C/CAG Technical Advisory Committee October 17, 2019 1 1 Project - - PowerPoint PPT Presentation

C/CAG Technical Advisory Committee October 17, 2019 1 1 Project Updates Construction Interface with Local Communities Public Outreach 2 Project Updates Construction Interface with Local Communities Public Outreach 3


slide-1
SLIDE 1

1

C/CAG Technical Advisory Committee October 17, 2019

1

slide-2
SLIDE 2

2

  • Project Updates
  • Construction Interface with Local

Communities

  • Public Outreach
slide-3
SLIDE 3

3

  • Project Updates
  • Construction Interface with Local

Communities

  • Public Outreach
slide-4
SLIDE 4

4 4

PROJECT UPDATES

  • San Mateo County Express Lanes Joint Powers

Authority (JPA) formed

  • South of Whipple: construction for HOV to

Express Lane conversion began March 2019

§ Substantial civil construction anticipated February 2020 § Toll System 65% design is underway

  • North of Whipple: 100% Design Plans for new

lanes completed September 30th

slide-5
SLIDE 5

5 5

CONSTRUCTION ACTIVITIES

slide-6
SLIDE 6

6

PROJECT UPDATES

6

slide-7
SLIDE 7

7

PROJECT UPDATES

2018 2019 2020 2021 2022

95% PS&E Jul 2019 Begin Construction Mar 2019 Begin Construction Jan 2020 Begin Toll Systems Installation May 2021 Open Express Lanes Oct 2022 Caltrans Project Approval (South and North) Nov 2018 Substantial Construction Completed Feb 2020

Express Lane Addition HOV to Express Lane Conversion

Begin Toll Systems Installation May 2020 Open Express Lanes Oct 2021

7

North of Whipple South of Whipple

Begin Toll Systems Testing Feb 2021 End Construction Jan 2022 Begin Toll Systems Testing May 2022 Full Freeway Closures TBD

slide-8
SLIDE 8

8

  • Project Updates
  • Construction Interface with Local

Communities

  • Public Outreach
slide-9
SLIDE 9

9 9

CONSTRUCTION BLOCKS

slide-10
SLIDE 10

10 10

STAGE 1 – PHASE 1 IN 3 BLOCKS

slide-11
SLIDE 11

11 11

STAGE 1 – PHASE 1 IN 4 BLOCKS

slide-12
SLIDE 12

12 12

STAGE 1 – PHASE 2 IN BLOCK 1

slide-13
SLIDE 13

13 13

STAGE 1 – PHASE 2 IN BLOCK 2

slide-14
SLIDE 14

14 14

STAGE 1 – PHASE 2 IN BLOCK 3

slide-15
SLIDE 15

16 16

STAGE 2 IN BLOCK 1

slide-16
SLIDE 16

17 17

STAGE 2 IN BLOCK 2

slide-17
SLIDE 17

18 18

STAGE 2 IN BLOCKS 3 & 4

slide-18
SLIDE 18

24

NORTHERN SEGMENT CONSTRUCTION

24

  • Sound wall removal/reconstruction
  • Sewer line relocation
  • Vegetation removal
  • Replacement planting
  • PG&E and AT&T service work
  • Creating a soil berm from excavated soils

containing Aerially Deposited Lead (ADL) in State’s ROW

  • Constructing additional lanes
  • Replacing existing auxiliary lanes

Noticeable Construction Activities:

Cities:

  • Redwood City
  • San Carlos
  • Belmont
  • Foster City
  • San Mateo
  • Burlingame
  • Hillsborough
  • Millbrae
  • San Bruno
  • South San Francisco

Minor Work in:

  • East Palo Alto
  • Menlo Park
  • Palo Alto
slide-19
SLIDE 19

25 25

MINOR TREE IMPACTS IN RESIDENTIAL AREAS Elliott Street Elliott Street

Wayne Way Wayne Way Lafayette Street Lafayette Street

City of San Mateo City of San Mateo

Caltrans Tree

Removal Location

slide-20
SLIDE 20

26 26

CITY STREET WORK

Work on City Streets

  • Primarily PG&E service point connections
  • Service pedestals placed in State R/W wherever

possible

  • When needed, pedestals are behind curbs or placed
  • ut of the walkway on sidewalks

Communication with City staff

  • We met with city staff in each city prior to 95%

PS&E circulation and requested review comments

  • Goal has been to incorporate city’s requests as

much as possible

slide-21
SLIDE 21

27 27

IMPACTS TO MOTORISTS

  • Nighttime freeway lane closures,

starting as early as 9:00

  • Temporary ramp closures
  • Temporary local roadway lane closures
  • Full freeway closures (2021)

Cities:

  • Redwood City
  • San Carlos
  • Belmont
  • Foster City
  • San Mateo
  • Burlingame
  • Hillsborough
  • Millbrae
  • San Bruno
  • South San Francisco

Roadway Closures:

Minor Work in:

  • East Palo Alto
  • Menlo Park
  • Palo Alto
slide-22
SLIDE 22

28

Criteria for Detour Development

  • Have drivers pass intended ramp or turn so they

“catch” the detour signing

  • Use State Routes whenever possible
  • Avoid use of residential streets
  • Pick routes with greatest capacity (rights over lefts)
  • Accommodate city staff input

DETOUR PLANS

28

slide-23
SLIDE 23

29

PERMIT REQUESTS

  • Contractor will apply for

permits for work in city right

  • f way
  • Per State Code:

§ Caltrans is not required to pay any permit fees § A permit is not required for work in State right of way

  • r for detours
  • All city requirements should

be included in the plans

29

slide-24
SLIDE 24

30

  • Project Updates
  • Construction Interface with Local

Communities

  • Public Outreach
slide-25
SLIDE 25

31 31

PUBLIC OUTREACH PLAN

  • Ramp closure light boards two weeks in advance
  • Weekly construction info emailed and posted to

website, including detour information

  • Quarterly “newsletter” distributed via email
  • Community meeting(s) in San Mateo

neighborhood with wall and sewer work

  • Focused calls to cities as requested
  • Survey to each City Public Works Department to

verify appropriate Public Outreach contacts and level of outreach desired

slide-26
SLIDE 26

32

MONTHLY CONSTRUCTION EMAILS TO PIOs

32 Your residents can sign up for monthly e-mails at the new SM 101 Express Lanes Project Webpage!

https://dot.ca.gov/caltrans-near-me/district-4/d4-projects/d4-sm-101-express-lane-project

slide-27
SLIDE 27

33 33

OUTREACH CONTACTS - BLOCK 1

Block 1: Whipple Avenue to Holly Street (Redwood City and San Carlos) Construction Dates: January 2020 to March 2021

City of Redwood City Alex Chan (achan@redwoodcity.org) James O’Connell (joconell@redwoodcity.org) Amanda Wilson (awilson@redwoodcity.org) City of San Carlos Steven Machida (smachida@cityofsancarlos.org)

slide-28
SLIDE 28

34 34

OUTREACH CONTACTS - BLOCK 2

Block 2: Holly Street to Route 92 (San Carlos, Belmont, and San Mateo) Construction Dates: January 2020 to July 2021

City of Belmont Leticia Alvarez (lavarez@belmont.gov) Gilbert Yau (gyau@belmont.gov) Rick Locke (rlocke@belmont.gov) City of San Mateo Brad Underwood (bunderwood@cityofsanmateo.org) Ray Jackson (rayjackson@cityofsanmateo.org) Catherine Zammit (czammit@cityofsanmateo.org) Bethany Lopez (blopez@cityofsanmateo.org) Kellie Benze (kbenz@cityofsanmateo.org)

slide-29
SLIDE 29

35 35

OUTREACH CONTACTS - BLOCK 3

Block 3: Route 92 to Broadway (San Mateo and Burlingame) Construction Dates: January 2020 to October 2021

City of San Mateo Brad Underwood (bunderwood@cityofsanmateo.org) Ray Jackson (rayjackson@cityofsanmateo.org) Catherine Zammit (czammit@cityofsanmateo.org) Bethany Lopez (blopez@cityofsanmateo.org) Kellie Benze (kbenz@cityofsanmateo.org) City of San Mateo Brad Underwood (bunderwood@cityofsanmateo.org) Ray Jackson (rayjackson@cityofsanmateo.org) Catherine Zammit (czammit@cityofsanmateo.org) Bethany Lopez (blopez@cityofsanmateo.org) Kellie Benze (kbenz@cityofsanmateo.org) City of Burlingame Andrew Wong (awong@burlingame.org) Mahesh Yedluri (myedluri@burlingame.org) Art Morimoto (amorimoto@burlingame.org)

slide-30
SLIDE 30

36 36

OUTREACH CONTACTS - BLOCK 4

Block 4: Broadway to Grand Avenue (Burlingame, Millbrae, San Bruno, and South San Francisco) Construction Dates: February 2020 to January 2022

City of Millbrae Khee Lim (klim@ci.millbrae.ca.us) Jane Kao (jkao@ci.millbrae.ca.us) Andrew Yang (ayang@ci.millbrae.ca.us) City of San Bruno Dalia Manaois (dmanaois@sanbruno.ca.gov) Matt Kato (mkato@sanbruno.ca.gov) City of South San Francisco Matthew Ruble (matthew.ruble@ssf.net)

slide-31
SLIDE 31

37 37

OUTREACH CONTACTS - OTHER WORK

City of East Palo Alto Sean Charpentier (cmoffice@cityofepa.org) Shari Carlet (scarlet@cityofepa.org) City of Menlo Park Starla Jerome-Robinson (slrobinson@menlopark.org) Curtin Clay (cjcurtin@menlopark.org) City of Foster City Norm Dorais (ndorais@fostercity.org) Town of Hillsborough TBD City of Palo Alto Ed Shikada (CityMgr@cityofpaloalto.org) Claudia Keith (claudia.keith@cityofpaloalto.org) Lisa Caracciolo (lisa.caracciolo@cityofpaloalto.org)

slide-32
SLIDE 32

38

REQUESTED LOCAL ACTIONS

  • 1. Provide concurrence on detour plans (ramp closure and

freeway closure)

  • 2. Respond to Kiewit request for no-cost/State permits
  • 3. Confirm that we have the right contacts for Public

Outreach

  • 4. Participate in Public Outreach Survey to learn how each

city communicates with its citizens

  • 5. Disseminate information to residents through

communication contacts

38

slide-33
SLIDE 33

39 39

Questions?

Stay informed - sign up to receive construction updates by e-mail.

https://dot.ca.gov/caltrans-near-me/district-4/d4-projects/d4-san-mateo-101-express- lane-project