ultratech cement limited unit reddipalayam cement works
play

ULTRATECH CEMENT LIMITED (UNIT: REDDIPALAYAM CEMENT WORKS) 18 th - PowerPoint PPT Presentation

ULTRATECH CEMENT LIMITED (UNIT: REDDIPALAYAM CEMENT WORKS) 18 th National Award for Excellence in Energy Management- 2017 30- Aug 2017 to 01-Sep 2017 , Hyderabad. Team Members: Mr. Praveen Kumar (HOD TS & WCM) Mr. S.Saravanan ( HOD


  1. ULTRATECH CEMENT LIMITED (UNIT: REDDIPALAYAM CEMENT WORKS) “ 18 th National Award for Excellence in Energy Management- 2017” 30- Aug 2017 to 01-Sep 2017 , Hyderabad. Team Members: Mr. Praveen Kumar (HOD TS & WCM) Mr. S.Saravanan ( HOD Project) 1

  2. UltraTech Cement Ltd Overview Location of Integrated Plants, Grinding Units and Bulk Terminals Number of Units Symbol Units Bathinda Cement Works Panipat Cement Works Dadri Cement Works Integrated Jhajjar Cement Works Aligarh Cement Works 18 Plants Kotputli Cement Works Aditya Cement Grinding Units 25 Patliputra Cement Works Wanakbori Cement Vikram Cement West Bengal Cement Works Works Sewagram Cement Works Hirmi Cement Works Dankuni Cement Works Bulk Terminals 7 Gujarat Cement Works Magdalla Cement Works Jharsuguda Cement Works Jafrabad Cement Works Awarpur Cement Works Magdalla Terminal RWCW Navi Mumbai Cement Unit Hotgi Cement Works Area of spread (RDCW) RDCW Unit Shankarapally Bulk Terminal Ratnagiri Cement Works Rajashree Cement Works Plant capacity 1.6 MTPA Andhra Pradesh Cement Works Ginigera Cement Works Area of mines 188.62 Ha Mangalore Cement Unit Arrakonam Cement Works Integrated plant BSBT- Dodballapur Area of plant 125 Ha Grinding unit Bulk terminals Trichy Reddipalayam Cement Works Nearest air port (75 km) Cochin Bulk Terminal 2

  3. CEMENT – MANUFACTURING PROCESS 3

  4. MILESTONES 3294 TPD 3250 TPD FY2016-17 3150 TPD Apr 2012  By continuous 3000 TPD improvement & Sep 2006 optimization 2800 TPD  Preheater upgraded Jun 2004 from IV to V stage 2400 TPD  Cooler up gradation Feb 2003  GCT vessel height increased 1800 TPD  Three cooler fans replaced with high Apr 2002 efficiency fans  Kiln speed  Modified Pre-heater twin cyclone Aero- increased from 3.2 Feb 2000 vane to 5.5 RPM  Kiln Inlet  Clinker breaker Upgradation  TA duct dia modification  New Plant increased from 2.1  Kiln feed bucket Commissioned M to 2.5 M elevator speed  Cooler grate area increased from increased from 1.5 to 1.7m/Sec 52m2 to 72m2 4

  5. UNIQUE FEATURES  State of the art Cement Plant commissioned in the millennium year 1 st Unit in UTCL having Robo lab for total quality control from sampling to  analysis  State of art testing laboratory for Alternative fuels  Designed for using multiple fuels  Pioneer in using alternate fuel with pre-processing system  Pioneer in Using alternate raw material (ETP Sludge)  First Plant in the World to get CDM credit for use of Agro waste alternate fuel  Packing facility with Centralized discharge from cement silo  No fatal accident since last 15 years 5

  6. MANAGEMENT SYSTEMS ISO :27001 ISMS ISO :50001 EnMS ISO : 9001 - Quality ISO :18001 -Safety ISO :14001 Environment 6

  7. Management System - Certification ISO 50001:2011 CII Green Co - Gold Certification Energy Management 7

  8. Management System • Energy Policy implemented in Dec – 2013 • Energy Policy states unit’s commitment to achieving energy performance improvement • Energy policy is communicated at all levels. • Energy policy is regularly reviewed. Next review of energy policy : Jan -2018 8

  9. Energy consumption 9

  10. Reduction in specific energy consumption AFR Substitution % TSR 12-13 8.34 Kcal/kg equivalent Cement 9.60 13-14 9.62 14-15 10.94 15-16 746 800 733 715 13 724 16-17 689 691 700 16.11 676 17-18 Q1 658 Better 616 600 Fly ash addition in PPC 13-14 26.89 14-15 500 27.79 15-16 28.47 16-17 30.61 17-18 Q1 31.55 Total 3554 No's of EScerts credited for PAT cycle-1 10

  11. Specific Power Consumption – kWh/MT Cement 80 72 71 72 67 70 65 64 Better 60 50 CII National 2012-13 2013-14 2014-15 2015-16 2016-17 Benchmark 12

  12. Energy saving Projects 13

  13. Methodology for Identification of Improvement Projects Suggestion Opportunity Identification • Energy Mapping • Idea Generation • Benchmarking Results Achieved Team formation Project execution • Idea Screening Rewards • Lost Cost Matrix & & • Feasibility Study & • OEE & VOC Allocation of project team Recognition Review of Progress 14

  14. Action Plan to Achieve PAT cycle – II Target Energy Consumption Annual Energy saving Date of (TOE) Investme completion of Sr. No. Energy efficiency improvement measures nt Rupees measure/ likely Before Coal in Lacs After Electricity completion Measures (Tonne) Measures (kWh) Pressure drop reduction in Preheater 4th stage 1 14 completed 1067 1016 583680 cyclone Reduction of pressure drop through junction box & 2 32 Completed 176 166 109440 duct modification at RM ESP Replace CFL lamps,HPSV lamps and Tube lights 3 10.6 Completed 8.39 4.94 40171 with LED lamps Installation of Aerzen Turbo blower for Kiln coal 4 34.89 Mar-18 32 21 124032 firing in place of existing Twin lobe blower 5 Substitution of alternate fuel from 11 % to 15% 45 Completed 48621 48370 321 6 To enhance fly ash addition up to 30% 124 Completed 60639 60342 151614 364 7 Replacement of HVMP lamps with LED in TPP 3 Completed 138 119 224400 8 VFD for BF pump in TPP 25 Mar-18 175 161 163200 9 Overhauling of TG in TPP 70 Mar-18 25851 25753 196 10 Heat recovery from rotary kiln 100 Mar-18 33978 33880 196 Total 242186 241239 15

  15. Increasing Alternate Fuel Consumption Purpose : To increase the thermal substitution rate from 10 % to 25% Al ternate Fuel Challenges Types of Industrial waste Moisture Size (mm) % of Usage used in RDCW (%) Carbon Powder 0.91 16 FMCG 33 4 Foot ware 0.82 4 Ballast Inhomogen Size Circulation (Cl, (Water, Ash) eous variation S, alkali ) Paint Sludge 32 400 7.8 Plastics 53 68 Plugging Poor High heat Spent Carbon 40 0.18 Combustion consumption Technical Approach : Poor availability Production loss  Granulometry of AF improved after double shredding  Spike rollers installed in hopper discharge chute to improve Increase in OEE down Poor clinker the flowability production cost quality  Optimizing AF feed bucket elevator speed to improve output. 16

  16. Installation of Multi purpose Shredder Purpose: Shredder Machine Capacity enhancement of Alternate fuel feeding system through size reduction. Technical Approach:  Installed Multi-purpose shredding machine  Double shredding of Alternate fuels Investment: Rs.77.05 Lac Savings : Rs. 158.37 Lac Benefits : Size reduction from 500 MM to 50 MM (Plastic, HDPE bags, Tarpaulin, Foot wear waste, Agro waste, wood and other miscellaneous waste. Shredded HDPE bags & Tarpaulin 17

  17. Increasing Alternate Fuel Consumption Shredder Machine 12-13 8.34 9.60 13-14 9.62 14-15 TSR % 10.94 15-16 13 16-17 Alternate Fuel - Samples 16.11 17-18 YTD… 6 8 10 12 14 16 18 Carbon powder feeding system 18

  18. Year Wise Energy Saving Projects Implemented 19

  19. Summary of Energy saving Initiatives ( FY 2013 to 2017) Year of Total Annual Energy Sl No Number of projects Savings In Rs Million Implementation Savings TOE 1 2013-14 14 4.61 81.42 2 2014-15 5 2.15 41.17 3 2015-16 6 3.25 66.62 4 2016-17 10 9.51 1306.96 Total 35 19.52 1496.17 20

  20. Energy saving Initiatives Energy Annual Savings Year Title of Energy Saving project saving Rs (Million) (MTOE)  Optimization of the instrument air compressor operation (Captive 0.11 2.37 Power Plant)  Installation of transparent sheet in workshop 0.03 0.60  Optimization of suction of raw meal silo top bag filter fan 0.12 2.47  Optimization of ESP Transport group running operation 0.15 3.20  Optimization of GCT Transport group running operation 0.32 6.58 2013-14  No water flow through idle equipment (stoppage of the cooling water 0.05 1.05 pump with Interlock)  Reduction in pressure drop across cement mill vent fan inlet 0.11 2.32 damper(by removal of suction Damper)  Optimization for the operation of cement silo top air slide fans 0.10 2.03  Upgradation of CCR building centralized air conditioning system 0.86 17.83 21

  21. Energy saving Initiatives Annual Savings Energy saving Year Title of Energy Saving project Rs (Million) (MTOE)  Replacement of aluminum blades with FRP blades for cooling tower fan 0.003 0.07  Minimization of compressed air leakage in ash conveying area 0.003 0.07 2013-14  Optimization of the operating frequency of generators 2.44 36.31  Optimization of the operation of DG distribution transformer 0.02 0.39  Optimization of the Voltage distribution in transformer TR3 & 5 0.30 6.14 22

  22. Energy saving Initiatives Annual Savings Energy saving Year Title of Energy Saving project Rs (Million) (MTOE)  Replacement of HPMV lamps with CFL lamps in Packing plant section 0.03 0.48  Unloading of Fly ash through blower air instead of compressed air 1.15 21.93 2014-15  Replacement of HPMV lamps with CFL lamps in CPP section 0.02 0.44  Upgradation of ESP control panel for Coal mill ESP 0.22 4.16  Upgradation of ESP control panel for Raw mill ESP 0.74 14.17  Installation of VFD in 1st RO HP pump 0.16 3.19  Installation of VFD in TPP Drag Chain Feeder 0.02 0.41 2015-16  Optimization in coal unloading & operation of crushing 0.30 6.17  Installation of Turbo Blower for PC firing 1.00 20.50 1.76 36.06  Kiln Auxiliary power reduction 23

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend