Initial Power System Evaluation
  • Evaluated opportunities to improve the design of key distribution substation

serving NRG stadium

  • Phase 1 - Converted key substation from a single breaker design to a dual

breaker design

  • Phase 2 – Converted substation from a dual breaker design to a four breaker

ring

  • Increased reliability mitigating possibility of complete substation outage due

to breaker failure or transmission line fault

slide-5
SLIDE 5

SEPTEMBER 5 - 7, 2018

Super Bowl LI Coordination

  • Outline Departmental Roles and Responsibilities
  • Developed a Super Bowl coordination committee
  • Representatives from various departments across the company
  • Communications, Corporate Security, Customer Service, Electric Operations,

Gas Operations, Human Resources, Logistics, Technology Operations, and Safety

  • Held regular discussions starting 12 months prior to the Super Bowl event
  • Coordination was also conducted with external entities
  • Federal Department of Homeland Security
  • Local law enforcement
  • City of Houston emergency management
  • NFL and NRG stadium security
slide-6
SLIDE 6

SEPTEMBER 5 - 7, 2018

Examples of Electric Operations Coordination Efforts

  • Distribution Operations
  • Identified and inspected 36 overhead circuits associated with Super

Bowl LI venues

  • Released and completed 25 work orders related to improvements
  • Identified and inspected 34 circuits associated with Super Bowl LI

venues for vegetation management issues

  • Transmission Operations
  • Inspected 138 kV transmission circuits that serve substation feeding

NRG stadium

  • Inspections resulted in the installation of avian protection on seven

transmission structures and one insulator string replacement

slide-7
SLIDE 7

SEPTEMBER 5 - 7, 2018

Examples of Electric Operations Coordination Efforts

  • Major Underground
  • Met with NRG stadium site electricians and contractors to develop

testing procedures for NRG stadium equipment and response to faults

  • Performed VLF (Very Low Frequency) testing on the conductors

feeding NRG stadium

  • Replacement of one pad mount transformer at NRG stadium due to

leaking bushings

  • Installed 30 locking manhole covers in key major underground

locations for increased safety and security

slide-8
SLIDE 8

SEPTEMBER 5 - 7, 2018

Examples of Electric Operations Coordination Efforts

  • Substation Operations
  • Performed infrared testing at substation feeding NRG stadium
  • Performed dissolved gas analysis on both transformers at substation
  • Installed new ballistic fencing around distribution substation feeding

NRG stadium

slide-9
SLIDE 9

SEPTEMBER 5 - 7, 2018

Hurricane Harvey – A Record-breaking Storm

  • 52 inches of rainfall in southeast Texas
  • Harvey made landfall multiple times
  • Category 4 near Port Aransas, Texas
  • Tropical storm in Cameron, Louisiana
  • More than 42,000 lightning strikes
  • Record number of tornado warnings in southeast Texas
  • 17 substation out of service or inaccessible due to high

water

  • 7 transmission lines locked out
  • 293 distribution circuits locked out
slide-10
SLIDE 10

SEPTEMBER 5 - 7, 2018

Operational Action due to Substation Flooding

  • Developed switching plans to bypass substations threatened

by flood water

  • Developed plans in advance for substations prone to flooding
  • Developed plans in real time for substations as risk during Harvey
  • Coordination with System Protection engineers
  • Coordination with Substation personnel

Imminent Flooded Substation Configuration Temporary Bypass Substation Configuration

slide-11
SLIDE 11

SEPTEMBER 5 - 7, 2018

slide-12
SLIDE 12

SEPTEMBER 5 - 7, 2018

Mobile Substation Use

  • Key distribution substation serving densely populated community flooded
  • Mobile Substation installed and power restored to customers with 2

weeks of flooding

  • Various technologies were utilized including drones, amphibious vehicles,

and airboats

slide-13
SLIDE 13

SEPTEMBER 5 - 7, 2018

slide-14
SLIDE 14

SEPTEMBER 5 - 7, 2018

Flooding Impacts on Transmission Towers

  • Various transmission tower foundations along the banks of river crossings

washed out

  • Transmission lines locked out due to contact with rising water
  • Temporary poles were set and power restored
slide-15
SLIDE 15

SEPTEMBER 5 - 7, 2018

slide-16
SLIDE 16

SEPTEMBER 5 - 7, 2018

Hurricane Harvey Video

slide-17
SLIDE 17

SEPTEMBER 5 - 7, 2018

Key Takeaways from Super Bowl and Hurricane Efforts

  • The 5 P’s – Proper Planning Prevents Poor Performance
  • Planning and preparing for Super Bowl readiness resulted in a successful

hosting of the event

  • Advanced preparation and storm hardening minimized impacts from

Hurricane Harvey

  • Learn from past experiences
  • Previous power outages during events like the Super Bowl brought

awareness of the need to prepare and assess system readiness

  • Past storms and flood events helped indicate where vulnerable

substations prone to flooding exists