BERRIMA CEMENT > Community Meeting 27 July 2017 Berrima Cement - - PowerPoint PPT Presentation

berrima cement
SMART_READER_LITE
LIVE PREVIEW

BERRIMA CEMENT > Community Meeting 27 July 2017 Berrima Cement - - PowerPoint PPT Presentation

Build something great BORAL BERRIMA CEMENT > Community Meeting 27 July 2017 Berrima Cement Works Berrima Agenda Welcome and introductions, safety moment Previous meeting and matters arising Boral Cement and Berrima Cement


slide-1
SLIDE 1

Build something great™

> Community Meeting

BORAL BERRIMA CEMENT

27 July 2017 Berrima Cement Works Berrima

slide-2
SLIDE 2

Agenda

˃

Welcome and introductions, safety moment

˃

Previous meeting and matters arising

˃

Boral Cement and Berrima Cement Works update

˃

Fuelling the Future: Solid Waste Derived Fuels Implementation

˃

Environmental monitoring and update

˃

Community activities and general business

slide-3
SLIDE 3

Introductions and safety moment

˃

Stuart Hutchings Operations Manager (NSW), Boral Cement

˃

Belinda Prideaux Environment Manager, Boral Cement

˃

Michael Curley Health Safety Environment Advisor, Boral Berrima Cement

˃

Madeline Westnidge Administration, Boral Berrima Cement Works

˃

Paul Jackson Stakeholder Rels Mgr (NSW/ACT and National Land Development), Boral Property

˃

Safety moment – Automated Rail Points Project

˃ https://vimeo.com/226255363/f586e24414

slide-4
SLIDE 4

Previous meeting and matters arising

˃

Previous community meeting

˃ 10 November 2016 ˃ Note: Presentations from previous meetings are available from the Cement Works website –

www.boral.com.au/berrimacement

˃

Any matters arising?

˃

Apologies for this meeting

slide-5
SLIDE 5

Build something great™

> Boral Cement and

Berrima Cement Works update

BORAL BERRIMA CEMENT

slide-6
SLIDE 6

Berrima Cement Works update

˃

Berrima had another outstanding year (FY16-17) in terms of clinker and cement production.

˃ Clinker production record for second straight year – just under 1.5 million tonnes produced ˃ Cement sales continued to be strong leading to highest weekly cement production in years

˃

Safety performance continued to improve across the year but there was one LTI.

˃ Operator’s finger injured while cleaning a chute ˃ Safety remains a key focus at site

˃

Major kiln shutdown – January 2018.

˃ Expected to take 23 days to complete

˃

Personnel changes

˃ New Maintenance Manager, Joao Nunes,

commenced at Berrima in Sep 2016.

˃ Currently recruiting for a new Production Manager

after internal promotion.

slide-7
SLIDE 7

New Berrima Road Overpass

˃

Council is implementing plans for a new overpass connecting Taylor Ave and Berrima Rd.

˃ We are finalising the relevant land access and acquisition agreements with Council to allow

construction to begin

˃ The new bypass will significantly improve traffic flow and eliminate rail/road interaction. ˃ The existing high volume air sampler (HVAS) situated between the cement works and Inghams

will need to be relocated.

slide-8
SLIDE 8

Stakeholder Perception Benchmark

˃

During this financial year (2017-18), we will be conducting an SPB for Berrima

˃ SPB is our award winning process for verifying the environmental and community performance of

a site by gathering feedback from neighbours

˃ Random selection of sites throughout Australia are subjected to SPBs in each FY

˃

The SPB process involves pre-notification followed by collection of feedback through various channels dependant on the site’s circumstances.

˃ Pre-notification usually by letter to all premises within footprint ˃ Feedback collection via combination of in-person visits, phone and online means

˃

The gathered information is used to both develop the subject site’s community engagement activities and to highlight operational issues of concern.

˃ Site Stakeholder Engagement Plans are framed

around the comments given through an SPB

˃ SEPs are part of the operational process of

sites, so identified priorities must be addressed

˃

We have not yet identified the timing of the SPB’s conduct

˃ However we will share the results with you at the

next community meeting.

slide-9
SLIDE 9

> Fuelling the Future:

Solid Waste Derived Fuels Implementation

BORAL BERRIMA CEMENT

Build something great™

slide-10
SLIDE 10

Solid Waste Derived Fuels (SWDF)

˃

At our last meeting in November, we announced that the NSW Department of Planning and Environment (DPE) had approved our modification for SWDF.

˃

To recap, the approval permits the following:

˃ Use of up to 100 000 tonnes per year of wood-waste derived fuel (WWDF) and refuse-derived

fuel (RDF) for the kiln’s energy needs, replacing equivalent amount of coal

˃ Amended air emissions limits ˃ Construction of a storage and feed system to allow SWDFs to be integrated into production

˃

The project represents an $11.3 million investment in the Berrima site.

˃ Supported by a $4.08 million grant from the NSW Environment Trust Waste Less, Recycle More

initiative

˃ Will substantially assist in reducing energy costs

and therefore cost of production, increasing long- term viability of the site.

slide-11
SLIDE 11

Recap – what is WWDF and RDF?

Wood waste-derived fuel (WWDF) Refuse-derived fuel (RDF)

‘Leftovers’ from other industries Untreated waste like sawdust, pallets, chipped bark, mill off-cuts NOT commercial or native forestry material Combustible materials recovered from ‘mainstream’ waste Papers, cardboards, packaging, some plastics, C&D material Screened and processed to specification

X

slide-12
SLIDE 12

We’re now ready to build!

Multiflex feeder Tube conveyor Auto grab crane Aeration High temperature slide gate Loading bins

Access & delivery

Calciner Receiving and storage shed Supports

slide-13
SLIDE 13

Construction schedule

˃

We recently updated our construction schedule which has seen some works already get underway:

˃ Site preparation and civil works have already started ˃ Sep 2017: Construction of storage building begins ˃ Oct 2017: Overseas-supplied kit delivery – pipe conveyor and supports ˃ Oct 2017: Mechanical installation of equipment begins ˃ Apr 2018: Commissioning of plant and equipment ˃ May 2018: Performance testing and final commissioning ˃ Jun 2018: Plant handover

˃

Between six and 30 construction personnel will be involved in the project at different times throughout the schedule.

˃ Where possible, manufacture and assembly will

  • ccur away from Berrima site before installation

˃ Local suppliers to be used where we can

slide-14
SLIDE 14

Construction details

˃

Due to the location of the project at the rear of the Cement Works, we expect there will be no discernible difference to normal operations.

˃

Construction hours will be

˃ Mon-Fri: 7am until 6pm ˃ Sat: 7am until 1pm ˃ No construction is allowed on Sundays or public holidays if the construction noise is audible at

  • ur site boundary

˃

The sequenced stages of the construction schedule include:

˃ Civils and earthworks: earthmoving, pouring of

slabs and foundations

˃ Materials store and Reception building: built off-

site, fitting pieces together, services connection

˃ Installation of ‘grab’ crane: built off-site, install

moving floor hopper, crane and electricals

˃ Installation of materials handling equipment:

tube conveyors, bin feeders, multiflex

˃ Electrical, control and instrumentation: cabling,

switchroom, light and power

˃ Some transport movements out of the

normal might be noticeable at times (eg concrete agitators)

˃ Preconstruction: set up site office, fencing, arrange utilities supply to project site

slide-15
SLIDE 15

Communication

˃

The SWDF project presents Berrima with an exciting opportunity to showcase technological ability and innovation, all achieved with your assistance.

˃

Accordingly, we’ll be sharing our progress regularly through the schedule with you:

˃ Tracking against schedule, major milestones, advance notice of activity (eg additional transport

movements) which may be noticeable outside site, first testing of SWDFs and your feedback, reports to authorities

˃ Information will be supplied by the Project Team, Berrima site management and Boral’s

Stakeholder Relations Manager.

˃ All regular channels will be used: usual community meetings, newsletter, Cement Works website,

local media editorial and advertorial, potential site inspection events (during and post)

˃

As usual, we will seek your ongoing feedback so that we can adjust either our works or communications to suit you.

˃

If you have a complaint or concern:

˃ Call the Cement Works on 4860 2222 (voicemail) ˃ Call Boral Stakeholder Relations on 0401 894 097 ˃ Email feedback@boral.com.au ˃ All complaints will be entered into the Boral SIMS

system and actioned as swiftly as possible – please get in touch as soon as the issue

  • ccurs!
slide-16
SLIDE 16

> Environmental monitoring and

update

BORAL BERRIMA CEMENT

Build something great™

slide-17
SLIDE 17

Licence Year 1/5/2016 – 30/4/2017

˃

Noise Monitoring

˃ Extensive (annual) noise monitoring undertaken ˃ Conclusion that we were compliant with our licencing noise requirements ˃ Recommendation to review a number of noise sources:

slide-18
SLIDE 18

Licence Year 1/5/2016 – 30/4/2017

˃

Stack Monitoring Solid Particulates and NOx Cadmium, mercury and hazardous substances

slide-19
SLIDE 19

Licence Year 1/5/2016 – 30/4/2017

˃

Dust Deposition Gauges

slide-20
SLIDE 20

Licence Year 1/5/2016 – 30/4/2017

˃

Ambient Air Monitoring Program - HVAS PM10, TSP Heavy Metals

slide-21
SLIDE 21

Licence Year 1/5/2016 – 30/4/2017

˃

Lake Quality Overflow Data Potassium, BOD, pH TSS, COD, Sulphate, Chloride, Sodium, Calcium

slide-22
SLIDE 22

Licence Year 1/5/2016 – 30/4/2017

˃

Lake Quality Overflow Data (2) Aluminium, Flouride, Oil and Grease Zinc, Nickel, Copper, Boron, Barium, Cyanide, TP

slide-23
SLIDE 23

Recent activities

˃

Pest Control

˃ Team of people monitoring rabbit population ˃ Recent virus release affecting pests ˃ Plans in place to supplement recent virus release if not

adequate

˃ People trained in the use of poisons

˃

Dust Collectors

˃ Consultant engaged to assist with providing

expertise

˃ Increased focus on DCs across site ˃ Increased focus on known issues ˃ People trained in the use of poisons

slide-24
SLIDE 24

Reminder – Pollution Incident Response Register

˃

Our obligations under the NSW Protection of the Environment Act 1997 require us to have procedures for notifying the community if a ‘pollution incident’ occurs.

˃ Examples include significant oil or hydrocarbon spills, release of high volumes of alkaline

water, fires and/or significant smoke

˃

Part of the procedures includes establishing a register of neighbour’s contact details to be used for such notification.

˃ Started in 2013, all details kept secure and not used for other purposes

˃

Please let us know if you’d like to be included in this register (or have your details updated)

˃ Open to those living within a one kilometre

radius of the site only.

˃ Register landline, mobile and/or email

addresses at your preference

˃ Call the site on 4860 2222 or email

feedback@boral.com.au

slide-25
SLIDE 25

Build something great™

> Community activities and

general business

BORAL BERRIMA CEMENT

slide-26
SLIDE 26

Change to community meeting regime

˃

As part of Berrima’s planning consent, we are required to establish and manage a Community Liaison Group (CLG).

˃ Purpose is to act as a two-way communication channel between residents and Boral, sharing

information as well as identifying and recommending solutions to matters of concern.

˃ Is to include representatives from Boral, Council and up to four community members

˃

The NSW Department of Planning and Environment introduced new guidelines for Community Consultation Committees in November which means we need to make changes.

˃ Until now, our open community meetings have been our way of meeting this requirement ˃ With the new guidelines, we need to properly constitute a CLG going forward

˃

The CLG is an independently chaired forum which will meet at least twice a year to review and discuss the same things as we do at the existing meetings.

˃ Up to seven community representatives may be

part of the CLG

˃ Membership is via an expression of interest to the

independent Chair who then makes the selection

˃ Boral and Council selects its own representatives ˃ Members sign a Code of Conduct and must

declare interests before joining the CLG

slide-27
SLIDE 27

Change to community meeting regime

˃

Following this meeting, we will begin the process of transitioning to this new arrangement.

˃ We will write to the DPE to request allocation of an independent Chair ˃ Once the Chair is identified, we will work with them per the guidelines to recruit community

representatives (advertising and general promotion)

˃ We will ensure all of our ‘regulars’ are updated with activities as they occur

˃

Recognising that joining a formal committee is not for everyone, and the valuable contribution made through our ‘open’ community meetings until now, we are also going to voluntarily hold a ‘whole of community’ meeting each year.

˃ WoC meetings will run as per our existing meetings – open to everyone, Boral to chair ˃ Will be held at the start of each new financial year (Jul-Aug) so we can review the previous year’s

activities and the new year’s plans

˃ Extra WoC meetings will be arranged if important

matters come up, or if the community requests

  • ne.

˃

We are making our voluntary WoC commitment because we believe it is needed to keep all locals connected with

  • ur operations. Thanks to you for your
  • ngoing interest and participation!
slide-28
SLIDE 28

Community activities

˃

Since our last meeting, the following community projects have been given support through the Cement Works’ community engagement program:

˃ Berrima Townlife: Berrima Carols by Candellight (Dec 16) ˃ Bundanoon Public School: Garden seating project (Feb 17) ˃ Moss Vale Chamber of Commerce: Moss Vale Buskers Battle (Feb 17) ˃ Southern Highlands Science & Engineering Challenge: S&EC Discovery Day (Mar 17) ˃ Hill Top Soccer Club (Mar 17) ˃ Southern Stars Baseball Club (Aug 17 – year two of three year sponsorship) ˃ Harper’s Mansion: Berrima Plant & Garden Fair (Oct 17) ˃ Southern Highlands Business Awards (Oct 17)

slide-29
SLIDE 29

General business and contacts

˃

Items of general business

˃

Next meeting

˃ Will be dependant on progress with transitioning to the CLG arrangements ˃ First ‘Whole of Community’ meeting will be Jul-Aug 2018 regardless

˃

Boral Berrima Cement contacts:

˃ Berrima Cement Works Reception

4860 2222 / madeline.westnidge@boral.com.au

˃ Paul Jackson Stakeholder Relations Manager

4677 2946 / 0401 894 097 / paul.jackson2@boral.com.au

˃ www.boral.com.au/berrimacement ˃ feedback@boral.com.au

slide-30
SLIDE 30

Build something great™

BORAL BERRIMA CEMENT

> Thank you for your attendance