Building infrastructure to support global trade Matthew - - PowerPoint PPT Presentation
Building infrastructure to support global trade Matthew - - PowerPoint PPT Presentation
Building infrastructure to support global trade Matthew Walton-Knight, PEng CEng MI CE I an Galsworthy, PEng CEng MI CE Jody Addah, PMP LEED-AP Port Metro Vancouver Non-shareholder, financially self- sufficient corporation established
p o r t m e t r o v a n c o u v e r.c o m 3
- Non-shareholder,
financially self- sufficient corporation established pursuant to the Canada Marine Act
- Accountable to
federal Minister of Transportation, I nfrastructure and Communities Port Metro Vancouver
p o r t m e t r o v a n c o u v e r.c o m 4
Port Metro Vancouver
- Our Mission: to lead
the growth of Canada’s Pacific Gateway in a manner that enhances the well- being of Canadians.
p o r t m e t r o v a n c o u v e r.c o m 5
- 640 km of shoreline
- 16 municipalities
- One treaty First
Nation, several
- ther First Nations
Our Jurisdiction
p o r t m e t r o v a n c o u v e r.c o m 6
I nfrastructure I nvestment
- Three key
development areas:
- North Shore
Trade Area
- South Shore
Trade Area
- Roberts Bank
Corridor
- I nvestment from
funding partners of more than $700M
p o r t m e t r o v a n c o u v e r.c o m 7
North Shore Trade Area
p o r t m e t r o v a n c o u v e r.c o m 8
Low Level Road Project
p o r t m e t r o v a n c o u v e r.c o m 9
Purpose: To provide for future increased rail capacity. Makes space for the rail expansion and installation of two new rail tracks. Closes three existing at grade rail crossings – train lengths & whistling. Constraints: Narrow corridor of interest – steep slopes/ existing road & rail.
Low Level Road Project
p o r t m e t r o v a n c o u v e r.c o m 10
Typical Section
p o r t m e t r o v a n c o u v e r.c o m 11
Low Level Road Project
Delivery: Lead: Port Metro Vancouver Project Management Services: MMM Group Technical Design Services: Stantec Consulting Contractor: B&B Heavy Civil Construction Ltd Project Cost: $101.6M Funding: Asia-Pacific Gateway & Corridor I nitiative (AGPCI ) – March 2015
p o r t m e t r o v a n c o u v e r.c o m 12
Low Level Road Project
Funding Partners: Transport Canada; Port Metro Vancouver; CN Rail; CP Rail; Translink; City of North Vancouver. Owner: City of North Vancouver – Low Level Road
- Spirit Trail
Port Metro Vancouver – Cargill Neptune overpass
p o r t m e t r o v a n c o u v e r.c o m 14
Schedule
2012 2013 2014 2015
Q1 Q2 Q3 Q4 Jan Feb Mar Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
REVISED FUNDING DEADLINE MARCH 31, 2015 ORIGINAL FUNDING DEADLINE MARCH 31, 2014 CNV COUNCIL DECISION JUNE 18
MAIN CONSTRUCTION
COMMUNICATION (ONGOING)
FINAL OPEN HOUSE SEPT 22
ROUND 4
DETAILED DESIGN FUNDING AGREEMENTS PERMITTING & APPROVALS
WE ARE HERE
TENDER
RFQ
COMMUNICATIONS (ONGOING)
p o r t m e t r o v a n c o u v e r.c o m 15
Construction - Current Status
Contract Awarded March 2013 Construction overall ~ 40% complete
- Earthworks ~ 90% complete
- Neptune/ Cargill overpass – out of the ground;
centre pier & south abutment substructure
- ngoing
- Retaining walls ~ 60% complete
Schedule for completion – 31 October 2014
p o r t m e t r o v a n c o u v e r.c o m 16
Low Level Road Project – Progress Photos
p o r t m e t r o v a n c o u v e r.c o m 17
Low Level Road Project – Progress Photos
p o r t m e t r o v a n c o u v e r.c o m 18
Low Level Road Project – Progress Photos
p o r t m e t r o v a n c o u v e r.c o m 19
p o r t m e t r o v a n c o u v e r.c o m 20
p o r t m e t r o v a n c o u v e r.c o m 21
p o r t m e t r o v a n c o u v e r.c o m 22
p o r t m e t r o v a n c o u v e r.c o m 23
p o r t m e t r o v a n c o u v e r.c o m 24
Low Level Road Project – Progress Photos
p o r t m e t r o v a n c o u v e r.c o m 25
p o r t m e t r o v a n c o u v e r.c o m 26
p o r t m e t r o v a n c o u v e r.c o m 27
p o r t m e t r o v a n c o u v e r.c o m 28
p o r t m e t r o v a n c o u v e r.c o m 29
p o r t m e t r o v a n c o u v e r.c o m 30
p o r t m e t r o v a n c o u v e r.c o m 31
p o r t m e t r o v a n c o u v e r.c o m 32
South Shore Trade Area By volume, 25% of Port cargo. By 2030, 70% container increase and 30% grain increase.
p o r t m e t r o v a n c o u v e r.c o m 33
South Shore Corridor Project
7
$75 million: Port Metro Vancouver lead Partners: Transport Canada, Canadian Pacific Railway, Canadian National Railway
p o r t m e t r o v a n c o u v e r.c o m 34
South Shore Corridor Project
Intent:
- Reduce congestion and improve traffic flows.
- Provide capacity for future rail expansion.
Constraints:
- Geography.
- Federal funding.
Port Benefits:
- Reduced congestion and delays.
- I mproved operational control and safety.
- Future additional east-west rail track.
p o r t m e t r o v a n c o u v e r.c o m 35
South Shore Corridor Project
7
Roadworks July 2012 to February 2014: at 95%
Ballantyne Staging Area Commissioner Staging Area Terminal Dock Staging Area Realigning Road Commissioner / New Brighton Commissioner / McGill
p o r t m e t r o v a n c o u v e r.c o m 36
South Shore Corridor Project
7
Stewart Street Elevated Roadway and Footbridges November 2012 to June 2014 Roadway: at 90%
800 m Roadway
- ver 10 rail switches
Build Victoria Drive Footbridge Remove Nanaimo Street Footbridge
p o r t m e t r o v a n c o u v e r.c o m 37
South Shore Corridor Project
7
Systems: Vehicle Access Control, digital cameras and fibre backbone June 2013 to June 2014: at 30%
Heatley Gate Upgrade Clark Gate Rebuild Commissioner Gate Rebuild
p o r t m e t r o v a n c o u v e r.c o m 39
Stewart Street Elevated Roadway
p o r t m e t r o v a n c o u v e r.c o m 40
Temporary Secant Pile Walls
p o r t m e t r o v a n c o u v e r.c o m 41
Main Bored Pile
p o r t m e t r o v a n c o u v e r.c o m 42
Main Bored Pile
p o r t m e t r o v a n c o u v e r.c o m 45
Reinforcement Cage
p o r t m e t r o v a n c o u v e r.c o m 46
Main Pile Concrete Poured
p o r t m e t r o v a n c o u v e r.c o m 47
Columns
p o r t m e t r o v a n c o u v e r.c o m 48
Columns and Pier Heads
p o r t m e t r o v a n c o u v e r.c o m 49
Placing Beams
p o r t m e t r o v a n c o u v e r.c o m 50
Beams in position
p o r t m e t r o v a n c o u v e r.c o m 51
Placing the Deck
p o r t m e t r o v a n c o u v e r.c o m 52
Laying Asphalt
p o r t m e t r o v a n c o u v e r.c o m 53
p o r t m e t r o v a n c o u v e r.c o m 54
Victoria Drive Footbridge
p o r t m e t r o v a n c o u v e r.c o m 55
p o r t m e t r o v a n c o u v e r.c o m 56
Powell Street Overpass Project
7
$50 million: City of Vancouver lead Partners: Port Metro Vancouver, Transport Canada, Canadian Pacific Railway, Translink
Powell Street Overpass Raymur Ave
p o r t m e t r o v a n c o u v e r.c o m 57
Powell Street Overpass Project
Intent:
- I mprove road access and safety.
- Provide space for future rail expansion.
Constraints:
- Geography.
- Federal funding.
Port Benefits:
- Future additional east-west rail track.
p o r t m e t r o v a n c o u v e r.c o m 58
Powell Street Overpass Project Hastings Street Powell Street Cordova Street Raymur Avenue
p o r t m e t r o v a n c o u v e r.c o m 59
This Summer
p o r t m e t r o v a n c o u v e r.c o m 60
Next Summer
p o r t m e t r o v a n c o u v e r.c o m 61
p o r t m e t r o v a n c o u v e r.c o m 62
Today: North Side
p o r t m e t r o v a n c o u v e r.c o m 63
Roberts Bank Corridor
p o r t m e t r o v a n c o u v e r.c o m 64
Container Capacity I mprovement Program
- I ncrease container
capacity to meet growth and demand
- I ndustrial land
densification
- Efficiency gains at
existing container facilities
- I mprovements to
road and rail infrastructure
- New container terminal
p o r t m e t r o v a n c o u v e r.c o m 65
West Coast Container Forecast
p o r t m e t r o v a n c o u v e r.c o m 66
West Coast Container Forecast
p o r t m e t r o v a n c o u v e r.c o m 67
Related Infrastructure Investments
Infrastructure Projects SFPR RBRC Total Investment $1.26B $360M Federal Contribution $365M $75M Provincial Contribution $899M $50M
p o r t m e t r o v a n c o u v e r.c o m 68
Proposed:
- 3-berth terminal
- 2.4 M TEUs per year
- Completion 2020s
Roberts Bank Terminal 2
p o r t m e t r o v a n c o u v e r.c o m 69
p o r t m e t r o v a n c o u v e r.c o m 70
MARINE TERMINAL LAYOUT
Location
p o r t m e t r o v a n c o u v e r.c o m 71
Marine Terminal Layout
p o r t m e t r o v a n c o u v e r.c o m 72
Environmental Assessment
- Mid Sept 2013: Project Description Submitted to BCEAO & CEAA
- 2020’s: Terminal Potentially Operational (phased operation possible)
p o r t m e t r o v a n c o u v e r.c o m 73
- $288M program.
- I ncrease
capacity: From 1.8M to 2.4M TEUs.
- Within existing
terminal, road and rail footprint.
73
Deltaport Terminal Road and Rail I mprovement Project
p o r t m e t r o v a n c o u v e r.c o m 74
Causeway Overpass Project
$60 million: Port Metro Vancouver Partner: Transport Canada
p o r t m e t r o v a n c o u v e r.c o m 75
Causeway Overpass Project
Intent:
- I mprove road access and safety.
- I mproved rail access and safety.
Constraints:
- Geography.
- Federal funding.
Port Benefits:
- Reduced congestion and delays.
- I ncreased capacity: 200,000 TEUs.
- I mproved operational control and safety.
p o r t m e t r o v a n c o u v e r.c o m 76
p o r t m e t r o v a n c o u v e r.c o m 77
Port Metro Vancouver
- Building the Pacific
gateway.
- Supporting global
trade.
- Delivering our
Mission.
p o r t m e t r o v a n c o u v e r.c o m 78