cambourne to cambridge public transport route
play

Cambourne to Cambridge Public Transport Route 14 November 2018 - PowerPoint PPT Presentation

Cambourne to Cambridge Public Transport Route 14 November 2018 Key City Deal Commitment 10-15% reduction in vehicles from 2011 figure Equivalent to a 24% reduction today Continued growth increases the challenge CPIER


  1. Cambourne to Cambridge Public Transport Route 14 November 2018

  2. Key City Deal Commitment • 10-15% reduction in vehicles from 2011 figure • Equivalent to a 24% reduction today • Continued growth increases the challenge CPIER Recommendation #7 A package of transport and other infrastructure projects to alleviate the growing pains of Greater Cambridge should be considered the single most important infrastructure priority […] in the short to medium term.

  3. Strategic Case 8,000 new homes Generating 44,000 1 million houses in the by 2031 new jobs Oxford to Cambridge arc by 2050 Increasing population has led to More demand for a modal shift Need to provide scheme to congestion along the A428/A1303 from cars to public transport, connect homes to employment making it unsustainable walking and cycling and services

  4. A world class public transport system for Greater Cambridge will : • Offer a genuinely competitive alternative to the car • Quicker, reliable and, where possible, segregated from other vehicles • Integrate bus, rail, mass transit, walking and cycling both physically and through timetabling, ticketing, and information • Focus on better serving employment clusters outside the city centre, with a wider journey to work geography • Be feasible to deliver, and can be sustained

  5. Cambridgeshire & Peterborough Combined Authority The Cambourne to Cambridge scheme must align with CAM proposals and be future-proofed May 2018 31 October 2018 January 2019 30 January 2018 8 February 2018 Combined Authority Review Cambridgeshire GCP formally Combined Combined evidence confirms off-road as and Peterborough adopts CAM Authority requests Authority Board optimal solution. CA Board halt to work and will review the Combined independent agrees scheme to advance at Strategic Outline Authority agrees pace. Confirms route as Business Case development of the review essential first phase of CAM Cambridgeshire for the CA Metro, Autonomous Metro prepared by consultants Steer (CAM).

  6. Project elements Phase 1 Phase 2 East from West from Madingley Mulch Madingley Mulch roundabout to roundabout, via Cambridge city – P&R site, to Bourn prioritised as a key Airfield and area of congestion. continuing to Cambourne New Park & Ride site at Waterworks or Scotland Farm

  7. Progress Phases of Technical Assessment Route Development Phases of Consultation Project Initial public consultation 6 Oct/Nov 2015 route options and P&R site Public consultation February 2016 responses published Executive Board agree in principle to a segregated route given wider economic benefits and to undertake further work. Phase 1 consultation proposed more detailed plans for three routes, on- Nov-Jan 2018 road, tidal on-road and off- road. Two Park and Ride sites - Scotland Farm and Technical Assessment Route Development The Waterworks. Public consultation responses published May 2018 May – October CA Mayor requests halt to work whilst review considers alignment with CAM. CA review concluded October/November 2018 C2C progress tabled for November/December GCP Assembly and Board

  8. Off-Road Option This off-line route option appears to Public Consultation Results be sufficiently distanced from designated sites and therefore unlikely to have any adverse impact on these. Q. Please indicate which overall route would be your preferred choice? On-Road Option Options A and B are located in close proximity to this (Madingley Wood SSSI) nationally designated 45% site and proposals could have an adverse impact, through direct and 40% indirect effects, on the notified 40% features of the ancient woodland. 35% Natural England Consultation 33% 30% Response Off-Road Option 25% We consider that the harm associated with either of the options 20% for Route C could be minimised or avoided subject to a robust 18% 15% mitigation strategy. 10% On-Road Option The proposal by reason of the 5% 6% proximity to the cemetery and loss 4% of verge would result in irreversible, 0% adverse impacts upon the On-Road B Off-Road C On-Road A None Not Sure approach, setting and layout of the cemetery site. 2,049 complete responses Historic England Consultation Response 8

  9. Jo Baker Mott MacDonald C2C Project Director

  10. Strategic and Technical Assessment – On road Option A o Option A and Option B were assessed against each other using Mott MacDonald’s in-house Investment Sifting and Evaluation Tool (INSET) to arrive at a preferred on-road option. o The findings of the INSET assessment have concluded that the on-road option is Option A. o However, a potential “optimisation” of the route has been explored to reflect the aspiration in Option B for some improvements to outbound traffic, and a need to further consider the operation of Junction 13 of the M11. Option B o Option A and Option B were assessed against each other using Mott MacDonald’s in-house Investment Sifting and Evaluation Tool (INSET) to arrive at the highest scoring on-road option. o Option B did not score as high as Option A. The need for gantries was a significant reason for the differences in scores. Although, this was not in the original proposal by the LLF gantries were included for safety and operational purposes.

  11. One of the main outcomes of the consultation was the development of an “Optimised” on-road option. This would include both inbound and outbound public transport priority, without the need for gantry structures and within the highway boundary.

  12. Optimised On-Road Option Optimisation Optimisation of Optimisation Madingley Mulch Roundabout Carriageway Optimisation of Widening for 200m M11 Junction 13 of west bound bus Change to M11 to lane added. allow two right turn lanes from off-slip Bus gate priority Inbound bus Public transport at Eddington lane up to M11 priority at M11 Avenue Optimisation Bus Lane from West Cambridge Development to Storeys Way Bus lane removed Optimisation High Cross Junction Park and Ride access relocated to Buses share with general traffic Eddington Avenue, additional from junction with Eddington eastbound and westbound bus lane and Avenue / High Cross bus gate at approach to junction.

  13. Strategic and technical assessment – Off-road Option C o Option C was split into the pink, blue and (through West Cambridge) development light green routes. These represented different alignment routes for Option C. o The route was broken down into five areas and assessed using INSET to arrive at a recommended Specific Route Alignment. o The recommended off-road specific route alignment is the “Blue” route through Madingley Mulch, and adjacent to Coton village and the light green route through West Cambridge, and the Rugby Ground connection to Grange Road.

  14. Option Assessment Off-road and On-road options were subject to financial review including wider scheme benefits and BCR. Level 1: = Conventional Transport Benefits >>Provides BCR 800,000,000 Level 2 = Wider Economic Benefits related to transport scheme (i.e. not land-use changes) >>Provides Adjusted BCR 700,000,000 Level 3 = Wider Economic Benefits associated with land-use changes. Nationally significant >> Provides Local Growth Benefits 600,000,000 500,000,000 0.25 400,000,000 0.2 300,000,000 0.15 Scheme Costs 0.1 200,000,000 £190M 0.05 100,000,000 £80M 0 0 On-line Off-line Scheme Benefits Local growth BCR Adjusted BCR

  15. Option Assessment results Multi-criteria assessment tool results Key findings from the assessment Off-Road  Aligns better with transport policy  More reliable journey  Less disruption to existing roads  Future proofing – Aligns better with aspiration for CAM (Cambridge Autonomous Metro)  Better in terms of heritage and biodiversity Key findings from the assessment On-Road  Has less impact on green belt  Lower cost

  16. Specific Route Alignment Project team continues to welcome views and contributions from stakeholders throughout the continuing development of plans for Phase 1 of the route, in conjunction with Phase 2 consultation and planning, working to deliver a single route option for GCP Board decision in late 2019.

  17. Next Steps Jan 19 Feb 19 Mar-Oct 19 Oct 19 Strategic Outline Phase 2 public Ongoing technical Specific Route Business Case for consultation - tbc assessment and Alignment Decision. the CAM Metro to route development pending December Combined Authority Board decision Board Consultation results Present a final published and option in the outline considered in business case. ongoing planning. Expected late 2019. Assessment and mitigation design continues.

  18. Q & A

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend