CAPITAL PROJECTS UPDATE TO SENATE CALIFORNIA STATE UNIVERSITY, CHICO MASTER PLAN FRAMEWORKS An Inclusive Chico State: Promote an inclusive environment by fostering a welcoming campus, access to robust support services, and facilities


slide-1
SLIDE 1

CAPITAL PROJECTS UPDATE TO SENATE

CALIFORNIA STATE UNIVERSITY, CHICO

slide-2
SLIDE 2

MASTER PLAN FRAMEWORKS

 An Inclusive Chico State:

Promote an inclusive environment by fostering a welcoming campus, access to robust support services, and facilities reflective of a diverse population

Provide new and renovated facilities and open space to reflect today’s student  An Experiential Chico State

Dedicate the campus core to the student experience

Enhance opportunities for campus activity beyond classroom hours

Improve and expand facilities  A Learning Chico State

Transform the academic environment for today’s student

Maximize existing academic space

Increase facilities to improve the academic and research environment

2

slide-3
SLIDE 3

3

~33% of our buildings!

~913,155 GSF Requires Total Renovation

  • r Complete Replacement

Critical Building Needs

0.00‐0.10 Excellent

Typically new

construction

0.11‐0.20 Good

Maintained within

lifecycle

0.21‐0.30 Fair

Normal renovations

needed

0.31‐0.50 Below Avg

Major renovations needed

0.51‐0.60 Poor

Total renovation

needed

> 0.60

Complete replacement

indicated

FACILITY CONDITION ASSESSMENT

slide-4
SLIDE 4

NEW SCIENCE BUILDING

4

slide-5
SLIDE 5

5

slide-6
SLIDE 6

TEAM CONTINUITY

6

slide-7
SLIDE 7

POTENTIAL MASSING

7

slide-8
SLIDE 8

8

slide-9
SLIDE 9

 Current Footprint = 89,075 GSF  Current usage

 3 Computer labs  24 Lecture spaces  161 Offices  7 Conference rooms  6,000 sf of teaching labs  4th floor IT personnel, data center, and

communications hub  Construction schedule:

 Summer 21 to Summer 23

9

BUTTE REMODEL

slide-10
SLIDE 10

DESIRED OUTCOMES

 Align with Master Plan  Academic icon for campus  More efficient use of space catering to active learning  Hazmat abatement  Mechanical, Electrical, and Plumbing upgrades  Aim for a Net ZERO building  Additional 10,000 sf for student “hang out” space  Exterior and landscape upgrades  Transition all or portions of the 4th floor to academics  Site logistics and traffic flow will be key

10

slide-11
SLIDE 11

CURRENT TIMELINE

 Summer 2020:

Complete New Science Building Start Old Physical Science remodel

 Summer 2021:

Complete Old Physical Science remodel Start Butte remodel

 Summer 2023:

Complete Butte remodel

11