cement stabilized base chipseal
play

Cement Stabilized Base & Chipseal County Road 54 NRRA Pavement - PDF document

5/24/2017 Cement Stabilized Base & Chipseal County Road 54 NRRA Pavement Conference May 24, 2017 John Brunkhorst, PE - McLeod County Engineer Dave Rettner, PE - American Engineering Testing Inc. CR 54 CSFDR NRRA Presentation 1


  1. 5/24/2017 Cement Stabilized Base & Chipseal “County Road 54” NRRA Pavement Conference May 24, 2017 John Brunkhorst, PE - McLeod County Engineer Dave Rettner, PE - American Engineering Testing Inc. CR 54 CSFDR NRRA Presentation 1

  2. 5/24/2017 T o pic s 1. Background 2. Project Overview 3. Construction Highlights 4. Design Process 5. Construction and Performance Testing 6. Costs 7. Lessons Learned 8. Next Steps CR 54 CSFDR NRRA Presentation 2

  3. 5/24/2017 Where is McLeod County? Located approximately 60 miles west of the Twin Cities CR 54 CSFDR NRRA Presentation 3

  4. 5/24/2017 Where is Project? County Road 54 (CR 54) ~ 6 miles South of Hutchinson, MN PROJECT LOCATION Length: ~1 mile CR 54 CSFDR NRRA Presentation 4

  5. 5/24/2017 BAC KG RO UND County Road 54 • Gravel Road • Primarily serves rural housing development • Seasonal agricultural traffic • ~ 200 ADT • County Funded (non State Aid route) CR 54 CSFDR NRRA Presentation 5

  6. 5/24/2017 BAC KG RO UND CR 54 Issues • ~$5,000 Annually for Dust Control (CaCl 2 ) • Washboards (due to speed/braking) • Frequent Blading Required • No Funding for traditional base and surfacing Goals for CR 54 • Dust Free Road • Washboard Free • Stand up to Agricultural Traffic • Cost Effective CR 54 CSFDR NRRA Presentation 6

  7. 5/24/2017 BAC KG RO UND – Pa st Effo rts 2014 Prime/Seal Project • CR 54 • Township Housing Development • Nearby County Park • Portions of CR 54 began to break up in fall 2015 Reclamation & Tiling Project • CR 54 CR 54 CSFDR NRRA Presentation 7

  8. 5/24/2017 NO W WHAT ? CR 54 CSFDR NRRA Presentation 8

  9. 5/24/2017 2016 Cement Stabilized Full Depth Reclamation (CSFDR) Double Chip Seal & Fog Seal Project Goal – Find the most cost effective optimal cement content and stabilization depth. • 4 Test Sections • Varying Cement Contents • Varying Stabilization Depths • Short Section of Single Chip Seal • 4% Cross Slope CR 54 CSFDR NRRA Presentation 9

  10. 5/24/2017 PRO JEC T O VERVIEW Section 1 Section 2 Section 3 Section 4 Cement Content 8 % 7 % 6 % 5 % Stabilization Depth 10” 10” 8” 8” Tack Coat 1300’ 1300’ 1300’ 1300’ Double Chip Seal 1300’ 1300’ 1300’ 1200’ Single Chip Seal - - - 100’ Fog Seal 1300’ 1300’ 1300’ 1300’ CR 54 CSFDR NRRA Presentation 10

  11. 5/24/2017 C O NST RUC T IO N Spreading Cement CR 54 CSFDR NRRA Presentation 11

  12. 5/24/2017 C O NST RUC T IO N Spreading Cement CR 54 CSFDR NRRA Presentation 12

  13. 5/24/2017 C O NST RUC T IO N Cement Incorporation CR 54 CSFDR NRRA Presentation 13

  14. 5/24/2017 C O NST RUC T IO N Cement Incorporation CR 54 CSFDR NRRA Presentation 14

  15. 5/24/2017 C O NST RUC T IO N Cement Incorporation CR 54 CSFDR NRRA Presentation 15

  16. 5/24/2017 C O NST RUC T IO N Breakdown Rolling CR 54 CSFDR NRRA Presentation 16

  17. 5/24/2017 C O NST RUC T IO N Breakdown Rolling CR 54 CSFDR NRRA Presentation 17

  18. 5/24/2017 C O NST RUC T IO N Initial Blading CR 54 CSFDR NRRA Presentation 18

  19. 5/24/2017 C O NST RUC T IO N Finish Rolling CR 54 CSFDR NRRA Presentation 19

  20. 5/24/2017 C O NST RUC T IO N Finish Rolling & Final Trimming CR 54 CSFDR NRRA Presentation 20

  21. 5/24/2017 C O NST RUC T IO N Final Trimming CR 54 CSFDR NRRA Presentation 21

  22. 5/24/2017 C O NST RUC T IO N Finished CSFDR CR 54 CSFDR NRRA Presentation 22

  23. 5/24/2017 C O NST RUC T IO N Finished CSFDR CR 54 CSFDR NRRA Presentation 23

  24. 5/24/2017 C O NST RUC T IO N Seal Coat – Broom prep CR 54 CSFDR NRRA Presentation 24

  25. 5/24/2017 C O NST RUC T IO N Tack Coat CR 54 CSFDR NRRA Presentation 25

  26. 5/24/2017 C O NST RUC T IO N Seal Coat – First Layer CR 54 CSFDR NRRA Presentation 26

  27. 5/24/2017 C O NST RUC T IO N Seal Coat – Second Layer CR 54 CSFDR NRRA Presentation 27

  28. 5/24/2017 C O NST RUC T IO N Seal Coat – Second Layer CR 54 CSFDR NRRA Presentation 28

  29. 5/24/2017 C O NST RUC T IO N Fog Seal (sorry no pics  ) 8/23/16 CR 54 CSFDR NRRA Presentation 29

  30. 5/24/2017 DESIG N PRO C ESS • Two mix designs • One for 8 inch SFDR section, one for 10 inch SFDR section • Relative proportions of gravel to subgrade were different due to reclamation depths • 8” Section Proctor 127.3 pcf at 9.1% moisture • 10” Section Proctor 122.6 pcf at 10.5% moisture • Target Unconfined Compressive Strength of 250-300 psi at 14 days CR 54 CSFDR NRRA Presentation 30

  31. 5/24/2017 DESIG N PRO C ESS • Two mix designs • 8” Section • 5% Cement Content at OMC • 272 psi UCS • 10” Section • 7% Cement Content at OMC • 267 psi UCS CR 54 CSFDR NRRA Presentation 31

  32. 5/24/2017 DESIG N PRO C ESS • After lab work was completed the roadways were graveled and graded, so the roadway had more gravel than the mix designs contained. • Likely result was going to be higher strength than the original mix design CR 54 CSFDR NRRA Presentation 32

  33. 5/24/2017 C O NST RUC T IO N & PERFO RMANC E T EST ING • Field Testing • Nuclear Gauge for Moisture and Density • Water was added to soil as necessary to achieve (or approach) optimum moisture content • Rolling Patterns were performed • Several Each Day to account for variability in the roadway materials • Density and moisture was checked during compaction • Density was typically >98% of rolling pattern density CR 54 CSFDR NRRA Presentation 33

  34. 5/24/2017 C O NST RUC T IO N & PERFO RMANC E T EST ING • Field Testing • DCP testing was performed post construction for strength verification • Target strengths (minimums) • CBR of 20 in 2 days • CBR of 50 in 7 days • Strengths measured greatly exceeded the targets CR 54 CSFDR NRRA Presentation 34

  35. 5/24/2017 C O NST RUC T IO N & PERFO RMANC E T EST ING CR 54 CSFDR NRRA Presentation 35

  36. 5/24/2017 C O NST RUC T IO N & PERFO RMANC E T EST ING • Performance Testing • Ground Penetrating Radar • Falling Weight Deflectometer • IRI • Performed October, 2016 CR 54 CSFDR NRRA Presentation 36

  37. 5/24/2017 C O NST RUC T IO N & PERFO RMANC E T EST ING • GPR - Sections were constructed thicker than plan • 10 inch sections • Section 1 – 14.5 inches • Section 2 – 14.6 inches • 8 inch Sections • Section 3 – 11.1 inches • Section 4 – 10.1 inches CR 54 CSFDR NRRA Presentation 37

  38. 5/24/2017 C O NST RUC T IO N & PERFO RMANC E T EST ING • FWD Results • Significant strength increase over non-stabilized roadway – all stabilized sections > 10 tons • No direct correlation between cement content and strength Load Length Thickness Modulus Section Capacity feet in. ksi tons/axle South Gravel 1300 4.8 16.7 4.8 1 1300 14.5 362.1 20.0 2 1300 14.6 560.9 21.8 3 1300 11.1 438.6 19.0 4 1300 10.1 280.4 10.8 North Gravel 1300 7.6 16.4 5.4 CR 54 CSFDR NRRA Presentation 38

  39. 5/24/2017 C O NST RUC T IO N & PERFO RMANC E T EST ING • Ride Quality Results • IRI of stabilized sections was significantly higher than the unstabilized gravel roadway on both ends of the project Length IRI Section feet in./mi. South Gravel 1300 84.8 1300 293.2 1 2 1300 237.4 3 1300 204.4 4 1300 210.9 1300 149.6 North Gravel CR 54 CSFDR NRRA Presentation 39

  40. 5/24/2017 C RAC K SURVEY - SPRING 2017 CR 54 CSFDR NRRA Presentation 40

  41. 5/24/2017 C RAC K SURVEY - SPRING 2017 CR 54 CSFDR NRRA Presentation 41

  42. 5/24/2017 C RAC K SURVEY - SPRING 2017 CR 54 CSFDR NRRA Presentation 42

  43. 5/24/2017 C RAC K SURVEY - SPRING 2017 Transverse Longitudinal Cracks Cracks Section 1 28 3 Section 2 43 12 Section 3 41 6 Section 4 35 7 CR 54 CSFDR NRRA Presentation 43

  44. 5/24/2017 SPRING 2017 1 Year Old CR 54 CSFDR NRRA Presentation 44

  45. 5/24/2017 SPRING 2017 1 Year Old CR 54 CSFDR NRRA Presentation 45

  46. 5/24/2017 SPRING 2017 1 Year Old CR 54 CSFDR NRRA Presentation 46

  47. 5/24/2017 C O ST S CSFDR Cost/Mile Cost/SY • Cement $ 51,300 $ 3.12 • Stabilization $ 16,300 $ 0.99 • Laydown/Compaction * $ 15,000 $ 0.93 CHIP SEAL • Tack Coat $ 3,100 $ 0.19 • 3/8” Seal $ 22,900 $ 1.40 • 1/4” Seal $ 20,000 $ 1.22 • Fog Seal $ 3,300 $ 0.20 TOTAL ~$ 132,000 ~$ 8 * County Roller Operators CR 54 CSFDR NRRA Presentation 47

  48. 5/24/2017 L ESSO NS L EARNED Ride • Finish longer sections • Tough to correct after project • Likely include Ride Spec in Future CR 54 CSFDR NRRA Presentation 48

  49. 5/24/2017 L ESSO NS L EARNED Subgrade • Need Good Drainage • Continue Centerline Tile Residential Driveways • Figure out Transition • Potential Plowing Damage Future Projects • No County Operators, One Contract • Ensure Samples Match Existing Conditions 2 nd Seal – Year 2 or later • CR 54 CSFDR NRRA Presentation 49

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend