ca se study intro to cvrb ca se study intro to cvrb
play

Ca se Study: Intro to CVRB Ca se Study: Intro to CVRB LEED Gold - PDF document

UCSF Ca rdiova sc ula r Re se a rc h Building Inte g ra te d Proje c t De live ry a nd L Inte g ra te d Proje c t De live ry a nd L e a n Proc e ss e a n Proc e ss Ca se Study: Intro to CVRB Ca se Study: Intro to CVRB LEED Gold


  1. UCSF Ca rdiova sc ula r Re se a rc h Building Inte g ra te d Proje c t De live ry a nd L Inte g ra te d Proje c t De live ry a nd L e a n Proc e ss e a n Proc e ss Ca se Study: Intro to CVRB Ca se Study: Intro to CVRB • LEED Gold Certified • 27 month schedule 27 th h d l • Five Stories • 236,000 GSF • Construction $190M Open wet labs, lab • Project $254M j support, offices, vivarium, and an outpatient clinic (OSHPD 3). 1

  2. IPD E IPD E volution volution Owner Architect Contractor T T e a m Org a niza tion e a m Org a niza tion Owner UCSF UCSF Cambridge CM Structural Eng. Architect Rutherford SmithGroup & Chekene Jim Jennings Lab Planners GPR All Other Design Consultants 2

  3. T T e a m Org a niza tion e a m Org a niza tion Owner UCSF UCSF All Other Cambridge Trades CM (lump sum bid) Structural Eng. Contractor Architect Rutherford Rudolph and SmithGroup & Chekene Sletten Jim Jennings Exterior Skin Walters & Wolf Lab Planners GPR Electrical All Other Rosendin Design Mechanical/ Consultants Plumbing Southland T T e a m Se le c tion e a m Se le c tion Owner UCSF B Best Value t V l Prequalification f Selection Selection General All Other Contractor Trades Design Build Mechanical/ Electrical Plumbing Exterior Skin 3

  4. Choosing the T Choosing the T e a m e a m Personalities of Select Team Members Individuals on Based on Experience Based on Experience Team Matter � Building Information Modeling (BIM) � Integrated Project Delivery � Design-Build for Key Trades � Lean Construction L C t ti Techniques Pre qua lific a tion T Pre qua lific a tion T e a m Se le c tion e a m Se le c tion • Prequalification prior to low Fast Track Buyout – bid process bid process E Early Packages l P k • Prequalification Based on: Management Experience with • Similar Projects • Management of DB Subs • Lean Construction • Integrated Team 4

  5. Be st Va lue Se le c tion Be st Va lue Se le c tion • Evaluate Contractors for: • Categories: • Categories: Management Capability • Safety • Financial Strength • Labor Compliance • Relevant Experience • Divide Points into Bid to Determine Lowest Cost Per Point • Evaluations are by Points Earned in Each Category De sig n Pre se nta tion De sig n Pre se nta tion 5

  6. De sig n Pre se nta tion De sig n Pre se nta tion Conceptual Massing and Orientation De sig n Pre se nta tion De sig n Pre se nta tion 6

  7. De sig n F De sig n F e a ture s e a ture s Architectural Features Glass at Offices Metal Panel and Mesh at Labs Terracotta at Support Spaces De sig n Pre se nta tion De sig n Pre se nta tion Planning Concepts – Scientific Collaboration and Translational Research 7

  8. De sig n Pre se nta tion De sig n Pre se nta tion Planning Concepts – Scientific Collaboration and Translational Research De sig n Pre se nta tion De sig n Pre se nta tion Planning Concept - Efficiency and Flexibility No Rated Corridors Lab Floor Efficiency Ratio 0.76 8

  9. Ma ximizing E Ma ximizing E ne rg y E ne rg y E ffic ie nc y ffic ie nc y Conceptual Segregation of Occupancies Horizontal Horizontal Vertical Vertical Ma ximizing E Ma ximizing E ne rg y E ne rg y E ffic ie nc y ffic ie nc y Conceptual Systems Integration with Planning 9

  10. Ma ximizing E Ma ximizing E ne rg y E ne rg y E ffic ie nc y ffic ie nc y Architectural Features Operable Windows at Offices Window Shading at Labs Minimal Openings at Vivarium Ma ximizing E Ma ximizing E ne rg y E ne rg y E ffic ie nc y ffic ie nc y Mechanical Design � Variable Speed Fans � Low Velocity Air Systems � Water Saving Plumbing Fixtures � Building Systems Control Electrical Design � Lighting Control Throughout g t g Co t o oug out � Energy Efficient Lighting 10

  11. F F our Ke y Conc e pts our Ke y Conc e pts 1. Integrating Technology 2. Communication 3. Dispute Resolution 4. Incentives 1. Inte g ra ting T 1. Inte g ra ting T e c hnolog y e c hnolog y • Whole Team in BIM • BIM Coordination = More BIM C di ti M Exchange of Ideas, Increased Commitment • Facilities Group on BIM • Define Team Member BIM is a tool R l Roles in Coordination i C di ti which makes IPD • Foster Trust to Enable possible Good Performance & Collaborative Approach 11

  12. 2. Communic a tion 2. Communic a tion Creating the tone • Goal Setting • Big Room • Schedules Pull Sessions Last Planner Last Planner Goa l Se tting Goa l Se tting 12

  13. Big Room Big Room – – Cre a ting the T Cre a ting the T one one CAMBRIDGE SMITHGROUP SOUTHLAND UCSF • All Key Members in ROSENDIN one trailer one trailer IOR • Team Approach COMMON Encouraged by owner PROJECT VISION • Blurring the lines W& W RUDOLPH & SLETTEN working as a team Sc he dule Proc e ss Sc he dule Proc e ss Weekly assignments, reliable promises, Remove measure PPC, and learn constraints, make work ready k d Specify handoffs, Weekly collaborative Schedule Work Plan Lookahead planning Detail Planning Set milestones, Phase/Pull establish project Scheduling duration Master Schedule Design Construction 13

  14. Sc he dule Proc e ss Sc he dule Proc e ss Pull Schedule L Last Planner Pl Inte g ra ting T Inte g ra ting T e c hnolog y e c hnolog y – – 4D 4D 14

  15. 3. Dispute Re solution 3. Dispute Re solution • Clear, Fair, Process Everyone Can Agree to Everyone Can Agree to • Set Clear Time Frames • Emphasize a Collaborative Approach • Review Key Project y j Process & Modify if Necessary 4. Inc e ntive 4. Inc e ntive – – Construc tion Construc tion Percent Planned • Performance Based Complete & Incentives Incentives S h d l Mil Schedule Milestone • Sharing Risk and Based Incentive Reward Program • Set Up a Way to Share the Reward • Everyone Fails Together Everyone Fails Together or Succeeds Together 15

  16. Inc e ntive Inc e ntive – – Construc tion Construc tion Percent Planned Planned P Planned Percent rcent Comple Complete Complete & (PPC) (PPC) (PPC) (PPC) S h d l Mil Schedule Milestone • Number of tasks Based Incentive completed vs number of Program tasks planned • 10 tasks planned for this week • 8 tasks completed this week • PPC = 80% Inc e ntive Inc e ntive – – Construc tion Construc tion Percent Planned SCHEDULE INCENTIVE SCHEDULE INCENTIVE Complete & MILES MILESTONES: Schedule Milestone S h d l Mil • Sept. 26, 2008: Based Incentive Structural Steel Mobilization Program • Jan. 27, 2009: Steel & Decking Complete • March 11, 2009: SOG & Deck Pours SOG & Deck Pours • May 27, 2009: Clinic Sheetrock & Taping Starts 16

  17. Inc e ntive Inc e ntive – –Pre Construc tion Pre Construc tion Bidder Participation For MEP Trades Incentive One Bidder Minimum Per One Bidder Minimum Per • Package For Every Bidder over Minimum • Contractor Receives $6K Incentive For All Other Trades One Bidder Minimum Per • Package For Every Bidder over Minimum • Contractor Receives $2K Incentive Inc e ntive Inc e ntive – –Pre Construc tion Pre Construc tion Target Cost & Complete Buyout Incentive Total Construction Cost at Bid Must be Between Anticipated Contract Value C t t V l ($175M) + 2% or -5% 17

  18. Inc e ntive Inc e ntive – –Pre Construc tion Pre Construc tion . . . And If Target Cost & Complete Buyout Total Cost at Bid Total Cost at Bid Incentive At end of Construction Then Scope Gap COs less than .5% Complete Complete + Buyout Incentive Constructability Achieved Omission COs less than .5% Be ne fits Be ne fits Greatest benefit is Accurate Buy-out at Target Cost • a successful project a successful project Improved Schedule Performance Improved Schedule Performance • • for the entire team Greatly Reduced Risk of Claims • Improved Design Process • Improved Risk Management • Process During Construction Improved Communications With • Stakeholders Decrease in RFI’s and Submittal • Turn Around Faster Decision Making • 18

  19. Be ne fits Be ne fits Greatest benefit is Cost Control from Beginning via • Integrated Team teg ated ea a successful project a successful project for the entire team Everybody’s ideas contribute • Early Integration of Installation • Criteria Lowered Risk for Owner Constructability Resolved Early Constructability Resolved Early • During Design Stages Predictability of Planning • Fewer Surprises Improve me nts Improve me nts Bring on CM/GC During What To Do • development of BOD Differently Differently Design build subs at the D i b ild b t th • beginning of Schematic Next Time design Further develop Incentive • Plan to include smaller subs and expand into design phase design phase Use Lean during Design • phase Content of Building • Information Model 19

  20. Ke ys to Suc c e ss Ke ys to Suc c e ss • Everybody Part of the Solution & Outcome Solution & Outcome • Culture of “How Can We…” • Consensus Building • Owner Driven IPD Process UCSF Ca rdiova sc ula r Re se a rc h Building Inte g ra te d Proje c t De live ry a nd L Inte g ra te d Proje c t De live ry a nd L e a n Proc e ss e a n Proc e ss 20

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend