Briefing on Californias Public Safety Power Shutoff (PSPS) program - - PowerPoint PPT Presentation

briefing on california s public safety power shutoff psps
SMART_READER_LITE
LIVE PREVIEW

Briefing on Californias Public Safety Power Shutoff (PSPS) program - - PowerPoint PPT Presentation

Briefing on Californias Public Safety Power Shutoff (PSPS) program John Phipps Director, Real Time Operations Board of Governors Meeting General Session July 24, 2019 The IOUs have Public Safety Power Shutoff (PSPS) programs to protect


slide-1
SLIDE 1

Briefing on California’s Public Safety Power Shutoff (PSPS) program

John Phipps Director, Real Time Operations Board of Governors Meeting General Session July 24, 2019

slide-2
SLIDE 2

The IOU’s have Public Safety Power Shutoff (PSPS) programs to protect public safety

  • The CPUC has reviewed & approved the IOU’s plans
  • The IOU’s PSPS plans include all voltage levels (distribution to 500kV)
  • PSPS triggers are based on meteorological data, vegetation, terrain, etc.
  • IOU’s evaluate conditions and determine which circuits will be de-energized
  • IOU’s direct the circuit de-energization at PSPS triggers
  • IOU’s are responsible for direct load management on circuit de-energization

– Direct load management happens when the circuit feeding the load is de-energized Note: These actions are independent of the ISO’s responsibilities

Page 2

slide-3
SLIDE 3

California ISO Principles

  • Facilitate Public Safety Power Shut-off outages
  • Analyze, identify & communicate PSPS impacts and required

mitigation to the IOU, if sufficient time is given

  • Maintain reliability of the bulk electric system, which may

require additional load management

  • Confine PSPS impacts to the initiating IOU to the extent

possible

  • Confine PSPS impacts to ISO BA to the extent possible

Page 3

slide-4
SLIDE 4

A PSPS may have minimal impact on the BES PSPS Scenario 1 – 60kV & distribution level

Page 4

Energy Capacity

ISO energy & transmission capacity available to meet demand

Demand

  • 200 MW of customer demand will be de-energized

by PG&E

  • No impact to ISO generation or transmission

Trans- mission Capacity

slide-5
SLIDE 5

Trans- mission Capacity Energy Capacity Demand

A PSPS may have a significant impact on the BES PSPS Scenario 2 – BES level

Page 5

ISO energy & transmission capacity unable to meet demand

  • 2000 MW of customer demand will be de-energized

by PG&E

COI Diablo Cyn BANC

  • BANC BA will lose 900 of imports, and need to de-

energize 400 MW of load to re-balance their system

  • 2500 MW of load will be ordered off by ISO
  • 3200 MW of transmission capacity will be lost (COI)
  • 2200 MW of generation will be forced off (Diablo Cyn)

ISO will order 400MW of additional load de-energized to provide energy to BANC

slide-6
SLIDE 6

PSPS Restoration

  • The IOU’s PSPS plans require a patrol of the circuits that

were de-energized before being re-energized.

  • Complete restoration may take several days

Page 6