Building Business Building Business in Nevada in Nevada MDW - - PowerPoint PPT Presentation

building business building business in nevada in nevada
SMART_READER_LITE
LIVE PREVIEW

Building Business Building Business in Nevada in Nevada MDW - - PowerPoint PPT Presentation

Building Business Building Business in Nevada in Nevada MDW TSX-V & NYSE MKT April 2013 FORW FORWARD LOOKING DISCLAIMER ARD LOOKING DISCLAIMER This presentation contains forward-looking statements about the Company and its


slide-1
SLIDE 1

April 2013

MDW TSX-V & NYSE MKT

Building Business Building Business in Nevada in Nevada

slide-2
SLIDE 2

FORW FORWARD LOOKING DISCLAIMER ARD LOOKING DISCLAIMER

2

This presentation contains forward-looking statements about the Company and its business. Forward looking statements are statements that are not historical facts and include, but are not limited to, statements about the Company's intended work plans for its projects and resource estimates. The forward-looking statements in this presentation are subject to various risks, uncertainties and other factors that could cause the Company's actual results or achievements to differ materially from those expressed in or implied by forward looking statements. These risks, uncertainties and other factors include, without limitation, risks related to the timing and completion of the Company's intended work plans for its projects, risks related to fluctuations in gold prices; uncertainties related to raising sufficient financing to fund the planned work in a timely manner and on acceptable terms; changes in planned work resulting from weather, logistical, technical

  • r other factors; the possibility that results of work will not fulfill expectations and realize the perceived potential of the Company's properties; uncertainties

involved in the interpretation of drilling results and other tests and the estimation of gold resources and reserves; the possibility that required permits may not be

  • btained on a timely manner or at all; the possibility that capital and operating costs may be higher than currently estimated and may preclude commercial

development or render operations uneconomic; the possibility that the estimated recovery rates may not be achieved; risk of accidents, equipment breakdowns and labor disputes or other unanticipated difficulties or interruptions; the possibility of cost overruns or unanticipated expenses in the work programs; and other factors identified in the Company's SEC filings and its filings with Canadian securities regulatory authorities. Forward-looking statements are based on the beliefs,

  • pinions and expectations of the Company's management at the time they are made, and other than as required by applicable securities laws, the Company

assumes no obligation to update its forward-looking statements if those beliefs, opinions expectations, or other circumstances should change. Cautionary note to U.S. investors concerning estimates of reserves and resources: This presentation and the technical reports referred to in this presentation use the terms "resource", "reserve", "measured resources", "indicated resources" and "inferred resources", which are terms defined under Canadian National Instrument 43-101 and the Canadian Institute of Mining and Metallurgy Classification system. Estimates of mineral resources in this presentation and in the technical reports referred to in this presentation have been prepared in accordance with NI 43-101 and such definitions differ from the definitions in U.S. Securities and Exchange Commission ("SEC") Industry Guide 7. Under SEC Industry Guide 7 standards, a "final" or "bankable" feasibility study is required to report reserves, the three-year historical average price is used in any reserve or cash flow analysis to designate reserves and the primary environmental analysis or report must be filed with the appropriate governmental authority. Mineral resources are not mineral reserves and do not have demonstrated economic viability. We advise investors that while those terms are recognized and required by Canadian regulations, the SEC does not recognize them. U.S. investors are cautioned not to assume that any part or all of mineral deposits in these categories will ever be converted into reserves as defined in the SEC's Guide 7. In addition, "inferred resources" have a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred mineral resource will ever be upgraded to a higher category. Under Canadian rules, estimates of inferred mineral resources may not form the basis of feasibility or pre-feasibility studies, except in rare cases. U.S. investors are cautioned not to assume that part or all of an inferred resource exists, or is economically

  • r legally minable. The SEC normally only permits issuers to report mineralization that does not constitute SEC Industry Guide 7 compliant "reserves" as in-place

tonnage and grade without reference to unit measures. It cannot be assumed that all or any part of mineral deposits in any of the above categories will ever be upgraded to Guide 7 compliant reserves. Accordingly, disclosure in this presentation and in the technical reports referred to in this presentation may not be comparable to information from U.S. companies subject to the reporting and disclosure requirements of the SEC.

slide-3
SLIDE 3

MIDW MIDWAY GOLD OPPORTUNITY Y GOLD OPPORTUNITY

3

Veteran Nevada Management Team Nevada = Stable Mining Jurisdiction Strong Cash Position Two Near-Term Producing Properties Simple, Low Cost Projects Near-T Near-Term Gold Production erm Gold Production è è Expansion from Cash Flow Expansion from Cash Flow Strong Partnership with Barrick Gold

slide-4
SLIDE 4

THE MIDW THE MIDWAY TEAM Y TEAM

4

Ken Brunk - Chairman, President, and CEO

  • +40 years of proven experience
  • Managed development of over 25 mines
  • Former Senior Vice President at Newmont
  • Executive positions at Romarco, Harrison Western,

Bateman Engineering, Unimin, and Owens-Illinois

Tom Williams - VP Environmental Affairs

  • +32 years environmental planning and

permitting experience at Homestake, SRK, Golder, and Walsh Environmental

  • Won independent awards for reclamation of

gold mining projects

Fritz Schaudies – CFO

  • +35 years financial leadership experience in

mining and real estate

  • Formerly with Newmont, Echo Bay Mines, Arch

Mineral, Morrison Knudsen, and Consolidation Coal Company (now Consol Energy)

Roger Gross – VP Nevada Operations

  • +30 years mine engineering and mine

management experience in Nevada and internationally

  • Formerly with American Colloid, Newmont, and

Freeport McMoran

Rick Moritz - Senior VP of Operations

  • +30 years experience in process engineering,

mine management, and on-site construction/ commissioning for 6 mines

  • Formerly with Royal Gold, Bateman Engineering,

Nerco Minerals, Falcon Exploration, and Gustavson Associates

Grant Shelton- Director of Projects

  • +40 years mine engineering and construction

management experience on over 24 projects, national and international

  • Served as project manager for Climax

molybdenum re-start - $700 mm construction project

Bill Neal - VP Geological Services

  • +30 years exploration geology
  • Former senior geologist for Battle Mountain Gold

and VP Exploration for Hanover Gold

  • Instrumental in four of Midway's Spring Valley

discoveries

+ 240 YEARS IN MINING + 240 YEARS IN MINING THIS IS EXPERIENCE THIS IS EXPERIENCE

slide-5
SLIDE 5

MUL MUL TIPLE ADV TIPLE ADVANCED ST ANCED STAGE AGE NEV NEVADA GOLD PROJECTS ADA GOLD PROJECTS

5

Spring Valley

Ely

Gold Rock Pan

Infrastructure decreases capital requirements and lowers operating costs.

Communities Paved Highways Grid Power Communications Excellent Water Conditions Mining-Experienced Labor Pool

ALL PROJECTS HA ALL PROJECTS HAVE INFRASTRUCTURE NEARBY VE INFRASTRUCTURE NEARBY

slide-6
SLIDE 6

PA PAN – MIDWAY’S 1st

st MINE

MINE

6

PROJECT A PROJECT ATTRIBUTES TTRIBUTES RESERVES & RESOURCES SUMMARY RESERVES & RESOURCES SUMMARY

(1) Resources as per Independent NI 43-101 Updated Resource Technical Report by Gustavson Associates, LLC (October, 2011). Assumes cutoff grade of 0.14 g/t (2) Reserves as per Independent NI 43-101 compliant Feasibility Study by Gustavson Associates, LLC (November, 2011). Assumes gold price of US$1,200/oz and cutoff grade of 0.27 g/t (South Pan) and 0.21 g/t (North Pan)

P&P Reserves are included in the M&I Resources

Simple, Low Cost Project

Open Pit/Heap Leach Low Capex to Build Starts at Surface = Low Strip (1.8:1) 60% of all Tons are Down Hill Haul Short Haul Distances Oxide Ore – Simple Processing 45 Day Leach Cycle No De-Watering of Pit Required Targeting Production in 2014

Resources(1) Tonnes Grade Contained

(‘000s) (g/t) (‘000s oz)

Measured

36,920 0.49 579

Indicated

43,118 0.40 551

M&I

80,037 0.44 1,130

Inferred

3,928 0.36 45

Reserves(2) Tonnes Grade Contained

(‘000s) (g/t) (‘000s oz)

Proven

25,245 0.60 487

Probable

23,067 0.51 377

P&P

48,311 0.56 864

slide-7
SLIDE 7

PA PAN – FEASIBILITY STUDY NOVEMBER 2011(1)

(1)

7

Project Parameters Project Capex(2) $99 mm Mine Life 9 years Life-Of-Mine Production (recovered) 648,800oz

  • Avg. Annual Production

81,000oz Total Cash Cost(3) $585/oz Fully Loaded, All-In Cost(4) $824/oz Average Gold Recovery 75% LIFE OF MINE SUMMARY LIFE OF MINE SUMMARY

(1) As per Independent NI 43-101 compliant Feasibility Study by Gustavson Associates, LLC (November, 2011) (2) Includes $8.2 mm of working capital and $6.8 mm contingency (3) Includes royalties, state tax and 5% contingency (4) Includes total cash cost, initial capital and sustaining capital costs

Incorporates 35% Federal Tax and 5% State Tax

PROJECT ECONOMICS (AFTER T PROJECT ECONOMICS (AFTER TAX) AX)

$0 $50 $100 $150 $200 $250 $300 $350 $400 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

$1,200 $1,550 $1,725 $1,900

NPV ($ Millions) Project IRR Gold Price

IRR

After Tax

Gold Price $1,200/oz $1,550/oz $1,725/oz $1,900/oz NPV5% $123 mm $235 mm $290 mm $344 mm IRR 32% 56% 67% 79% Payback 2.6 yrs 1.7 yrs 1.4 yrs 1.2 yrs

slide-8
SLIDE 8

PA PAN – CAPEX

8

Mine Equipment $ 29.5 mm Processing Plant $ 35.8 mm Infrastructure $ 14.1 mm Owners Costs $ 4.8 mm Working Capital $ 8.2 mm Contingency $ 6.8 mm Total $99 mm

CAPIT CAPITAL COMPONENTS AL COMPONENTS FINANCIAL POSITION FINANCIAL POSITION

Cat 777G 100 ton truck Cat 993K loader Well Funded Evaluating Future Financing Options No More Dilutive Equity

slide-9
SLIDE 9

PA PAN – OUTLOOK

9

OPTIMIZE ¡

  • Ongoing ¡

¡ FINANCE ¡

  • Expected ¡Mid-­‑Year ¡

to ¡be ¡in ¡Place ¡

PERMIT ¡

  • An7cipate ¡Q4 ¡

Record ¡of ¡Decision ¡

CONSTRUCT ¡

  • On ¡Track ¡for ¡Q4 ¡

PRODUCE ¡ MID-­‑2014 ¡

MILESTONES TO PRODUCTION MILESTONES TO PRODUCTION

slide-10
SLIDE 10

PA PAN – PERMITTING ON TRACK

ENVIRONMENT ENVIRONMENTAL IMP AL IMPACT ST ACT STATEMENT (EIS) PROCESS TEMENT (EIS) PROCESS Pan Project NEPA Process 2010 2011 2012 2013

  • Base line studies

✔ ¡

  • Submit mine plan of operations

✔ ¡

  • Completeness review by BLM

✔ ¡

  • 3rd Party contractor selection

✔ ¡

  • Publish notice in Federal Register

✔ ¡

  • Public Scoping Meetings

✔ ¡

  • Preparation of Draft EIS

✔ ¡

  • Publish notice of Draft EIS in Federal Register

  • Draft EIS public meetings/comments
  • Address comments for Final EIS
  • Publish notice of Final EIS in Federal Register
  • Final EIS public meetings/comments
  • EIS Record of Decision
  • Begin Construction

Current Stage

PAN ATTRIBUTES DE-RISK THE PROCESS No impact on surface or ground water: No 404 permit required No ARD potential

The Long & Labor Intensive Piece – Analysis – is almost done! 10

slide-11
SLIDE 11

GOLD ROCK – MIDW GOLD ROCK – MIDWAY’S 2 Y’S 2nd

nd MINE

MINE

11

WHY NOW WHY NOW

  • Sister project to Pan – located 8km away
  • Targeting first production in 2016
  • Pan-style deposit

– Shallow mineralization = low strip – Oxide Ore = simple processing – Pan-style economics expected

  • Low Capex project
  • Open Pit / Heap Leach
  • Nearby infrastructure & no de-watering

– Potential to be larger/higher grade than Pan

  • Leveraging Pan development and permitting

experience to Gold Rock

Eureka

Gold Rock Pan

N

10 km GOLD ROCK PROJECT LOCA GOLD ROCK PROJECT LOCATION TION

slide-12
SLIDE 12

GOLD ROCK – THE PROJECT GOLD ROCK – THE PROJECT

12

Resources(1) Tonnes Grade Contained

(‘000s) (g/t) (‘000s oz)

Indicated 12,968 0.74 310 Inferred 17,894 0.58 331

(1) Resources as per Independent NI 43-101 compliant Technical Report by Gustavson Associates, LLC (February, 2012). Assumes cutoff grade of 0.27 g/t

GOLD ROCK – EASY JUNIOR OPEN PIT GOLD ROCK – EASY JUNIOR OPEN PIT

  • Initial resource limited to historic drilling
  • Below and on strike with historic Easy Jr pit
  • Open in all directions
  • 2012 drilling identified new mineralized extensions

Easy ¡Jr ¡Pit ¡

OUTLINE OF GOLD RESOURCE AREA OUTLINE OF GOLD RESOURCE AREA RESOURCES SUMMARY RESOURCES SUMMARY

slide-13
SLIDE 13

GOLD ROCK – THE T GOLD ROCK – THE TARGETS ARGETS

13

DRILLING A DRILLING AT GOLD ROCK T GOLD ROCK

Optimizing shareholder return by shortening time to production and capitalizing on high gold price – Drill 20,000 m near existing resource – Initiate EIS process – Start baseline studies – Develop conceptual mine plan – Resource Update – Preliminary Economic Assessment – Production in 2016 – Mining rate: 80-100,000 oz/year

Phase 2 Drill Target Phase 1 Drill Target

12 ¡km Resource Phase ¡2 Drill ¡Targets Phase ¡1 Drill ¡Targets 2.5 ¡km

OBJECTIVE OBJECTIVE 2013 PROGRAM 2013 PROGRAM

slide-14
SLIDE 14

SPRING V SPRING VALLEY – ALLEY – BARRICK EARNING IN TO A MIDW BARRICK EARNING IN TO A MIDWAY ASSET Y ASSET

14

  • Required expenditures to earn-in (only if met)

– $30 mm by end of 2013 to earn 60% interest – $38 mm by end of 2014 to earn 70% interest

  • Barrick has accelerated their rate of earn-in

– 60% earn-in expected Q1-Q2 2013 – 70% earn-in expected Q3-Q4 2013

  • Midway right to be carried to commercial production

– Midway gives up additional 5% – Retains 25% interest – ABX right to recover Midway capital from 90% of Midway cash flows – Interest rate of Prime + 2%

BARRICK EXPENDITURE REQUIREMENTS BARRICK EXPENDITURE REQUIREMENTS GOLD FROM CUTTINGS GOLD FROM CUTTINGS DRILLING A DRILLING AT SPRING V T SPRING VALLEY ALLEY

slide-15
SLIDE 15

SPRING V SPRING VALLEY – THE PROJECT ALLEY – THE PROJECT

15

  • Barrick is Midway’s Partner and Project Operator
  • Large Resource and Growing Larger

– Potentially World-Class Deposit – Expansion Potential: North, South, Depth

  • Barrick Development Team – Making a Mine

RESOURCES SUMMARY RESOURCES SUMMARY Resources(1) Tonnes Grade Contained

(‘000s) (g/t) (‘000s oz)

Measured 59,032 0.49 931 Indicated 85,793 0.45 1,229 M&I 144,825 0.46 2,160 Inferred 103,935 0.59 1,971

(1) Resources as per Independent NI 43-101 compliant Technical Report by Gustavson Associates, LLC (May, 2011). Assumes cutoff grade of 0.14 g/t

RESOURCE AREA RESOURCE AREA

Exploration Targets

Expanded Barrick Permit Boundary

slide-16
SLIDE 16

SPRING V SPRING VALLEY – WHY IT WILL WORK ALLEY – WHY IT WILL WORK

16

  • Work completed in 2012

– Exploration drilling – Deposit modeling – Metallurgical tests (in progress) – Hydrology studies – Internal scoping study (in progress)

  • Barrick to complete Internal Scoping Study
  • Midway to complete Resource Update
  • Midway to assess 25% carry forward option

N

Lovelock Florida Canyon Relief Canyon Rochester

Spring Valley

  • Nearby community
  • Paved road to site
  • Power line on site
  • Nearby Interstate hwy
  • Nearby railroad
  • Known mining area

10 km

BARRICK 2012 BARRICK 2012 PLAN FOR 2013 PLAN FOR 2013 INFRASTRUCTURE SUPPORTS PROJECT GRADE INFRASTRUCTURE SUPPORTS PROJECT GRADE

slide-17
SLIDE 17

CAPIT CAPITAL MARKETS OVERVIEW AL MARKETS OVERVIEW

17

Barclays Hale Capital BlackRock Ingalls & Snyder BNY Mellon State Street Cambrian Capital Sun Valley Gold Davenport Securities Van Eck Deans Knight Vanguard Franklin Templeton Northern Trust

COMMON SHARE STRUCTURE COMMON SHARE STRUCTURE(2)

(2)

Shares Outstanding (Basic) 128,251,298 Options 8,335,834 Warrants 6,130,781 Fully Diluted 142,907,913

PREFERRED SHARE STRUCTURE PREFERRED SHARE STRUCTURE

Preferred Shares(3) 37,837,838

8310 South Valley Highway, Suite 280, Englewood, Colorado, 80112 │Office: 720.979.0900 │Website: www.midwaygold.com

KEY INVESTORS - 56% KEY INVESTORS - 56%(4)

Symbol (TSX-V/NYSE MKT) MDW Share Price(1) $1.11 Shares Outstanding (Basic) 128.0M Market Capitalization $191.1mm

(1) As of close on February 28, 2013 (2) As of September 30th, 2012 (3) Convertible to Common Shares as of December 13, 2012 (4) Assumes full dilution

ANAL ANALYST COVERAGE YST COVERAGE

Haywood Securities Stifel Nicolaus RBC Capital Markets Dahlman Rose Stonecap Securities Jacobs Securities

MARKET ST MARKET STATISTICS TISTICS

slide-18
SLIDE 18

MIDW MIDWAY GOLD OPPORTUNITY Y GOLD OPPORTUNITY

18

Veteran Nevada Management Team Nevada = Stable Mining Jurisdiction Strong Cash Position Two Near-Term Producing Properties Simple, Low Cost Projects Near-T Near-Term Gold Production erm Gold Production è è Expansion from Cash Flow Expansion from Cash Flow Strong Partnership with Barrick Gold