Catcher Hook Up & Commissioning 23 rd October 2017 Executive - - PowerPoint PPT Presentation

catcher hook up commissioning
SMART_READER_LITE
LIVE PREVIEW

Catcher Hook Up & Commissioning 23 rd October 2017 Executive - - PowerPoint PPT Presentation

Catcher Hook Up & Commissioning 23 rd October 2017 Executive Summary Vessel arrived in Nigg on 8 th October and was deployed in the field on 18 th October Removal of cone plate and hook-up with the buoy have been completed Hook-up


slide-1
SLIDE 1

Catcher Hook Up & Commissioning

23rd October 2017

slide-2
SLIDE 2

Executive Summary

  • Vessel arrived in Nigg on 8th October and was deployed in the field on 18th

October

  • Removal of cone plate and hook-up with the buoy have been completed
  • Hook-up of risers ongoing; hook-up of umbilicals plus reinstatement of

equipment and leak testing of pipework will follow

  • Commissioning activities are running in parallel
  • Introduction of hydrocarbons after flushing of gas export line and final

rotation testing

  • Forecast for first oil remains on track for before year end
  • Field ramp up will be over 3-4 month period with Catcher being the first field
  • n line followed by Varadero and Burgman
  • Full field plateau production of 60kbopd will be achieved at this time
  • Expected to trade in line with Brent

October 2017 | P1

slide-3
SLIDE 3
  • Risers will be pulled up by 2

metres from temporary hang-off and installed in their permanent hang-off position

Catcher Hook Up

Cone Plug Removal

*ESDV: Emergency Shut-Down Valves Note photographs are from similar operations on other vessels

Arrival in the UK and Hook-Up 4-6 Weeks Commissioning 3-4 Weeks Harbour On location

  • In place for protection during

voyage

  • Removed in harbour prior to

deployment

Typical Buoy top Permanent hang-off

  • Buoy pulled in and locked in

place

  • Rotation test completed

Risers Umbilical's ESDV’s* Swivel Stack Reinstate- ment Commiss- ioning Pre-Commiss- ioning Buoy Hook-Up October 2017 | P2

slide-4
SLIDE 4
  • ESDV valves will be removed from storage, installed on risers,

bolts torqued and valves tested

Catcher Hook Up

October 2017 | P3

  • Umbilicals will be pulled up by 5 metres and

permanently hung-off

  • Seal cans will be installed and packed with resin

Riser Size ESDV Weight CATCHER Production 10" 3.3T Gas Export 10" 3T Water injection 8" 2.2T Gas lift 6" 0.5T BURGMAN Production 10" 3.3T Water injection 8" 2.2T Gas lift 6" 0.5T VARADERO Production 10" 3.3T Water injection 8" 2.2T Gas lift 6" 0.5T

ESDV installed ESDV being lowered

Cone Plug Removal

Arrival in the UK and Hook-Up 4-6 Weeks Commissioning 3-4 Weeks Harbour On location

Risers Umbilical's ESDV’s* Swivel Stack Reinstate- ment Commiss- ioning Pre-Commiss- ioning Buoy Hook-Up

slide-5
SLIDE 5
  • Geostationary pipework will be reinstated along with

power, instrumentation and shipside structures

  • Production lines will be connected to the swivel
  • Hook-up equipment such as buoy bumper bars, hang-
  • ffs and sheave arrangements will be removed

Catcher Hook Up

October 2017 | P4

  • Swivel stack (270t) in sail away location to allow buoy

installation

  • Will be skidded to the centre of the turret, aligned

with the buoy, mated and bolts tensioned

Shipside Pipework ESDVs pipework Removed structure

Cone Plug Removal

Arrival in the UK and Hook-Up 4-6 Weeks Commissioning 3-4 Weeks Harbour On location

Risers Umbilical's ESDV’s* Swivel Stack Reinstate- ment Commiss- ioning Pre-Commiss- ioning Buoy Hook-Up

slide-6
SLIDE 6

Catcher Commissioning

October 2017 | P5

  • Where possible equipment was leak tested, commissioned and

systems accepted by operations in Singapore prior to sail away

  • The voyage and movement of the vessel and equipment

requires them to be re-tested ahead of the introduction of hydrocarbons

  • Vessel activities:

– Pipework: Nitrogen/helium testing; and Deluge testing – Tubing: Leak testing – Electrical & Instrumentation: Pig tail termination & tests; and Removed equipment reinstated and tested

  • Subsea activities

– Completion of umbilical core flushing – Gas export riser dewatering – Tree & manifold valve function testing

  • Final activities

– Testing of offloading hose connection – Final rotation test

  • Ready for the introduction of hydrocarbons from Catcher field

Gas export line – commissioned prior to start up Teekay shuttle tanker

Cone Plug Removal

Arrival in the UK and Hook-Up 4-6 Weeks Commissioning 3-4 Weeks Harbour On location

Risers Umbilical's ESDV’s* Swivel Stack Reinstate- ment Commiss- ioning Pre-Commiss- ioning Buoy Hook-Up

slide-7
SLIDE 7

10,000 20,000 30,000 40,000 50,000 60,000 70,000 Daily Oil Potential (stb/d) Catcher Varadero Burgman

Catcher Commissioning & Production Profile

October 2017 | P6

  • Catcher is the initial field on production due to it’s ability to produce oil in a stable fashion for the first stages
  • f the FPSO plant commissioning
  • Each field will be brought on in the following manner

– Well clean up (initial clean up restricted by rig surface equipment) – Well test through the subsea multi-phase meters – Restricted rate to manage gas rates through commissioning period

  • Following gas train commissioning completion and the introduction of Burgman fluids the plant will be run at

60 kbopd

Fuel Gas Import Catcher First Oil Oil Stabili- sation Fuel Gas Varadero First Oil Permeat. Comp Water Injection Gas Lift Gas Export Comm. Burgman First Oil Flash Gas Comp Primary Gas Handling Produced Water