PORTFOLIO COMMITTEE ON BASIC EDUCATION
Presentation on: Provincial Infrastructure Programme ASIDI & SAFE
1
BASIC EDUCATION Presentation on: Provincial Infrastructure - - PowerPoint PPT Presentation
PORTFOLIO COMMITTEE ON BASIC EDUCATION Presentation on: Provincial Infrastructure Programme ASIDI & SAFE 1 PRESENTATION OUTLINE Purpose National Development Plan Background Provincial Infrastructure Programme ASIDI
1
2
3
National Planning Commission: National Development Plan, November 2011)
4
“School infrastructure backlogs have been considerably reduced over the past 10 years. But many school environments are still not conducive to learning. The Department of Basic Education has committed itself to eradicating 496 inappropriate structures, providing basic water to 1 257 schools, providing basic sanitation to 868 schools and providing electricity to 878 schools in the 2012/13 financial year. To meet these commitments, the department will have to:
efficiently and cost-effectively
National Planning Commission: National Development Plan, November 2011)
5
National Planning Commission: National Development Plan, November 2011)
6
programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative (SAFE)
targets the provision of basic services, new schools, additions to existing schools, new and upgrading of services and maintenance. It is funded through the Education Infrastructure Grant and the Provincial contribution through the equitable share.
the DBE to address school's infrastructure backlog on schools that do not meet the basic safety norms and standards. It is funded through the Schools Infrastructure Backlogs Grant. The purpose of the programme is for the eradication of schools made entirely of inappropriate structures and the provision of basic level of water, sanitation and electricity to schools.
the DBE to eradicate all pit latrines and other forms of unacceptable sanitation, provide safe and appropriate ablution facilities as well as address insufficient or inadequate sanitation facilities and maintenance of all ablution facilities
7
existing infrastructure in education including district and circuit accommodation;
standards for school infrastructure; and
8
EIG 73.8% ES 12% SIBG 14.2% EIG, R 10.514 bn ES, R 1.713 bn SIBG, R 2.027 bn
Total Budget = R 14. 255bn
EIG = Education Infrastructure Grant ES = Equitable Share SIBG = Schools Infrastructure Backlog Grant
9
10
Provinces
Allocation MTEF Estimates
2019/20 2020/21 2021/22 R'000 R'000 R'000 Eastern Cape 1 585 532 1 564 208 1 685 128 Free State 833 485 722 425 778 272 Gauteng 1 474 715 1 440 169 1 551 501 KwaZulu-Natal 2 187 162 2 013 405 2 169 050 Limpopo 1 050 160 1 175 467 1 266 336 Mpumalanga 731 792 819 111 882 432 Northern Cape 639 817 505 649 544 738 North West 902 484 1 010 169 1 088 260 Western Cape 1 109 331 1 031 186 1 110 902 Unallocated
1 250 010 Total 10 514 478 11 466 632 12 326 629
11
12
Provinces EIG Equitable Share Total % of equitable share to total budget
Eastern Cape
1,585,532 1,585,532 0%
Free State
833,485 16,378 849,863 1.9%
Gauteng
1,474,715 474,821 1,949,536 24.4%
KwaZulu-Natal
2,187,162 359,210 2,546,372 14.1%
Limpopo
1,050,160 1,826 1,051,986 0.2%
Mpumalanga
731,792 202,727 934,519 21.7%
North West
902,484 2,228 904,712 0.2%
Northern Cape
639,817 7,720 647,537 1.2%
Western Cape
1,109,331 648,843 1,758,174 36.9% 10,514,478 1,713,753 12,228,231
13
No. PROGRAMME
Target 2019/20
EC FS GP KZN LP MP NC NW WC 1 Full Service Schools 1 1 5 2 Provision/replacement of Sanitation 178 73 13 150 13 85 14 12 14 3 Provision/upgrade of Water 178 10 13 150 22 3 9 10 14 4 Provision/upgrade of Electricity 5 10 13 100 1 1 11 14 5 Maintenance Projects 20 27 40 370 34 29 36 48 173 6 Libraries Project 5 1 13 12 2 3 4 7 7 Laboratories Projects 5 4 13 12 1 8 7 8 School Halls 1 13 2 5 7 9 Technical Workshops 2 10 Nutrition Centres 5 7 13 10 9 3 5 5 15 11 Additional Classrooms 285 39 350 210 22 104 43 26 68 12 Grade R Classrooms 13 18 200 50 23 3 8 10 73 13 Administration Blocks 5 4 13 10 3 5 4 7 15 14 Provision/upgrade of fence 302 9 13 40 1 15 5 15 15 Provision/upgrade of sport field 13 9 1 3 5 8 15 16 Special Schools 1 2 1 17 Boarding Schools 2 19 18 Guard House 13 9 4 1 7 19 Natural Disasters Projects 2 150
14
PROVINCE
FINANCIAL YEARS
TOTAL 2019/20 2020/21 2021/22 2022/23 2023/24 Eastern Cape 1 5 3 9 Free State 6 3 2 4 2 17 Gauteng 7 8 7 6 6 34 KwaZulu-Natal 7 5 1 13 Limpopo 12 4 14 9 11 50 Mpumalanga 2 6 7 5 2 22 Northern Cape 3 2 11 3 5 24 North West 14 3 11 12 1 41 Western Cape 13 7 10 10 10 50 ASIDI 40 31 29 100 TOTAL 104 70 97 52 37 376
15
Total Infrastructure Spending as at end September 2019 PROVINCE Allocated Budget 2019/20 ('000) Total Spent as at end September 2019 ('000) % Spent of Allocated Budget Eastern Cape 1,585,532 876,882 55% Free State 849,863 337,569 40% Gauteng 1,949,536 476,773 24% KwaZulu-Natal 2,546,372 1,281,619 50% Limpopo 1,051,986 254,945 24% Mpumalanga 934,519 545,389 58% North West 904,712 183,984 20% Northern Cape 647,537 263,316 41% Western Cape 1,758,174 781,989 44% TOTAL 12 228 231 5 002 466 41%
16
Education Infrastructure Grant Expenditure as at end September 2019 PROVINCE Allocated Budget 2019/20 ('000) EIG Transfers to PEDs ('000) Total Spent as at end September 2019 ('000) % Spent of the transferred Amount % Spent of Allocated Budget Eastern Cape 1,585,532 990,958 876,668 88% 55% Free State 833,485 520,928 330,546 63% 40% Gauteng 1,474,715 921,697 428,981 47% 29% KwaZulu-Natal 2,187,162 1,367,157 1,164,205 85% 53% Limpopo 1,050,160 656,350 254,937 39% 24% Mpumalanga 731,792 457,370 504,643 110% 69% North West 902,484 564,052 183,139 32% 20% Northern Cape 639,817 399,886 260,064 65% 41% Western Cape 1,109,331 693,332 453,018 65% 41% TOTAL 10 514 478 6 571 730 4 456 201 68% 42%
17
Prov
Maint’nce Projects in 2019/20 FY Overall Adjusted Infrastructure Budget ('000) Maint’nce Budget ('000) %ge Maint’nce Budget to Total Total Expenditure as at end September 2019 ('000) %ge Expenditure
Relative to Maint’nce Budget Eastern Cape 454 R 1,585,532 R 255,716 16% R 130,786 51% Free State 27 R 849,863 R 158,668 19% R 39,540 25% Gauteng 144 R 1,949,536 R 1,083,137 56% R 240,909 22% KwaZulu-Natal 445 R 2,546,372 R 944,228 37% R 304,308 32% Limpopo 119 R 1,051,986 R 360,106 34% R 27,249 8% Mpumalanga 118 R 934,519 R 131,468 14% R 94,759 72% North West 62 R 904,712 R 114,097 13% R 33,575 29% Northern Cape 113 R 647,537 R 181,294 28% R 79,729 44% Western Cape 173 R 1,758,174 R 646,215 37% R 287,283 44% TOTAL 1 655 12 228 231 3 874 929 32% 1 238 138 32%
18
SUMMARY OF PROJECTS COMPLTED FOR THE 2019/20 FINANCIAL YEAR Province TARGET 2018/19 NEW SCHOOLS TARGET 2018/19 REPLACEMENT SCHOOLS TOTAL SCHOOLS TARGETED TOTAL COMPLETED PROGRESS FIRST QUARTER SECOND QUARTER THIRD QUARTER FOURTH QUARTER TOTAL FIRST QUARTER SECOND QUARTER THIRD QUARTER FOURTH QUARTER TOTAL Number of Schools
Eastern Cape 1 4 5 0% Free State 7 2 1 3 3 10 3 30% Gauteng 4 1 1 2 1 5 2 40% Kwazulu Natal 5 1 1 2 1 1 7 2 29% Limpopo 4 1 5 6 4 1 6 7 8 13 163% Mpumalanga 3 3 3 1 1 1 4 4 100% Northern Cape 2 2 4 0% North West 2 5 7 0% Western Cape 4 2 2 9 1 1 13 3 23% Total Number of schools 32 9 8 17 31 2 8 10 63 27 43%
IDMS REPORT 2nd QUARTER OF 2019/20 PER PROVINCE
19
Programme Total Targets for 2019/20 Q2 EC FS GP KZN LP MP NC NW WC Total Number of New Schools 32 1 1 1 5 8 Replacement schools 31 1 6 1 8 Full Service Schools 13 2 2 Provision/replacement of Sanitation 776 2 2 19 46 23 11 103 Provision/upgrade of Water 515 2 2 64 17 5 1 91 Provision/upgrade of Electricity 133 2 2 1 5 Maintenance Projects 727 2 25 4 14 9 15 69 Libraries Project 45 2 4 7 1 14 Laboratories Projects 51 2 3 2 9 16 School Halls 30 8 1 2 11 Technical Workshops 8 5 5 Nutrition Centres 51 4 1 5 Additional Classrooms 1020 12 69 34 21 7 15 158 Grade R Classrooms 266 3 4 4 5 4 4 2 26 Administration Blocks 52 1 6 55 1 2 65 Provision/upgrade of fence 387 1 1 30 16 2 3 53 Provision/upgrade of sport field 28 Special Schools 3 Boarding Schools 31 1 1 Guard House 30 2 1 3 Natural Disasters Projects 185 17 4 21
20
Prov
Budgeted for PROGRESS Planning Construction Close-out EC 2,916 1,197 445 1274 FS 152 40 112 GT 290 216 61 13 KZ 1,311 520 420 371 LP 682 174 387 121 MP 624 409 140 75 NC 405 235 140 30 NW 265 93 64 108 WC 98 69 26 3 TOTAL 6,743 2,953 1,795 1,995 37% 35% 28%
21
Provnce No of Approved Posts Filled Not Filled Progress % Eastern Cape 63 42 21 67% Free State 78 50 28 64% Gauteng 101 83 18 82% KwaZulu-Natal 74 71 3 96% Limpopo 65 49 16 75% Mpumalanga 113 97 16 86% North West 54 30 24 56% Northern Cape 81 43 38 53% Western Cape 54 45 9 83% Total Weight 683 510 173 75%
Quantity Surveyors 11% Architects 9% Elec.Engineers 2% Civil Engineers 3% GIS Specialists 1% Town & Regional Planners 5%
Planners 9% Works Inspectors 33% Finance and administration 27%
22
23 Reports Submission Date Compliance Final U-AMP for 2019/20 Due 30 March 2019 This is the final plan for all programmes to be implemented over the period of at least 10 years. Monthly IRM reports 22 Day of each month This report captures all infrastructure projects being implemented in the financial year and seeks to present the financial and non financial progress of projects End of Year Reports for 2018/19 Due 31 May 2019 The main purpose of the end-of-year report is to measure progress made by the programme against the objectives and outcomes set, focusing mainly on the previous financial year Draft U-AMP 2020/21 Due 28 June 2019 This is a draft plan for all infrastructure programmes to be implemented
Infrastructure Programme Management Plan (IPMP) & CPS Due 30 August 2019 The IPMP & CPS is an infrastructure programme management plan which includes the construction procurement strategy for infrastructure programmes or projects envisaged to commence within the period for the medium term expenditure framework (MTEF period). The plan specifies how the infrastructure programme will be executed, monitored and controlled. Human Resource Reports 22 Days after end of each Quarter This report seeks to measure progress of the implementation of the DoRA Human Resource Strategy. It report provides progress on the filling
affected provincial department Non-Financial Performace Reports Due 30 days after end of each Quarter The purpose of this report is to measure quarterly progress made by the programme against the objectives and outcomes set for the specific financial year.
24
Weighting for the 2019/20 assessment process (R1.185 billion)
Focus Area Documents / Reports Weight End of the year evaluation report 20% Human Resource Capacitation 5% Infrastructure Reporting Model 40% User-Asset Management Plans 15% Infrastructure Programme Management Plans and; Construction Procurement Strategy Performance Planning 20% TOTAL WEIGHT 100%
25
Implementing Agent: Department of Public Works Allocated budget: R 51.1 million Construction Period: 33 months Project completed: January 2019
26
Implementing Agent: Independent Development Trust Allocated budget: R124 million Construction Period: 54 months Project completed: June 2018
27
28
29
Thembisa Special School
30
31
32
2019/20
2020/21 2021/22 R'000 R'000 R'000 ASIDI 1 327 048 996 036 1 038 937 SAFE 700 000 800 000 1 300 000
TOTAL 2 027 048 1 796 036 2 338 937
33 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 TargetedCompleted Q1 Q2 Q3 Q4 Deviation Inapp Structures
36 59 52 16 14 21 229 40 14 8 6
Sanitation 41 89 161 152 38 41 32 207 834 311 73 46 27
Water 16 64 135 317 90 35 42 205 957 432 53 39 14
Electricity 148 101 39 18 66 372 Past Performance Electricity Scope Completed Current Financial Year 2019/20 Sub- Programme Complete d since Inception
34
35
|
3 6
Siyavuya JPS Sihlahleni JSS Mbekweni HS
Sifonondile JPS
|
3 7
BHEKIZULU JSS HERMANA PS EBENHAUSER INTERMEDIATE
TWEESPRUIT PS
Strategic Objective Programme Performance Indicator Medium-term targets
2019/20 2020/21 2021/22 4.2 Provide basic infrastructure services (water, sanitation, electricity) and replace schools built using inappropriate materials
conditions under which learners are taught 4.2.1 Number of new schools built and completed through ASIDI
40 31 29
4.2.2 Number of schools provided with sanitation facilities through ASIDI.
717 691 995
4.2.3 Number of schools provided with water through ASIDI.
225 125
38
39
Quarterly Targets Programme Performance Indicator Annual Target 2019/20 1st 2nd 3rd 4th
Number of new schools built and completed through ASIDI 40 8 5 12 15 Number of schools provided with sanitation facilities through ASIDI 717 120 147 210 240 Number of school provided with water through ASIDI 225 147 25 35 18
40
<25% 25%-49% 50%-74% >75%
DBSA 114 3 4 5 2 2 13 98 IDT 31 3 5 3 8 20 CDC 31 2 2 1 2 7 24 DRPW 16 16 NDPW 20 1 3 2 2 7 14 5 DBE# 29 29 29 DBE# 57 57 27 5 8 4 8 25 5 Sub-Total
63 14 17 14 22 67 168 IDT 6
2 4 DBSA 19
1 18 FSDoE 5
3
Sub-Total
2 3 3 8 22 KZN Adopt-A-School 3
WC WCED 25
MP DBSA 5
NW DBSA 2
NC DBSA 1
LP DBSA 3
Total 367 63 14 19 17 25 75 229 Projects in Construction No of Projects Complete d FS Provinces Implementing Agents (IA) Projects being Implement ed Construction Progress Design & Procur ement EC Tender Cancelled. Projects to be Re-Tendered
41 <25 % 25% - 49% 50% - 74% >75% LP 437
EC 298 17 6 1 14 17 38 243 FS 39 27
KZN 116
NC 13 - - - - - - 13 NW 18 8
GP 14 - - - - - - 14 MP 38 - - - - - - 38 WC 19 - - - - - - 19 TOTALS 992 52 9 6 36 54 106 834 No of Projects Completed Construction Progress Planning, Design & Procurement Projects being Implemented PROVINCES Projects in Construction
42
<25 % 25% - 49% 50% - 74% >75% EC 520 21 1 - 7 150 158 341 MP 36
FS 67 14
GP
KZN 224 6 3 1
LP 364
NC 5
NW 3
WC 3
TOTALS 1 222 41 6 15 19 185 224 957 No of Projects Completed Construction Progress Planning, Design & Procurement Projects being implemented PROVINCES Projects in Construction
Providers (PSP’s) and Implementing Agents (IA’s) that the Department of Basic Education and provinces are utilizing for the implementation of the infrastructure programme.
project management. These are interrogated and a sample of projects are
devised with the province and monitored by the DBE.
libraries, laboratories, Grade R]
43
construction is progressing satisfactorily, [i.e. on programme, on budget, at acceptable quality…]; and
being wrapped up.
44
45
CHALLENGE NATURE OF CHALLENGE REMEDIAL ACTION
1.
Share toward Infrastructure Delivery poses pressure on the Education Infrastructure Grant.
sites been abandon. Budget/ Finance
commence to construction, whilst awaiting for adjustments.
work done by the IA to ensure that work on ground is equivalent to the expenditure.
bases. 2.
with reliable data information to enhance the planning and delivery of the required Infrastructure timeously IT
transversal system (EFMS) by all the PEDs to manage the data.
system. 3.
maintenance Planning
projects earmarked for maintenance to comply with the DoRA condition of the 30% allocation towards the programme.
avoid duplications or over emphasis on the same schools. 4.
resulting in irregular expenditure by the Implementing Agent Procurement
compliance on all the process.
46
CHALLENGE NATURE OF CHALLENGE REMEDIAL ACTION
5.
(contractors) by the Implementing Agent for projects that were already planned and designed in previous financial years.
programme management.
poor quality of infrastructure.
expenditure targets as per IPIPs
as per the signed SLA with the implementing agents Programme/ Project Management
PED’s prior to the commencement of implementation.
closely monitors the projects under implementation.
reporting and to mitigate any challenges.
by FIPDM schedule and the projects reassigned to IA’s that have the capacity to delivery.
engagements are regulated in order to be able to enforce of penalties on non-performing.
and Local Communities
leading to many companies going under and others filing for Business Rescue Programme/ Project Management
and Political Leadership to address the identified challenges.
forecasting of trends
still have inappropriate sanitation facilities.
SAFE Initiative over the MTEF as follows: – 2019/20 : R700 000 000.00 – 2010/21 : R800 000 000.00 – 2021/22 : R1 300 000 000.00
– Provincial EIG allocation – Partnerships/Donations – SAFE Initiative Allocation
48
49
52
IA
Projects Estimated Total Budget Paid to date Invoice at hand Comments DBSA 240 R 256, 197,789.95 R 0 R 126 410 728.11 Awaiting supporting documents from the IA. (Tranche payment) DEA 58 R 63 729 187.69 R 0 R0 DEA is awaiting for National Treasury to approve deviation from normal procurement process before any invoice can be generated. The Mvula Trust 187 R 268 531 197.17 R 0 R 11 847 646.58 Awaiting supporting documents from the IA. (Assessment reports - Planning) NECT 121 R 100 685 316.15 R 0 R 40 274 126 .46 Awaiting National Treasury approval to extend the scope of work for NECT. (Tranche payment) TOTAL 606 R 689 143 490.96 R 0 R 178 532 501.15 26% of invoice at hand
53
Province
Schools Verification Balance Comments Verified PIT Proper Sanitation EC 1598 359 305 54 1239 Further verification to commence mid October. FS 156
No verification will be carried-out as the province is implementing all the projects. KZN 1365 335 255 80 668 (1030) 362 Schools will not be verified, the province has allocated the projects to be implemented with EIG allocation. LP 507 259 217 42 248 All the schools will be verified by the end of October MP 127 88
39 Schools will not be verified, the province is implementing all the projects with EIG allocation. NW 145 137 66 71 8 Verification to be completed by 8 October. TOTAL 3898 1205 843 247 2136
54
Province
Planning Construction
EC 262 262 FS 148 80 68 KZN 402 372 30 LP 162 162 MP 33 4 29 Total 1007 880 127
Province
Donor EIG & ASIDI
EC 11 4 7 FS 29 29 KZN 93 2 91 LP 35 3 32 MP 20 9 11 TOTAL 188 18 170
55
CHALLENGES REMEDIAL ACTION
the same year is the major cause of delay.
year will be allocated to the IAs at the beginning of the fourth quarter, for planning to commence within the current financial year.
commences at the beginning of the financial year.
the commencement of construction.
projects are completed in time and the quality is up to standard.
project implementation.
57
SEKANEKAMOYI PRIMARY SCHOOL
58
MAMAILA PRIMARY SCHOOL
59
PAAPA PRIMARY SCHOOL
60
TSHINANGE PRIMARY SCHOOL
61
RAMOTLHATSWANE PRIMARY SCHOOL
62
SEKANEKAMOYI PRIMARY SCHOOL
63
64
Ntlhodumela PS Maaphoko LPS Govani Govani PS
PLANNING, DELIVERY AND MAINTANANCE ▪ Integrated National School Infrastructure Sector Plan: All schools in the country profiled in terms of their infrastructure needs in line with Norms and Standards; ▪ Revise Education Infrastructure Delivery Model: This delivery model will address:
▪ Expediting delivery of infrastructure projects, ▪ Controlling the cost of providing education infrastructure and; ▪ Improve Contracts Management Processes;
and specifications for all Education Facilities (Primary Schools, Secondary Schools, Learner Boarding Facilities, District and Circuit Offices);
Infra Bureau/Agency to be set up at national level to centrally facilitate and co-ordinate all the macro and micro planning processes, implementation, monitoring and evaluation of all infrastructure projects in the Basic Education Sector.
65
assessment as a determinant for Project Priority List.
at a local level, to ensure that size of schools built addresses the current and future population dynamics;
non-compliance with progress delivery, deduct management fees for non compliance or withdraw projects as a result of poor performance.
Contract Management and Monitoring processes on infrastructure delivery.
66
environment professionals:
– Revise remuneration scales for professionals; – Improve working conditions and provision of tools of trade;
construction;
the cost of building schools;
67
and ring fence such funding for infrastructure;
intended purpose, as a condition of the grant;
Case and progress on projects implemented;
68
69
70