The CS Project Developing a new source of high quality natural pozzolan in Nevada CS Project Location & Logistics Tonopah, Nevada Northern Nevada Northern California UP Rail Head Thorne Nevada CS PROJECT Tonopah Southern Nevada
CS Project – Location & Logistics
Northern Nevada Northern California Southern California Southern Nevada
UP Rail Head Thorne Nevada
Location:
- Adjacent to County maintained road
- Adjacent to 120KV power line
- 9 miles off Highway 6
- 20 minutes from Tonopah (regional town)
CS PROJECT Tonopah Tonopah, Nevada
3
CS Project – Geology
Tuff & Tephra Pozzolan and Perlite (pozzolan) deposits developed during the build up of a 7 million-year-old silicic volcano.
17 May 2019
4 Sunrise Resources plc
CS Project – Main Zone Pozzolan
21 February 2019
Main Zone
Northeast Zone In the Main Zone large deposits of pozzolan form hills and extend below the level of the plane for at least 150ft Truck for scale
Main Zone – Tephra Type Pozzolan
5 Sunrise Resources plc
Tephra type natural pozzolan Main Zone
17 May 2019
CS Project - Tuff Zone
Tuff Zone
In the Tuff Zone large deposits of pozzolan extend along the hillside and to depths of at least 200ft in drill holes Truck for scale
Tuff Zone – Tuff Type Pozzolan
7 Sunrise Resources plc
Tuff type natural pozzolan Tuff Zone
17 May 2019
CS Project - Drilling & Trenching
Sunrise Resources plc 8
- 33 drill holes in Main Zone, Tuff Zone & Northeast Zone
- 11 trenches completed in and around Main Zone
- Over 150 composite drill samples submitted for testwork
1 km
.
2017 drill hole 2018 drill hole 2017 trench
17 May 2019
9 Sunrise Resources plc
CS Testwork – ASTM C618
Over 150 composite drill samples and surface samples have been strength tested at Magmatics Inc. according to the methodology set out in ASTM C618. Samples typically ground to a D50 size of 10-12 micron: A mini-bulk sample of the tephra pozzolan has been tested at times up to 12 months with the following result:
Meets the requirements of ASTM C618
CS Average Commercially available Natural Pozzolan A Commercially available Natural Pozzolan B 7-day SAI 82% 82% 75% 28-day SAI 91% 93% 91% CS Average Commercially available Natural Pozzolan A Commercially available Natural Pozzolan B Si+Al+Fe Oxide 84.7 81.0 86.2 SiO2% 70.4 69.2 73.3 Al2O3% 12.5 10.8 12.0 Fe2O3% 1.9 1.0 0.8 CaO% 1.5 0.9 1.9 K2O% 4.2 5.08 4.6 Na2O% 3.1 2.13 4.5 SO3% 0.0 0.0 0.3
17 May 2019
Sample Type 7 day SAI 28 day SAI 6-month SAI 12-month SAI Tephra pozzolan 85% 100% 107% 116% Continuing strength gain
Selective mining Can give higher values
10
CS Testwork – ASTM C618 & AASHTO M295
1 km
Independent Certification Tuff Zone Independent Certification Main Zone
ASTM C39-96 Compressive Strength test Mix design strength = 4000 psi Cement replacement Level Fly ash CS Pozz 15% 15% Strength increase over fly ash Strength at 7 days, (psi) 1,810 2,680 48% Strength at 28 days, (psi) 3,720 4,510 21% Strength at 56 days, (psi) 4,373 5,060 16% Fly ash CS Pozz 15% 25% Strength increase over fly ash Strength at 7 days, (psi) 1,810 2,035 12% Strength at 28 days, (psi) 3,720 3,900 5% Strength at 56 days, (psi) 4,373 4,750 9%
11 Sunrise Resources plc
CS Testwork – ASTM C39-96
1 km
Like-for-like 15% replacement CS natural pozzolan outperforms fly ash in concrete test 25% replacement of CS natural pozzolan stronger than 15% replacement with fly ash* Concrete cylinders - Compressive strength – Mix design strength 4,000 psi
17 May 2019
*control using well known fly ash widely used in California
Testwork – ASR Mitigation: ASTM C1567
1 km
Main Zone Pozzolan Tuff Zone Pozzolan
CS Project natural pozzolan is an excellent mitigator of ASR
Test results using strongly “reactive” aggregate
17 May 2019 12 Sunrise Resources plc
▪ 100t bulk sample ground in production clinker mill to produce a finished ground pozzolan product. ▪ Tested for compliance with ASTM C618. ▪ Scale up from lab results confirmed.
13 Sunrise Resources plc
CS Testwork – Commercial Grinding Trials
17 May 2019
14
CS Project - Mine Planning
Pozzolan Pozzolan
Sunrise Resources plc
- Deposits of pozzolan crop out at surface
- Open pit mining by dozer and front end loader
- Phase 1 Mine Plan - Early low cost production - removal of hills
- Low waste/ore ratio
- Mining no more than 150ft deep from surface
- No water encountered to 180ft in drilling – dry mine
17 May 2019
Mine Design
15 Sunrise Resources plc 17 May 2019
Mine Design – Permitting Plan of Operations
27-year mine plan includes four-phase pit design targeting production of 14.5 million tons of pozzolan at rates up to 500,000t per year.
16 Sunrise Resources plc
The Mine Plan does not include the extensive areas
- f pozzolan in northern Main Zone, Northeast Zone
and western Tuff Zone.
Tuff Zone Main Zone
North
17 May 2019
Mine permitting on track for completion in 4th quarter
- f 2019.
- Project is on Federally owned land - Lead regulatory authority is
US Bureau of Land Management (BLM).
- No biological or cultural impediments to development identified
by baseline biological and cultural surveys.
- Plan of Operations will allow flexibility on production options and
initial 27 year mine life – submitted.
- Following shorter Environmental Assessment path rather than
longer Environmental Impact Statement.