bernalillo county 2018 2024 capital improvement plan cip
play

BERNALILLO COUNTY 2018-2024 CAPITAL IMPROVEMENT PLAN (CIP) & - PowerPoint PPT Presentation

BERNALILLO COUNTY 2018-2024 CAPITAL IMPROVEMENT PLAN (CIP) & GENERAL April 17, 2018 OBLIGATION Public Meeting #5 BOND Vista Grande Community Center Commission District 5 Commissioner James E. Smith Tonights Agenda 2


  1. BERNALILLO COUNTY 2018-2024 CAPITAL IMPROVEMENT PLAN (CIP) & GENERAL April 17, 2018 OBLIGATION Public Meeting #5 BOND Vista Grande Community Center Commission District 5 Commissioner James E. Smith

  2. Tonight’s Agenda 2  Commissioner remarks, Introductions, Spanish Interpretation  Community information re: 2020 Census, Public Art Program, Behavioral Health, and County Assessor  Commission Districts and Capital Improvement Program Objectives  Unfunded and Committed Capital Funding Needs  Video of Completed Capital Projects  Proposed Uses of 2018 Bond Funding  2018 Bond Schedule  Questions and Answers

  3. Commission Districts 3

  4. Capital Improvement Program Objectives 4  Plan, leverage, align, and accumulate funds  Inform public about capital projects’ funding status  Serve as a strategic tool for the county  Identify the maintenance budget impact of a capital project

  5. Unfunded and Committed Capital Committed $ 955,960,683 $ 212,331,185 Approximate Value 22% of Desired Capital Projects Unfunded $ 743,629,498 78% 5

  6. Unfunded Capital by Division Nonprofit Community Organizations Services $ 2,308,000 $ 137,841,714 <1% 19% Libraries $2,450,000 $ 743,629,498 <1% Approximate Total Value of Unfunded Capital Projects Health & Public Safety $ 32,070,505 4% Public Works $ 568,959,279 77% 6

  7. Committed Funds by Source Partners (ABCWUA, COA, AMAFCA) $ 30,811,370 15% State G.O. Bond $ 21,614,803 $ 70,369,930 10% 33% General Fund $ 3,169,133 $ 212,331,185 1% Approximate Total Value of Committed Funds Impact Fees $ 335,907 <1% Federal $ 86,030,042 41% 7

  8. Video of Completed Capital Projects 8

  9. Proposed Uses of 2018 Bond Funding 9  Dividing $38.45 million  How are bonds paid back?  Two “clocks” for bond funding  1% for Arts  Bond questions for the electorate and proposed uses

  10. Proposed Future LIBRARY USES Bond Question #1 10  Library  Cost: N/A  Committed: $1.5 million in 2016  Proposed 2018 Bond Amount: $1.75 million  Objectives: To continually acquire and upgrade books and materials for the City/County library system

  11. Proposed Future HEALTH & PUBLIC SAFETY, FLEET, & COUNTY FACILITIES Bond Question #2 11  Buildings & Equipment  Proposed Bond Amount: $16.5 million  Objectives: Reduce energy use, reduce use of non- renewable energy, reduce maintenance costs, improve buildings’ systems, comfort of buildings, make ADA upgrades, and prolong the life of County facilities o Fire Station improvements o Youth Services Center remodel o Heavy equipment replacement o Emergency Mobile Radio system

  12. Proposed Future RECREATION USES Bond Question #3 12  Recreational Facility Rehabilitation, Improvements, and Development  Proposed Bond Amount: $4.95 million  Objective: To implement a variety of necessary and desirable projects countywide identified in the 2015 Park, Recreation, and Open Space Plan. Projects would address: o Ballfield improvements Countywide o Community Centers improvements o Playgrounds' improvements Countywide o Parks' improvements Countywide o ADA upgrades Countywide

  13. Proposed Future PUBLIC WORKS TRANSPORTATION USES Bond Question #4 13  Countywide Road Rehabilitation, Improvements, and Development  Proposed Bond Amount: $8.5 million  Objective: To address a variety of necessary transportation and mobility projects countywide o Rehabilitating existing paved roads with a low Remaining Service Life (RSL) o Installing guardrails, signage, striping and improving school bus routes o Funding trails, bikelanes, and sidewalks o Providing local matching funds for Sunport Blvd Extension, Bridge Blvd Redevelopment, and 2nd Street SW

  14. Proposed Future PUBLIC WORKS STORM DRAINAGE & UTILITY USES Bond Question #5 14  Countywide Storm Drainage and Utility Improvements  Proposed Bond Amount: $5.5 million  Objectives: Remove acreage from floodplain and eliminate nuisance flooding in North Albuquerque Acres and the South Valley.  Install fiber optic lines in important corridors as part of other road and/or drainage reconstruction work

  15. Proposed Future HOUSING USES Bond Question #6 15  Senior and Disabled Multifamily Proposed Bond Amount: $500,000  Objective: To improve energy efficiency of County-owned housing  units that are rented to low-income seniors and families with a member who has a disability.  Tiny Home Village Phase 2 Proposed Bond Amount: $750,000  Objective: To complete construction of a commons building and to  design and construct actual tiny homes. Phase 1 funding will be used for land acquisition, infrastructure improvements, and the start of a common building.

  16. 2018 Schedule 16  May 4 Deadline for project submittals, www.bernco.gov/2018CIPGOBond  July Technical evaluations and bond package recommendation  Early August Review and recommend bond package to CIP Committee  Aug. 14 Commission approval of bond package for November ballot  September Public outreach about approved bond package and submittal of ICIP to State of New Mexico  Fall 2018 Formulate capital outlay priorities & federal transportation requests for 2019 funding cycles  Oct. 20 Early voting begins  Nov. 6 General Election

  17. Questions? 17 Thank you for your time and interest Clay Campbell, AICP Chief of Staff to the County Manager (505) 468-7309 ccampbell@bernco.gov On-Line Public Feedback at www.bernco.gov/2018CIPGOBOND

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.