briefing on california s public safety power shutoff psps
play

Briefing on Californias Public Safety Power Shutoff (PSPS) program - PowerPoint PPT Presentation

Briefing on Californias Public Safety Power Shutoff (PSPS) program John Phipps Director, Real Time Operations Board of Governors Meeting General Session July 24, 2019 The IOUs have Public Safety Power Shutoff (PSPS) programs to protect


  1. Briefing on California’s Public Safety Power Shutoff (PSPS) program John Phipps Director, Real Time Operations Board of Governors Meeting General Session July 24, 2019

  2. The IOU’s have Public Safety Power Shutoff (PSPS) programs to protect public safety • The CPUC has reviewed & approved the IOU’s plans • The IOU’s PSPS plans include all voltage levels (distribution to 500kV) • PSPS triggers are based on meteorological data, vegetation, terrain, etc. • IOU’s evaluate conditions and determine which circuits will be de-energized • IOU’s direct the circuit de-energization at PSPS triggers • IOU’s are responsible for direct load management on circuit de-energization – Direct load management happens when the circuit feeding the load is de-energized Note: These actions are independent of the ISO’s responsibilities Page 2

  3. California ISO Principles • Facilitate Public Safety Power Shut-off outages • Analyze, identify & communicate PSPS impacts and required mitigation to the IOU, if sufficient time is given • Maintain reliability of the bulk electric system, which may require additional load management • Confine PSPS impacts to the initiating IOU to the extent possible • Confine PSPS impacts to ISO BA to the extent possible Page 3

  4. A PSPS may have minimal impact on the BES PSPS Scenario 1 – 60kV & distribution level • 200 MW of customer demand will be de-energized by PG&E • No impact to ISO generation or transmission Trans- Energy mission Demand Capacity Capacity ISO energy & transmission capacity available to meet demand Page 4

  5. A PSPS may have a significant impact on the BES PSPS Scenario 2 – BES level • 2000 MW of customer demand will be de-energized COI by PG&E • 2200 MW of generation will be forced off (Diablo Cyn) • 3200 MW of transmission capacity will be lost (COI) • 2500 MW of load will be ordered off by ISO BANC • BANC BA will lose 900 of imports, and need to de- energize 400 MW of load to re-balance their system Trans- Energy mission Demand Capacity Capacity Diablo Cyn ISO energy & ISO will order 400MW of additional load transmission de-energized to provide energy to BANC capacity unable to meet demand Page 5

  6. PSPS Restoration • The IOU’s PSPS plans require a patrol of the circuits that were de-energized before being re-energized. • Complete restoration may take several days Page 6

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend