BC HYDRO WIND RESOURCE OPTION ENGAGEMENT JUNE 3, 2015 WIND - - PowerPoint PPT Presentation
BC HYDRO WIND RESOURCE OPTION ENGAGEMENT JUNE 3, 2015 WIND - - PowerPoint PPT Presentation
BC HYDRO WIND RESOURCE OPTION ENGAGEMENT JUNE 3, 2015 WIND RESOURCE ENGAGEMENT PURPOSE Report on BC-wide cost curve assumption Present preliminary results on wind UECs Seek input from stakeholders on cost assumptions and
2
PURPOSE
- Report on BC-wide cost curve assumption
- Present preliminary results on wind UECs
- Seek input from stakeholders on cost assumptions and representation
- f wind potential in BC
WIND RESOURCE ENGAGEMENT
3
SUMMARY OF CHANGES BASED ON STAKEHOLDER INPUT
- 100 m hub height
- 3 MW turbine nameplate capacity
- 12.75% loss factor
- Updated power curves based on current/forward looking turbine
technology
- 25 year project life
WIND RESOURCE ENGAGEMENT
4
COST ASSUMPTIONS
- Based on line item analysis conducted by Hatch
- Considers impact of project size on capital costs
- Based on stakeholder input, use BC-wide costs instead of region
specific costs (differences in site characteristics outweigh regional differences)
- Costs based on generic ‘best case scenario’ site conditions
WIND RESOURCE ENGAGEMENT
5
BC-WIDE COST CURVE BASED ON GENERIC ‘BEST CASE SCENARIO’ SITE CONDITIONS
WIND RESOURCE ENGAGEMENT 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 3000 50 100 150 200 250 300 350 400
Capital Cost ($/kW) Project Size (MW)
6
CONCERN VOICED IN PREVIOUS SESSION
- Hatch cost estimates are representative of ‘best case scenario’
sites, but not reflective of sites with challenging topography and high relief approaches
- Many of the high wind speed sites in BC are associated with
challenging topography/high relief approaches
- Cost estimates likely underestimate UECs for those sites
WIND RESOURCE ENGAGEMENT
7
ESTIMATING IMPACT OF CHALLENGING TOPOGRAPHY ON CAPITAL COSTS
- Informal survey of IPPs (conducted by GE)
- Capital costs range from $2,590/kW (plateau site) to
$2,940/kW (complex site)
- Compare this to $2,350/kW based on the BC-wide cost curve
(all estimates for a ~100 MW project) IPP estimate for complex site is roughly 25% more than Capex estimate based on BC-wide cost curve Proposal:
- Apply a percent increase in Capex to sites with challenging
topography (identified using Google Earth) to better reflect higher costs associated with building in difficult terrain.
WIND RESOURCE ENGAGEMENT
8
UEC AT POINT OF INTERCONNECTION
WIND RESOURCE ENGAGEMENT
- Preliminary - based on estimated CFs and 2013 R1/T1 values)
- Does not include cost adders (capacity, wind integration, etc)
50.00 70.00 90.00 110.00 130.00 150.00 170.00 190.00 210.00 230.00 250.00 10,000 20,000 30,000 40,000 50,000
UEC at POI ($/MWh) GWh
Capex based on Best Case Scenario Site Conditions Capex based on Best Case Scenario Site Conditions plus 25% 15% Increase Applied to Challenging Sites 20% Increase Applied to Challenging Sites 25% Increase Applied to Challenging Sites
9
OTHER CONCERNS
- Is it reasonable to assume 100 m hub heights for Class I sites?
- Database contains 17 projects with average wind speeds > 9 m/s
and 8 projects with wind speeds > 9.5 m/s (at 100 m) Are these wind speeds overly optimistic?
WIND RESOURCE ENGAGEMENT
10
NEXT STEPS
- Complete UECs based on today’s input
- Send out results to stakeholder group
- Post results on BC Hydro website (expected summer, 2015)
WIND RESOURCE ENGAGEMENT