Big Stone Plant AQCS Project Update South Dakota Public Utilities - - PowerPoint PPT Presentation

big stone plant aqcs project update
SMART_READER_LITE
LIVE PREVIEW

Big Stone Plant AQCS Project Update South Dakota Public Utilities - - PowerPoint PPT Presentation

Big Stone Plant AQCS Project Update South Dakota Public Utilities Commission November 25, 2014 1 2 Plant quick facts Located by Big Stone City near Milbank, SD Jointly owned by: Montana-Dakota Utilities Co. (22.7%)


slide-1
SLIDE 1

Big Stone Plant AQCS Project Update

South Dakota Public Utilities Commission

November 25, 2014

1

slide-2
SLIDE 2

2

slide-3
SLIDE 3

Plant quick facts

  • Located by Big Stone City near Milbank, SD
  • Jointly owned by:

– Montana-Dakota Utilities Co. (22.7%) – NorthWestern Energy (23.4%) – Otter Tail Power Company, operating agent, (53.9%)

  • Baseload resource for all three companies

– Available around the clock – Serves 298,500 customers in Minnesota, North Dakota, South Dakota, and Montana – Has an excellent environmental compliance record

3

slide-4
SLIDE 4

Environmental requirements

  • Regional haze

– Improve visibility in Class I areas – Requires installation of Best Available Retrofit Technology (BART) - see slide 5

  • Mercury and Air Toxics Standards (MATS)

– Reduce emissions of mercury, other toxins – Use activated carbon injection system (ACI) – Will reduce mercury more than 90 percent – Compliance by 2015

4

slide-5
SLIDE 5

BART for Big Stone Plant

  • Install a flue gas desulphurization

system (FGD)

  • Install a selective catalytic reduction

system (SCR)

  • Use baghouse for particulate control
  • Reduce SO2 and NOx approximately

90 percent

5

slide-6
SLIDE 6

6

slide-7
SLIDE 7

Project execution

  • Sargent & Lundy Design Engineer
  • Otter Tail/Sargent & Lundy

procurements

  • Graycor – construction – target price
  • Otter Tail Construction Management

7

slide-8
SLIDE 8

Safety

Hours Recordable Lost Near First Time Miss Aid Graycor 1,154,301 3 10 13 Project Team & Cont. 91,553 0 0 0 Engineering 164,223 0 0 0 Total 1,410,007 3 10 13

  • OSHA rate .43 (recordables), 0 lost time
  • Zero Injury Safety Award for 2013, presented in October in

Washington, D.C.

KPI goal 1.0 OSHA rate

8

slide-9
SLIDE 9

Budget (total project)

  • Original budget

$491M

  • Budget as of 3/01/13

$405M

  • Budget as of 3/01/14

$384M

9

slide-10
SLIDE 10

Construction

  • Approximately 80% complete
  • Staffing 425 Graycor employees
  • Staffing 25 construction management/

commissioning

  • Commissioning effort started
  • SCR – final assembly, piping, wiring, and

insulation

  • Scrubber – installing inlet ducts, and

insulation

  • Baghouse – piping, wiring, and insulation

10

slide-11
SLIDE 11

11 2013-08-21 Steel erection CFB, WA/PL 2014-08-27 Plant southwest view, WA/PL, CFB, S SCR 2013-08-17 Concrete finishing on baghouse 2014-08-29 CFB & baghouse top view

slide-12
SLIDE 12

12 2013-08-23 North SCR 2014-08-27 North SCR 2013-10-01 Ammonia foundation formwork 2014-07-03 Ammonia system

slide-13
SLIDE 13

13 2013-08-29 Center SCR concrete placement 2014-08-20 Center SCR grating install 2013-08-23 ID fan 1A foundation 2014-08-20 ID fan 1B

slide-14
SLIDE 14

14 2014-05-14 Setting aux boiler stack 2014-05-18 Installing new DC MCC 2014-08-15 Scrubber outlet transition elbow T2, heaviest lift 2014-08-29 ID fan duct support steel – Notice IW on top beam!

slide-15
SLIDE 15

15

Winter of 1975

slide-16
SLIDE 16

16

2013-10-01 Aerial shot

slide-17
SLIDE 17

17

2014-08-15 Aerial shot

slide-18
SLIDE 18

18

2014-08-15 Aerial shot

slide-19
SLIDE 19

19

2014-10-15 Aerial photo

slide-20
SLIDE 20

Timeline 2015

  • March 1 – June 9

Tie-in outage

  • AQCS tie-in
  • $50M AQCS boiler work
  • Turbine generator inspection
  • Normal outage work
  • Other capital projects
  • June 9 – Sept. 30

Start-up – tuning – testing

  • October 1

Commercial operation date

20

slide-21
SLIDE 21

Remaining work

  • Demo: existing baghouse, ash silo, ID

fans

  • Site restoration
  • Units of property
  • Project closeout

21

slide-22
SLIDE 22

22