Place Project Rendering Here Beecher Terrace Redevelopment November 27, 2018 Opening Remarks & Purpose Laura Kinsell-Baer & Johnathan Coates McCormack Baron Salazar Opening Remarks and Purpose The purpose of this session is to


  1. Place Project Rendering Here Beecher Terrace Redevelopment November 27, 2018

  2. Opening Remarks & Purpose Laura Kinsell-Baer & Johnathan Coates – McCormack Baron Salazar

  3. Opening Remarks and Purpose The purpose of this session is to assemble MBE, WBE, DBE and Section 3 subcontractors and suppliers interested in bidding or receiving information for the Beecher Terrace Redevelopment . This session is an on-going effort to obtain maximum community involvement and participation . BEECHER TERRACE MESSER CONSTRUCTION CO.

  4. Agenda & Introductions Mark Ketterer, Senior Project Executive - Messer

  5. Agenda • Introductions • Economic Inclusion Strategies • Project Overview • Bid Packages • Questions & Answers • Networking BEECHER TERRACE MESSER CONSTRUCTION CO.

  6. Project Team • Laura, Kinsell-Baer – McCormack Baron Salazar • Johnathan Coates – McCormack Baron Salazar • Mark Ketterer, Senior Project Executive - Messer • Stephanie Pierson, Project Manager - Messer • Sonya Walton, Director of Economic Inclusion - Messer • Natasha Moffitt, Economic Inclusion Coordinator - Messer BEECHER TERRACE MESSER CONSTRUCTION CO.

  7. Economic Inclusion Strategies Sonya Walton, Director of Economic Inclusion – Messer

  8. Inclusion Requirements BEECHER TERRACE PROJECT GOALS 25% MBE (Minority-owned Business Enterprise) $25.2M 10% WBE (Women-owned Business Enterprise) .5% DBE (Disabled Business Enterprise) 12% SECTION 3 BUSINESS CONCERN 33% SECTION 3 RESIDENT HIRING $80.3M 11.2% EEO MINORITY WORKFORCE PARTICIPATION 6.9% EEO FEMALE WORKFORCE PARTICIPATION no BEECHER TERRACE MESSER CONSTRUCTION CO.

  9. Inclusion Requirements BEECHER TERRACE CERTIFICATION REQUIREMENTS  Tristate Minority Supplier M/WBE Development Council $25.2M  Louisville & Jefferson County Human Relations Council  MSD’s Minority & Women Business Enterprise Program  Record of physical or mental DBE $80.3M impairment  Section 3 Certification & Affidavit SECTION 3 no BEECHER TERRACE MESSER CONSTRUCTION CO.

  10. Inclusion Requirements Community Resources  Louisville Metro Housing Authority Phillip Stepteau, MBE/Section 3 Coordinator $25.2M 420 South 8 th Street, Louisville, KY 40203  Kentucky Cabinet for Economic Development 502-564-2064  Louisville & Jefferson County Human Relations Commission 502-574-3631 $80.3M  Tristate Minority Supplier Development Council 502-625-0159 no BEECHER TERRACE MESSER CONSTRUCTION CO.

  11. Economic Inclusion Strategies • Our commitment to Economic Inclusion and the established M/W/DBE & Section 3 goals for the $25.2M project • Overview of Economic Inclusion requirements for the Project Basis of Award • Certification required for all bidders for their $80.3M specific scope of work • Monitoring, tracking & reporting no BEECHER TERRACE MESSER CONSTRUCTION CO.

  12. Economic Inclusion Results Annual Supplier Diversity Results Awards and Recognition 19.59% 19.17% 20%  Nashville Minority Business Center’s MEDWeek 18% 17.06% Corporate Award (2017) 15.69% 15.55% 15.38% 16%  Spirit of Diversity, South Central Ohio Healthcare Supplier 14% Diversity Symposium Major Supplier award (2017) 11.66% 12%  DiversityInc’s Top 13 Companies for Supplier Diversity 10% No. 8 (2016) 8%  Ohio Minority Supplier Development Council Class I Corporation of the Year (2014 – 2016) 6% 4%  Ohio Minority Supplier Development Advocate of the Year $80.3M Award (2016) 2% 0%  Charlotte-Mecklenburg MWSBE Crowns of Enterprise FY2012 FY2013 FY2014 FY2015 FY 2016 FY 2017 FY 2018 Award Prime Contractor of the Year (2016) 2019 Goal: 16.0% ($176.2 million) BEECHER TERRACE MESSER CONSTRUCTION CO.

  13. Construction Project Overview Mark Ketterer, Senior Project Executive – Messer

  14. Beecher Terrace Redevelopment BEECHER TERRACE MESSER CONSTRUCTION CO.

  15. Phase 2 Demolition Overview Mark Ketterer, Project Executive, Messer Out to Bid: November 20 th , 2018 December 10 th , 2018 Bids Due: $25.2M Bid Categories: BC-01 Abatement $80.3M BC-02 Demolition & Site Preparation no BEECHER TERRACE MESSER CONSTRUCTION CO.

  16. Phase 1 Infrastructure Overview Mark Ketterer, Project Executive, Messer Out to Bid: December 10 th , 2018 January 8 th , 2019 Bids Due: $25.2M Bid Categories: BC-01 Earthwork, Erosion Control & Storm Drainage $80.3M BC-02 Concrete Sidewalks, Curbs & Ramps BC-03 Paving & Pavement Markings no BEECHER TERRACE MESSER CONSTRUCTION CO.

  17. Senior Building Overview Mark Ketterer, Project Executive, Messer Out to Bid: December 10 th , 2018 Bids Due: January 8 th , 2019 $25.2M Bid Categories: BC-01 Surveying, Layout & Staking BC-02 Concrete Footings, Elevator Pits & Slabs on Grade (building) $80.3M BC-03 Site Concrete Pavement, Sidewalks, Curbs & Ramps BC-04 Concrete Floor Topping (Gypcrete) no BEECHER TERRACE MESSER CONSTRUCTION CO.

  18. Senior Building Overview Mark Ketterer, Project Executive, Messer Bid Categories (cont’d): BC-05 CMU Masonry $25.2M BC-06 Brick Masonry & Manufactured Masonry Units BC-07 Structural & Miscellaneous Steel BC-08 Decorative Metal Railings BC-09 Wood Framing (Material Only) BC-10 Wood Frame Installation (Labor Only) $80.3M BC-11 General Trades BC-12 Custom Casework & Woodwork BC-13 Residential Casework (Material Only) no BEECHER TERRACE MESSER CONSTRUCTION CO.

  19. Senior Building Overview Mark Ketterer, Project Executive, Messer Bid Categories (cont’d): BC-14 Synthetic Marble & Quartz Countertops $25.2M BC-15 Residential Casework & Countertops Installation BC-16 Building Insulation BC-17 Fiber Cement Wall Panels BC-18 Fiber Cement Siding, Soffits & Trim BC-19 Roofing $80.3M BC-20 Intumescent Fireproofing BC-21 Firestopping no BEECHER TERRACE MESSER CONSTRUCTION CO.

  20. Senior Building Overview Mark Ketterer, Project Executive, Messer Bid Categories (cont’d): BC-22 Joint Sealants $25.2M BC-23 Hollow Metal Doors/Frames, Solid Core Wood Doors, Hardware & Access Control Systems BC-24 Prehung Hollow-Core Wood Doors & Hardware (Material Only) $80.3M BC-25 Prehung Hollow Core Door/Hardware Installation BC-26 Overhead Coiling Doors BC-27 Windows, Storefront & Glazing BC-28 Drywall no BEECHER TERRACE MESSER CONSTRUCTION CO.

  21. Senior Building Overview Mark Ketterer, Project Executive, Messer Bid Categories (cont’d): BC-29 Tile $25.2M BC-30 Acoustic Ceilings BC-31 Flooring BC-32 Painting & Wallcovering BC-33 Division 10 (Material Only) BC-34 Division 10 Installations $80.3M BC-35 Ventless Gas Fireplace BC-36 Aluminum Canopies BC-37 Residential Appliances (Material Only) no BEECHER TERRACE MESSER CONSTRUCTION CO.

  22. Senior Building Overview Mark Ketterer, Project Executive, Messer Bid Categories (cont’d): BC-38 Molded Tub Units (Material Only) $25.2M BC-39 Window Blinds BC-40 Site Tables & Benches (Material Only) BC-41 Elevators BC-42 Fire Protection BC-43 Plumbing $80.3M BC-44 HVAC BC-45 Electrical BC-46 Voice / Data / CATV Systems no BEECHER TERRACE MESSER CONSTRUCTION CO.

  23. Senior Building Overview Mark Ketterer, Project Executive, Messer Bid Categories (cont’d): BC-47 Earthwork, Erosion Control & Storm Drainage $25.2M BC-48 Fencing & Gates BC-49 Landscaping BC-50 Final Cleaning BC-51 Construction Clean-up $80.3M no BEECHER TERRACE MESSER CONSTRUCTION CO.

  24. Questions & Answers Project Team Thank $25.2M You! $80.3M no BEECHER TERRACE MESSER CONSTRUCTION CO.

  25. Resources Project Team • For project specific questions contact: $25.2M Mark Ketterer at mketterer@messer.com Stephanie Pierson at spierson@messer.com • For certification requirements / questions contact: $80.3M Natasha Moffitt at nmoffitt@messer.com no BEECHER TERRACE MESSER CONSTRUCTION CO.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.