Celtic Interconnector Connecting Ireland to Continental Europe - - PowerPoint PPT Presentation

celtic interconnector
SMART_READER_LITE
LIVE PREVIEW

Celtic Interconnector Connecting Ireland to Continental Europe - - PowerPoint PPT Presentation

Celtic Interconnector Connecting Ireland to Continental Europe Presentation to Engineers Cork, 13/11/2018 Eoghan Tuite, CEng Who are EirGrid? EirGrid is the Transmission System Operator (TSO) and is responsible for ensuring a safe,


slide-1
SLIDE 1

Connecting Ireland to Continental Europe

Presentation to Engineers Cork, 13/11/2018 Eoghan Tuite, CEng

Celtic Interconnector

slide-2
SLIDE 2

Who are EirGrid?

  • EirGrid is the Transmission System

Operator (TSO) and is responsible for ensuring a safe, secure and reliable supply of electricity, across the island

  • f Ireland – now and in the future.
  • We develop, manage and operate the

electricity transmission grid.

  • We are mandated to explore and

develop opportunities to interconnect the Irish transmission system with

  • ther systems.
  • EirGrid developed the East West

Interconnector.

slide-3
SLIDE 3

East West Moyle

Celtic

Celtic Interconnector Project

slide-4
SLIDE 4

Project Elements

slide-5
SLIDE 5

Project Partner

slide-6
SLIDE 6

Project Benefits

slide-7
SLIDE 7

Competition

WHOLESALE BASELOAD ELECTRICTY PRICES Second Quarter of 2018

Facilitates increased electricity trading & downward pressure

  • n cost of electricity.
slide-8
SLIDE 8

Security of Supply

Additional supply of power and increased diversification

  • f fuel sources.
slide-9
SLIDE 9

Sustainable Energy

Facilitates transition to low carbon future.

slide-10
SLIDE 10

Telecoms

Strategic

  • pportunity to

provide a direct fibre link to Europe

Source: Telegeography, Analysys Mason

slide-11
SLIDE 11

Image: E-Highway2050

European Context

slide-12
SLIDE 12

Funding

  • Proposal made to both National

Regulatory Authorities (CRU & CRÉ) on cost split between EirGrid and RTE.

  • Connecting Europe Facility:

– EU funding instrument for targeted infrastructure investment. – Celtic has received grant of €3.6m and allocated further €4m to date. – Budget of €4.7bn for grants for energy projects up to 2020.

slide-13
SLIDE 13

Strategic Imperative

  • Allows Ireland directly contribute

to, and be part of, Energy Union.

  • Reduces Ireland’s electrical

isolation (below EC’s targets and thresholds for Interconnection).

– Average yearly price difference > €2/MWh. – Interconnection capacity is < 30% of peak load. – Interconnection capacity is < 30% of installed renewable generation.

Green: meets all three thresholds Yellow: meets two of the thresholds Red: meets one or none of the thresholds

slide-14
SLIDE 14

Project Roadmap

2011 - 2014 Contract Award Manufacturing Energisation Preliminary Feasibility Construction Benefits Technology Costs Timetable EirGrid / RTE Project Work Streams Phase Description 2021 – 2025/26 Marine survey Project Parameters Economic & Financial Analysis 2014 - 2016 Feasibility Initial Design Pre-Consultation Investment Request Grant Application 2016 - 2019 Initial Design & Pre-Consultation Detailed Design EPC Procurement Consenting 2019 – 2021 Detailed Design & Consents Key Milestones

  • Apr 2019 –

Regulator’s Investment Request Decision

  • ~ Apr 2019 –

Make Grant Application to EC

  • ~ Aug 2019 –

EC Grant Decision

  • Early 2020 –

Launch EPC Tender

  • Mid 2020 –

Submit Consents Applications

  • End 2021 – Final

Investment Decision

  • 2026 – Go Live

EirGrid Framework for Grid Development Step 6 Step 1 Steps 2 - 4 Step 5

slide-15
SLIDE 15

What have we learnt?

Connection Point:

  • 220kV substations at Knockraha and Great Island identified as feasible

connections points based on level of connectivity in transmission grid and their geographical location along the south coast of Ireland

  • Grid assessment shows connection point at Knockraha can accommodate

interconnector flows far better than Great Island

slide-16
SLIDE 16

What have we learnt?

Land Studies:

  • Concluded that there are feasible options in both East Cork and West

Wexford for the various onshore elements of interconnector.

  • Specific landfall study concluded all 10 identified locations are feasible with

East Cork area performing better than West Wexford.

slide-17
SLIDE 17

Social Impact Assessment:

  • High level Social Baseline Report has

been prepared.

  • It does not identify project as having a

greater social impact in either region.

  • Report will be built on with input from

communities, landowners and other stakeholders.

What have we learnt?

slide-18
SLIDE 18

What have we learnt?

Marine Route Investigation:

  • Six trunk routes identified between East Cork / West Wexford and NW France.
  • Best performing and least constrained route is Route 2 from East Cork.
  • A full marine survey concluded this route was largely feasible with no major

constraints.

slide-19
SLIDE 19

SSS Hydrophone Multibeam echo sounder Pinger SBP Sparker SBP Magnetometer

Marine Surveys

Grab Camera Vibrocorer CPT

Geophysical Surveys 2014 & 2017 Geotechnical Surveys 2015 & 2018

slide-20
SLIDE 20

2014/15 Marine Surveys – Vessels in Cork

slide-21
SLIDE 21

Rock identified in Irish Nearshore Rock identified in French Nearshore

slide-22
SLIDE 22
slide-23
SLIDE 23

2017/18 - Additional Marine Surveys

slide-24
SLIDE 24

Step 2 Pre-Consultation

  • Aligned project with the new Framework for

Grid Development.

  • Developed detailed project update

brochure for Step 2 (2017).

  • Outlined that the best performing option for

project is to connect to France via the East Cork area.

  • Engaged in stakeholder outreach with

elected reps, municipal districts, local businesses, industry reps, community and environmental groups, fisheries groups.

  • Carried out public consultation on 2017

marine survey foreshore licence.

slide-25
SLIDE 25

Step 3 Pre-Consultation to date

  • Confirmed East Cork as best performing

connection point at launch of Step 3 in February 2018.

  • Developed detailed project update brochure for

Step 3 (2018) with infographic of project elements.

  • Carried out public consultation on 2018 marine

survey foreshore licence.

  • Held series of project open days and

community meetings at locations in East Cork.

slide-26
SLIDE 26

Project Development

  • Project is currently in Step 3 of Framework for Grid Development.
  • Step 3 Objectives:

– Identification of a shortlist of converter station location zones. – Identification of best performing landfall options (narrow down current shortlist).

  • Cork based Community Liaison Officer appointed to project.
  • Timeline:
slide-27
SLIDE 27

East Cork

slide-28
SLIDE 28

Summary

Project is Feasible

  • Various studies

and surveys complete

Benefits

  • European

energy market integration

  • Facilitates low

carbon future

  • Improved

security of supply

  • Direct telecoms

link to EU

Key Approval Steps

  • Investment

Request

  • Grant

Application

Project Development

  • Project

progressing on all fronts

  • Consultation

and engagement

  • ngoing
slide-29
SLIDE 29

Thank You

celticinterconnector@eirgrid.com