big stone plant aqcs project update
play

Big Stone Plant AQCS Project Update South Dakota Public Utilities - PowerPoint PPT Presentation

Big Stone Plant AQCS Project Update South Dakota Public Utilities Commission November 25, 2014 1 2 Plant quick facts Located by Big Stone City near Milbank, SD Jointly owned by: Montana-Dakota Utilities Co. (22.7%)


  1. Big Stone Plant AQCS Project Update South Dakota Public Utilities Commission November 25, 2014 1

  2. 2

  3. Plant quick facts • Located by Big Stone City near Milbank, SD • Jointly owned by: – Montana-Dakota Utilities Co. (22.7%) – NorthWestern Energy (23.4%) – Otter Tail Power Company, operating agent, (53.9%) • Baseload resource for all three companies – Available around the clock – Serves 298,500 customers in Minnesota, North Dakota, South Dakota, and Montana – Has an excellent environmental compliance record 3

  4. Environmental requirements • Regional haze – Improve visibility in Class I areas – Requires installation of Best Available Retrofit Technology (BART) - see slide 5 • Mercury and Air Toxics Standards (MATS) – Reduce emissions of mercury, other toxins – Use activated carbon injection system (ACI) – Will reduce mercury more than 90 percent – Compliance by 2015 4

  5. BART for Big Stone Plant • Install a flue gas desulphurization system (FGD) • Install a selective catalytic reduction system (SCR) • Use baghouse for particulate control • Reduce SO 2 and NOx approximately 90 percent 5

  6. 6

  7. Project execution • Sargent & Lundy Design Engineer • Otter Tail/Sargent & Lundy procurements • Graycor – construction – target price • Otter Tail Construction Management 7

  8. Safety Hours Recordable Lost Near First Time Miss Aid Graycor 1,154,301 3 0 10 13 Project Team & Cont. 91,553 0 0 0 0 Engineering 164,223 0 0 0 0 Total 1,410,007 3 0 10 13 • OSHA rate .43 (recordables), 0 lost time • Zero Injury Safety Award for 2013, presented in October in Washington, D.C. KPI goal 1.0 OSHA rate 8

  9. Budget (total project) • Original budget $491M • Budget as of 3/01/13 $405M • Budget as of 3/01/14 $384M 9

  10. Construction • Approximately 80% complete • Staffing 425 Graycor employees • Staffing 25 construction management/ commissioning • Commissioning effort started • SCR – final assembly, piping, wiring, and insulation • Scrubber – installing inlet ducts, and insulation • Baghouse – piping, wiring, and insulation 10

  11. 2013-08-21 Steel erection CFB, WA/PL 2014-08-27 Plant southwest view, WA/PL, CFB, S SCR 2014-08-29 CFB & baghouse top view 2013-08-17 Concrete finishing on baghouse 11

  12. 2013-08-23 North SCR 2014-08-27 North SCR 2013-10-01 Ammonia foundation formwork 2014-07-03 Ammonia system 12

  13. 2013-08-29 Center SCR concrete placement 2014-08-20 Center SCR grating install 2014-08-20 ID fan 1B 2013-08-23 ID fan 1A foundation 13

  14. 2014-08-15 Scrubber outlet transition elbow T2, heaviest lift 2014-08-29 ID fan duct support steel – Notice IW on top beam! 2014-05-18 Installing new DC MCC 2014-05-14 Setting aux boiler stack 14

  15. Winter of 1975 15

  16. 2013-10-01 Aerial shot 16

  17. 2014-08-15 Aerial shot 17

  18. 2014-08-15 Aerial shot 18

  19. 2014-10-15 Aerial photo 19

  20. Timeline 2015 • March 1 – June 9 Tie-in outage  AQCS tie-in  $50M AQCS boiler work  Turbine generator inspection  Normal outage work  Other capital projects • June 9 – Sept. 30 Start-up – tuning – testing • October 1 Commercial operation date 20

  21. Remaining work • Demo: existing baghouse, ash silo, ID fans • Site restoration • Units of property • Project closeout 21

  22. 22

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend