Beecher Terrace Redevelopment
November 27, 2018
Beecher Terrace Redevelopment November 27, 2018 Opening Remarks - - PowerPoint PPT Presentation
Place Project Rendering Here Beecher Terrace Redevelopment November 27, 2018 Opening Remarks & Purpose Laura Kinsell-Baer & Johnathan Coates McCormack Baron Salazar Opening Remarks and Purpose The purpose of this session is to
November 27, 2018
Laura Kinsell-Baer & Johnathan Coates – McCormack Baron Salazar
MESSER CONSTRUCTION CO.
The purpose of this session is to assemble MBE, WBE, DBE and Section 3 subcontractors and suppliers interested in bidding or receiving information for the Beecher Terrace Redevelopment. This session is an on-going effort to obtain maximum
community involvement and participation.
BEECHER TERRACE
Mark Ketterer, Senior Project Executive - Messer
MESSER CONSTRUCTION CO.
BEECHER TERRACE
MESSER CONSTRUCTION CO.
BEECHER TERRACE
Sonya Walton, Director of Economic Inclusion – Messer
MESSER CONSTRUCTION CO.
$80.3M $25.2M no
BEECHER TERRACE
BEECHER TERRACE PROJECT GOALS 25% MBE (Minority-owned Business Enterprise) 10% WBE (Women-owned Business Enterprise) .5% DBE (Disabled Business Enterprise) 12% SECTION 3 BUSINESS CONCERN 33% SECTION 3 RESIDENT HIRING 11.2% EEO MINORITY WORKFORCE PARTICIPATION 6.9% EEO FEMALE WORKFORCE PARTICIPATION
MESSER CONSTRUCTION CO.
$80.3M $25.2M no
BEECHER TERRACE
BEECHER TERRACE CERTIFICATION REQUIREMENTS M/WBE
Development Council
Relations Council
Enterprise Program DBE
impairment SECTION 3
MESSER CONSTRUCTION CO.
$80.3M $25.2M no
BEECHER TERRACE
Community Resources
Phillip Stepteau, MBE/Section 3 Coordinator 420 South 8th Street, Louisville, KY 40203
502-564-2064
502-574-3631
502-625-0159
MESSER CONSTRUCTION CO.
$80.3M $25.2M no
established M/W/DBE & Section 3 goals for the project
the Project Basis of Award
specific scope of work
BEECHER TERRACE
MESSER CONSTRUCTION CO.
$80.3M
Corporate Award (2017)
Diversity Symposium Major Supplier award (2017)
Corporation of the Year (2014–2016)
Award (2016)
Award Prime Contractor of the Year (2016)
2019 Goal: 16.0% ($176.2 million) Annual Supplier Diversity Results Awards and Recognition
11.66% 15.55% 19.17% 19.59% 15.69% 15.38% 17.06% 0% 2% 4% 6% 8% 10% 12% 14% 16% 18% 20% FY2012 FY2013 FY2014 FY2015 FY 2016 FY 2017 FY 2018
BEECHER TERRACE
Mark Ketterer, Senior Project Executive – Messer
MESSER CONSTRUCTION CO.
BEECHER TERRACE
MESSER CONSTRUCTION CO.
$80.3M $25.2M no
Out to Bid: November 20th, 2018 Bids Due: December 10th, 2018 Bid Categories: BC-01 Abatement BC-02 Demolition & Site Preparation
BEECHER TERRACE
Mark Ketterer, Project Executive, Messer
MESSER CONSTRUCTION CO.
$80.3M $25.2M no
Out to Bid: December 10th, 2018 Bids Due: January 8th, 2019 Bid Categories: BC-01 Earthwork, Erosion Control & Storm Drainage BC-02 Concrete Sidewalks, Curbs & Ramps BC-03 Paving & Pavement Markings
BEECHER TERRACE
Mark Ketterer, Project Executive, Messer
MESSER CONSTRUCTION CO.
Mark Ketterer, Project Executive, Messer
$80.3M $25.2M no
Out to Bid: December 10th, 2018 Bids Due: January 8th, 2019 Bid Categories: BC-01 Surveying, Layout & Staking BC-02 Concrete Footings, Elevator Pits & Slabs on Grade (building) BC-03 Site Concrete Pavement, Sidewalks, Curbs & Ramps BC-04 Concrete Floor Topping (Gypcrete)
BEECHER TERRACE
MESSER CONSTRUCTION CO.
Mark Ketterer, Project Executive, Messer
$80.3M $25.2M no
Bid Categories (cont’d): BC-05 CMU Masonry BC-06 Brick Masonry & Manufactured Masonry Units BC-07 Structural & Miscellaneous Steel BC-08 Decorative Metal Railings BC-09 Wood Framing (Material Only) BC-10 Wood Frame Installation (Labor Only) BC-11 General Trades BC-12 Custom Casework & Woodwork
BC-13 Residential Casework (Material Only)
BEECHER TERRACE
MESSER CONSTRUCTION CO.
$80.3M $25.2M no
Bid Categories (cont’d): BC-14 Synthetic Marble & Quartz Countertops BC-15 Residential Casework & Countertops Installation BC-16 Building Insulation BC-17 Fiber Cement Wall Panels BC-18 Fiber Cement Siding, Soffits & Trim BC-19 Roofing BC-20 Intumescent Fireproofing BC-21 Firestopping
BEECHER TERRACE
Mark Ketterer, Project Executive, Messer
MESSER CONSTRUCTION CO.
$80.3M $25.2M no
Bid Categories (cont’d): BC-22 Joint Sealants BC-23 Hollow Metal Doors/Frames, Solid Core Wood Doors, Hardware & Access Control Systems BC-24 Prehung Hollow-Core Wood Doors & Hardware (Material Only) BC-25 Prehung Hollow Core Door/Hardware Installation BC-26 Overhead Coiling Doors BC-27 Windows, Storefront & Glazing BC-28 Drywall
BEECHER TERRACE
Mark Ketterer, Project Executive, Messer
MESSER CONSTRUCTION CO.
$80.3M $25.2M no
Bid Categories (cont’d): BC-29 Tile BC-30 Acoustic Ceilings BC-31 Flooring BC-32 Painting & Wallcovering BC-33 Division 10 (Material Only) BC-34 Division 10 Installations BC-35 Ventless Gas Fireplace BC-36 Aluminum Canopies BC-37 Residential Appliances (Material Only)
BEECHER TERRACE
Mark Ketterer, Project Executive, Messer
MESSER CONSTRUCTION CO.
$80.3M $25.2M no
Bid Categories (cont’d): BC-38 Molded Tub Units (Material Only) BC-39 Window Blinds BC-40 Site Tables & Benches (Material Only) BC-41 Elevators BC-42 Fire Protection BC-43 Plumbing BC-44 HVAC BC-45 Electrical BC-46 Voice / Data / CATV Systems
BEECHER TERRACE
Mark Ketterer, Project Executive, Messer
MESSER CONSTRUCTION CO.
$80.3M $25.2M no
Bid Categories (cont’d): BC-47 Earthwork, Erosion Control & Storm Drainage BC-48 Fencing & Gates BC-49 Landscaping BC-50 Final Cleaning BC-51 Construction Clean-up
BEECHER TERRACE
Mark Ketterer, Project Executive, Messer
MESSER CONSTRUCTION CO.
Project Team
$80.3M $25.2M no
BEECHER TERRACE
MESSER CONSTRUCTION CO.
Project Team
$80.3M $25.2M no
BEECHER TERRACE
Mark Ketterer at mketterer@messer.com Stephanie Pierson at spierson@messer.com
Natasha Moffitt at nmoffitt@messer.com