forestry reclamation
play

FORESTRY RECLAMATION APPROACH BEARWALLOW SURFACE MINE Hurley, Va. - PowerPoint PPT Presentation

INDUSTRY APPLICATION OF THE FORESTRY RECLAMATION APPROACH BEARWALLOW SURFACE MINE Hurley, Va. BEARWALLOW SURFACE MINE 1,055 ACRES 24 LANDOWNERS PMLUs -Unmanaged Forestry, Fish & Wildlife (Wetlands) & Industrial (Gas


  1. INDUSTRY APPLICATION OF THE FORESTRY RECLAMATION APPROACH BEARWALLOW SURFACE MINE Hurley, Va.

  2. BEARWALLOW SURFACE MINE 1,055 ACRES 24 LANDOWNERS PMLU’s -Unmanaged Forestry, Fish & Wildlife (Wetlands) & Industrial (Gas Wells/Pipelines)

  3. Post-Mining Land Use(s) Numerous Landowners Lease Agreements

  4. 2005-2006-Reclamation prior to gaining approval to implement Forestry Reclamation Approach

  5. Planted 2006-Reclamation prior to gaining approval to implement Forestry Reclamation Approach

  6. FRA Plan Submitted in 2006

  7. Revegetation Plan 2006

  8. Revegatation Plan 2006

  9. 2006 — Revision to Incorporate the FRA Minimal Grading Practices and Revegation Plan Approved

  10. ARRI Forestry Reclamation Approach (FRA) Training Changing Reclamation practices can be difficult for equipment operators The Pride Factor

  11. Single Pass/Loose Grading

  12. Minimal run-off on Loose Graded Area

  13. ARRI Forestry Reclamation Approach (FRA) Training Best Available Material Timing & Handling

  14. Hydroseeding Application

  15. Williams Forestry has Managed the Planting since 2007. Date Acres Hardwoods Wildlife/Shrubs Pines Total 2006 146 64,500 20,500 15,000 100,000 2007 144 63,360 20,016 14,688 98,064 2007 230 114,420 24,840 17,020 156,280 2009 197 98,050 23,750 19,000 140,800 2010 150 70,940 18,330 12,700 101,970 Total 867 411,270 107,436 78,408 597,114

  16. 06/07-FRA Reclamation “New Ridge Area”

  17. 06/07-FRA Reclamation “New Ridge Area”

  18. 2008-FRA Reclamation

  19. 2009-FRA Reclamation

  20. 2010-FRA Reclamation

  21. 2010-FRA Reclamation

  22. 2010-FRA Reclamation

  23. 2010-FRA Reclamation

  24. Promotion of Reforestation on Surface Mined Lands Arbor Day April, 2009

  25. Arbor Day April, 2009

  26. Arbor Day April, 2009

  27. Arbor Day April, 2009

  28. Reclamation & Reforestation Awards VMA, Individual and ARRI(State) Trees species planted: White & Pitch Lob Pines, Red & White Oaks, Black Cherry, Red Maple, White Ash, Sycamore, Crab Apple, Gray Dogwood, Hazelnut, Chestnut, Black Locust, Persimmon, Eastern Redbud, Sawtooth Oak and Red Mulberry

  29. Arbor Day April, 2009 Reclamation & Reforestation Awards

  30. Questions

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.