ccs case studies
play

CCS Case Studies Olav Kaarstad, StatoilHydro ASA Workshop on - PowerPoint PPT Presentation

1 CCS Case Studies Olav Kaarstad, StatoilHydro ASA Workshop on development of natural gas resources with high CO2 & Carbon Capture and Storage (CCS) in CCOP, Bali, Indonesia, 17-20 March 2009 2 Topics covered An overview of


  1. 1 CCS Case Studies Olav Kaarstad, StatoilHydro ASA Workshop on development of natural gas resources with high CO2 & Carbon Capture and Storage (CCS) in CCOP, Bali, Indonesia, 17-20 March 2009

  2. 2 Topics covered � An overview of CCS-projects world-wide � The four large projects and history of development � Sleipner, Norway � In Salah, Algeria � Snøhvit, Norway � Weyburn, Canada � What did they cost? � Things can go wrong � Some other projects � Exploring for CO 2 -storage

  3. 3 An overview of CCS-projects world-wide

  4. 4 So far only four large and some smaller CO 2 -storage projects in operation Sleipner, In Salah, Snøhvit, Weyburn, Norway Algeria Norway Canada

  5. 5 Numerous aspiring CCS projects in the power generation sector � how many will go ahead? � and are we seeing too little focus on the below ground aspects? Map credit: Scottish Centre for Carbon Storage, School of Geosciences, University of Edinburgh (www.geos.ed.ac.uk/ccsmap)

  6. 6 Pure CO 2 -reservoirs & CO 2 -rich natural gas reservoirs Source: IPCC SRCCS, 2005

  7. 7 The Sleipner CO 2 -injection - started operation in 1996 - nearly 1 mill tonnes CO2 per year Licence partners: ExxonMobil E&P Norw ay, Norsk Hydro AS, Total E&P Norw ay

  8. 8

  9. Introduction 9 Sleipner Vest GIIP: 5.6 TSft 3 (160 GSm 3 ) Production start 1996 CIIP: 427 mill.bbl Natural gas with (70 MSm 3 ) 9 mol% CO 2 1°40’ 1°40’ 2°00’ 2°00’ NORWAY 10 km 10 km Sleipner Øst 58°30’ 58°30’ Production start 1993 Natural gas with < 1 mol % CO 2 58°15’ 58°15’ UK Gas sales specifications: < 2.5 mol% CO 2

  10. 10 1. Extraction Sleipner A Sleipner T Injection Well Amine Plant Sleipner B 2. Compression Gas with Injected and vented CO 2 1996 - 2006 CO 2 1.20 1 Mtons Injected Vented 1.00 0.80 M to n s Gas with 0.60 CO 2 CO 2 0.40 3. Injection 3. Injection 0.20 0.00 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 Utsira Fm CO 2 4. Subsurface storage Sleipner Vest

  11. 11 Main issues focused on prior to injection - INJECTIVITY Tem perature critical, 2 7 0 C � Reservoir Simulation (black oil, oil-gas model) 0 .2 7 – 0 .4 1 SGAS ( CO 2 ) after 1 0 years of injection 0 .4 1 – 0 .5 4 0 .6 7 – 0 .8 1 Shale barriers

  12. 12 Main issues focused on prior to injection - MIGRATION Assumed CO 2 No migration of the CO 2 back to the migration Sleipner wells direction � New seismic survey in 1994 � changed the location from NW to 2.8 km NNE of the SLA (the current location) � Structural trap identified, saddle area northwards Predicted migration direction � northwards SLA � Base Utsira Fm shows shale diapirs east of SLA � expected to reduce the horizontal distribution of the CO 2 towards the SLA

  13. 13 The In Salah CO 2 -injection in Algeria

  14. Amine co 2 14 Removal 4 Gas 3 CO 2 Production Injection Wells Wells Carboniferous Reservoir 20 metres thick G a s W a t e r The In Salah CO 2 injection � From left to right: � Location map � Picture of the gas processing plant � Schematic illustration of CO 2 -injection in 3 wells � Injection of nearly 1 million tons of CO 2 per year � CO 2 extracted from natural gas Sources: BP, Sonatrach, StatoilHydro

  15. 15 More on In Salah CO 2 injection

  16. 16 The Snøhvit CO 2 -injection - started operation in April 2008 - about 0,7 mill tonnes CO 2 per year

  17. 17 Before construction start Snøhvit

  18. 18 First CO 2 injected: 2 2 . April 2 0 0 8 CO 2 -capture plant at Melkøya Snøhvit

  19. 19 The Snøhvit LNG + CO 2 capture, -transport and -storage project � Above, from left to right: � Location map � Picture of the Melkøya LNG-plant with CO 2 -capture plant � An illustration of the sub-sea wells and pipelines � About 0,7 million tons of CO 2 per year injected � CO 2 extracted from natural gas to be stored below the gas reservoir

  20. 20 Depressurising the sub-sea CO 2 -pipeline – it gets cold

  21. 21 Snøhvit 153 km sub-seapipeline and CO 2 -injection 2 inch orifice “safe location” >150 bar, 15 o C 30 kg/s CO 2 ~150 bar, 5 o C 320 m 153 km, 8 inch 5 o C DHSV Need for depressurising • When testing the DHSV – Required to be tested at dp= 30 bar 2700 m • In case of operating problems and pipeline breakage (anchors etc.) Factors that needs verification : • How long time to depressurise? ~300 bar • Minimum design temperature: -23 o C • Heat transfer from sea-water and sediments

  22. 22 The Weyburn-Midale CO 2 -EOR and –storage project

  23. 23 The Weyburn-Midale CO 2 -EOR Projects in Canada (2) The CO 2 - compressor facility This is where CO 2 arrives after a 320 km pipeline transport from the coal gasification at Beulah in North Dakota, USA

  24. 24 The Weyburn-Midale CO 2 -EOR Projects in Canada (1)

  25. 25 What does it cost?

  26. 26 Investment costs for CO 2 -storage projects (ex. capture) Sleipner Snovit Gorgon Project Country Norway Norway Australia Start 1996 2007 2008-2010 Aquifer Aquifer Depleted Oil Annual Injection rate Million T/year 1 0,7 5,2 CO2 Avoided * * 4,8 Onshore/Offshore Offshore Offshore Onshore Number of Wells 1 1 Pipeline length km 0 153 Investment Costs Compression and Dehydration $ million * 70 Pipeline $ million None 73 Drilling and Well Completion $ million 10 25 Facilities $ million * 12 Other $ million * 11 Total Investment Costs $ million 80 191 A$ 300-400 Operating Costs Annual Costs $ million USD 0.75 million N/A N/A

  27. 27 Sleipner CO 2 operating costs Type of cost Mill US$/yr System cost (average for all systems) 5,6 Logistics, catering etc. 0,7 Monitoring of storage reservoir 1,8 CO2- and NOx-taxes 4,5 Average yearly cost 12,5

  28. 28 In Salah costs • US $100mm Incremental Cost for Storage • No commercial benefit, no CO2-tax • Test-bed for CO2 Monitoring Technologies $30mm Research Project

  29. 29 � a lesson from a water/sand injection project Things can go wrong

  30. 30 The Tordis water/sand injection incident A A A’ A’ 34/7-L-1 H 34/7-L-1 H 0.00 m 0.00 m Top Nordland Gp. Top Nordland Gp. 200.00 m 200.00 m 400.00 m 400.00 m 600.00 m 600.00 m � Triggering factors � Injection operated at pressures and flow higher than the 800.00 m 800.00 m formation could take Top Utsira Fm. Top Utsira Fm. � Underlying causes 1. Misjudgement of potential hazard Top Hordaland Gr. Top Hordaland Gr. 2. Requirements/guidelines incomplete or missing 1000.00 m 1000.00 m 3. Inadequate follow-up / control of work 4. Important information not communicated/understood 5. Consequences of the modification was inadequately assessed

  31. CO 2 injection facilities at Nagaoka, Japan 31 A couple of other, smaller scale CCS-projects Ketzin, Germany

  32. 32 Castor pilot, DK Aker Clean Carbon, N Vattenfall oxy-fuel, D RWE full scale, D Test Center Mongstad, N Capture from power plants and industrial sources; � Capture from flue gases can be a magnitude more difficult than CO 2 -capture from natural gas � Volume, pressure, concentration, energy consumption, emissions to air and so forth � Large activity in EU and globally wrt. finding better technologies � Lots of pilot and a few demo units, numerous industrial scale engineering projects � Many more than shown in the above pictures

  33. 33 The next step at StatoilHydros Mongstad refinery

  34. 34 Combined heat and power plant being built The next big step for CO 2 -capture from flue gas sources; The European CO 2 Test Centre (TCM) plus full scale CO 2 -capture at StatoilHydros Mongstad refinery � From the left: � Location map, picture of the Mongstad refinery, an illustration of the power plant � Rule of the thumb: the capture part may be ¾ of the total CCS-cost � The primary objective of TCM is to test and qualify technology for the capture of CO 2 in order to reduce the costs and risks associated with large-scale plants

  35. Exploring for CO 2 -storage StatoilHydro’s COSMaP program m e

  36. 36 Methodology – HOW Mapping activities Cretaceous P(90) Cretaceous (Mean) Cretaceous P(10) 5.3 9.9 15.5 Capacity Large uncertainty Capacity “Final” numbers DG1 Feasibility Basin evaluation & Appraisal drilling “YTF-figures” DG0 DGA Data collection Drilling / gathering Capacity Monte Carlo simulation Static and dynamic Prospect evaluation 3D modelling Uncertainty analysis Capacity Moderate uncertainty WHY HOW WHERE WHO WHEN WHAT CI 2 4/ 6 2 4 1 1 1

  37. 37 Methodology – HOW Storage options Depleted oil and gas reservoirs Dry structures (“static” storage) Always CO2 for EOR as an option! Aquifers (“dynamic” storage) WHY HOW WHERE WHO WHEN WHAT CI 2 5/ 6 2 4 1 1 1

  38. 38 Methodology – HOW Evaluate leakage risks Through the Along faults Along CO 2 Along poorly Up-dip the cap rock injection well plugged old wells reservoir itself Avoid pressure build up! Cross flow between reservoirs Site specific - Each storage needs individual attention WHY HOW WHERE WHO WHEN WHAT CI 2 6/ 6 2 4 1 1 1

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend