bc hydro wind resource option engagement
play

BC HYDRO WIND RESOURCE OPTION ENGAGEMENT MAY 5, 2015 WIND - PowerPoint PPT Presentation

BC HYDRO WIND RESOURCE OPTION ENGAGEMENT MAY 5, 2015 WIND RESOURCE ENGAGEMENT AGENDA Review impact of updated turbine characteristics on net CF Review updated wind costs and assumptions 2 WIND RESOURCE ENGAGEMENT SUMMARY OF PROPOSED


  1. BC HYDRO WIND RESOURCE OPTION ENGAGEMENT MAY 5, 2015

  2. WIND RESOURCE ENGAGEMENT AGENDA • Review impact of updated turbine characteristics on net CF • Review updated wind costs and assumptions 2

  3. WIND RESOURCE ENGAGEMENT SUMMARY OF PROPOSED CHANGES TO TURBINE CHARACTERISTICS • Increase hub height (HH) from 80m to 100m • Use uniform turbine size of 3 MW (no impact) • Increase loss factor from 11.6% to 12.75% • Update power curves based on current/forward looking turbine technology 3

  4. WIND RESOURCE ENGAGEMENT POWER CURVES UPDATE 1.00 0.90 0.80 Normalized Power Output 0.70 Class I ‐ 2009 Wind Data Study 0.60 Class I ‐ 2013 ROU Class I ‐ 3MW (2015) 0.50 Class II ‐ 2009 Wind Data Study 0.40 Class II ‐ 2013 ROU Class II ‐ 3MW (2015) 0.30 Class III ‐ 2013 ROU 0.20 Class III ‐ 3MW (2015) 0.10 0.00 0.0 5.0 10.0 15.0 Wind Speed (m/s) 4

  5. WIND RESOURCE ENGAGEMENT SUMMARY OF PROPOSED CHANGES IN TURBINE CHARACTERISTICS Average net CF total Average net CF percentage point increase Average net CF total percentage point from 2013 ROU (includes percentage point increase from 2013 updated power curves, 100 increase from 2009 BC ROU due to updated HH and new loss Hydro Wind Data Study power curves assumptions) 1.3 3.5 8.1 IEC Class I 1.9 3.6 7.9 IEC Class II 1.0 3.4 8.2 IEC Class III 5

  6. WIND RESOURCE ENGAGEMENT IMPACT OF CHANGES IN TURBINE ASSUMPTIONS ON NET CF 40 35 30 Number of Projects 25 20 2009 Wind Data Study 2013 ROU 15 2015 ROU (Preliminary) 10 5 0 <20% 20 ‐ 25% 25 ‐ 30% 30 ‐ 35% 35 ‐ 40% 40 ‐ 45% 45 ‐ 50% Net Capacity Factor 6

  7. WIND RESOURCE ENGAGEMENT WIND CAPITAL AND O&M COSTS UPDATE Cost information obtained through: • Wind project cost review by Hatch • Survey of developers active in BC, conducted by GE Power & Water • EPC cost review for Canadian wind projects by Borea Construction (confidential report) 7

  8. WIND RESOURCE ENGAGEMENT HATCH COST REVIEW FOR BC WIND PROJECTS • Cost analysis includes pre-construction costs, turbine supply agreement, BoP costs, and owner’s cost during construction • Out of scope for Hatch analysis • Financing costs Common to all • Transmission/interconnection costs resource options • Off-site road access • Wind Participation Rent and community/FN accommodation calculated separately (based on CF/revenue) 8

  9. WIND RESOURCE ENGAGEMENT HATCH COST REVIEW ‐ APPROACH • Based on line item analysis for a base case wind project in each of the four regions (PC, NC, SI, VI) • Cost estimates based on information from publically available sources and interviews with turbine vendors, EPC contractors and developers • Total capital cost adjusted to reflect that larger projects benefit from economies of scale 9

  10. WIND RESOURCE ENGAGEMENT BASE CASE PROJECT ASSUMPTIONS • Base case reflects median project size in each region • Assume generic `best case scenario` site conditions: • Good site access via existing public roads and located in proximity to services in a small community • No considerable importation/exportation of material required • No rock blasting • Minimal number of waterway crossings • Does not cover costs associated with challenging topography with high relief approaches 10

  11. WIND RESOURCE ENGAGEMENT CAPITAL AND O&M COSTS FOR BASE CASE PROJECTS ($/KW) Project Phase NC PC SI VI (195 MW) (117 MW) (117 MW) (48 MW) Pre ‐ Construction 50 80 67 137 Wind Turbines* 1,384 1,383 1,366 1,415 BoP 635 686 603 759 Owner’s Costs during 198 225 196 238 Construction Total Capital Cost 2,268 2,374 2,231 2,549 Annual O&M Cost 68 73 67 74 * Cost estimates based on a 20-yr project life. For a 25-yr project, expect 3-4% increase in turbine cost. 11

  12. WIND RESOURCE ENGAGEMENT CAPITAL AND O&M COSTS FOR A 102 MW WIND FARM ($/KW) Project Phase NC PC SI VI Pre ‐ Construction 78 86 71 75 Wind Turbines 1,396 1,383 1,367 1,403 BoP 699 695 610 654 Owner’s Costs during 221 227 200 215 Construction Total Capital Cost 2,394 2,391 2,248 2,347 Annual O&M Cost 79 74 68 72 12

  13. WIND RESOURCE ENGAGEMENT ADJUSTMENT OF COST FOR SIZE OF PROJECT 3,000,000 2,500,000 Capital Cost ($/kW) 2,000,000 PC 1,500,000 NC SI 1,000,000 VI 500,000 ‐ 0 50 100 150 200 250 300 350 Installed Capacity (MW) 13

  14. WIND RESOURCE ENGAGEMENT SURVEY OF DEVELOPERS ACTIVE IN BC • Organized/conducted by GE Power & Water • Small number of respondents, but all reputable, active in BC and experienced with bringing wind projects to completion • Cost estimates based on a 100 MW+ project • Includes engineering, development fees, insurance, FN accommodation, legal fees, BoP (i.e. everything but turbine costs) • Respondents asked to specify if project site is plateau or complex • Results: US $1,060/kW for plateau site US $1,400/kW for complex site 14

  15. WIND RESOURCE ENGAGEMENT COMPARISON OF CAPITAL COSTS ($/KW) Hatch IPP Survey IPP Survey (Plateau Site)* (Complex Site)* Development, BoP, 881 ‐ 1,010 1,180 1,550 Owner’s Costs Turbine Cost 1,370 ‐ 1,400 1,330** 1,390** Total 2,250 – 2,395 2,510 2,940 * Cost estimates were provided in USD. Exchange rate of 1 USD = 0.9 CAD was used to convert to CAD. ** Turbine costs estimated by GE 15

  16. WIND RESOURCE ENGAGEMENT EPC ESTIMATES BY BOREA CONSTRUCTION General learnings: • BoP cost estimates for PC region in line with Hatch’s estimates • BoP costs in Peace region can be competitive with rest of Canada • Project site (water crossings, terrain complexity, etc) matters • Can substantially increase BoP costs 16

  17. WIND RESOURCE ENGAGEMENT PUTTING EVERYTHING TOGETHER… • Hatch cost estimates are representative of `best case scenario` sites in the four regions of BC • These sites exist, but likely do not overlap with high wind speed sites (presumably more complex terrain) • Concern – combination of high wind speed sites and low cost estimates will underestimate UECs Feedback from Stakeholders? 17

  18. WIND RESOURCE ENGAGEMENT FUTURE TURBINE PRICING • Turbine prices have fallen ~30% from peak in 2008/2009 • No significant additional reductions expected in foreseeable future • Future trends in turbine pricing? • Future wind energy price reductions usually attributed to changes in wind turbine technology which lead to cost reductions and/or improvements in turbine efficiencies • Market/economic conditions can drive turbine prices higher (e.g. as seen in 2004-2009 period) • Propose to treat future turbine pricing as scenarios 18

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend