PORTFOLIO COMMITTEE ON BASIC EDUCATION Presentation on: Provincial Infrastructure Programme ASIDI & SAFE 1 PRESENTATION OUTLINE Purpose National Development Plan Background Provincial Infrastructure Programme ASIDI


slide-1
SLIDE 1

PORTFOLIO COMMITTEE ON BASIC EDUCATION

Presentation on: Provincial Infrastructure Programme ASIDI & SAFE

1

slide-2
SLIDE 2

PRESENTATION OUTLINE

  • Purpose
  • National Development Plan
  • Background
  • Provincial Infrastructure Programme
  • ASIDI
  • SAFE

2

slide-3
SLIDE 3

PURPOSE To present a progress report on Infrastructure planning and delivery as well as SAFE to the Portfolio Committee

  • n

Basic Education.

3

slide-4
SLIDE 4

NATIONAL DEVELOPMENT PLAN “Ensure that all schools meet minimum standards for infrastructure and commit to progressively upgrading each school’s infrastructure to meet

  • ptimum standards.”

National Planning Commission: National Development Plan, November 2011)

4

slide-5
SLIDE 5

NATIONAL DEVELOPMENT PLAN…

“School infrastructure backlogs have been considerably reduced over the past 10 years. But many school environments are still not conducive to learning. The Department of Basic Education has committed itself to eradicating 496 inappropriate structures, providing basic water to 1 257 schools, providing basic sanitation to 868 schools and providing electricity to 878 schools in the 2012/13 financial year. To meet these commitments, the department will have to:

  • Find ways to deliver infrastructure and services more

efficiently and cost-effectively

  • Improve the quality of information used for planning.”

National Planning Commission: National Development Plan, November 2011)

5

slide-6
SLIDE 6

NATIONAL DEVELOPMENT PLAN…

“Take learner safety into account when planning infrastructure.”

National Planning Commission: National Development Plan, November 2011)

6

slide-7
SLIDE 7

BACKGROUND

  • The sector provides infrastructure through three programmes; viz, the provincial

programme, the Accelerated School infrastructure Delivery Initiative (ASIDI) as well as the Sanitation Appropriate for Education initiative (SAFE)

  • The Provincial Schools Build Programme is implemented by provinces and it

targets the provision of basic services, new schools, additions to existing schools, new and upgrading of services and maintenance. It is funded through the Education Infrastructure Grant and the Provincial contribution through the equitable share.

  • The Accelerated School Infrastructure Delivery Initiative is a programme driven by

the DBE to address school's infrastructure backlog on schools that do not meet the basic safety norms and standards. It is funded through the Schools Infrastructure Backlogs Grant. The purpose of the programme is for the eradication of schools made entirely of inappropriate structures and the provision of basic level of water, sanitation and electricity to schools.

  • The Sanitation Appropriate for Education initiative (SAFE) is a programme driven by

the DBE to eradicate all pit latrines and other forms of unacceptable sanitation, provide safe and appropriate ablution facilities as well as address insufficient or inadequate sanitation facilities and maintenance of all ablution facilities

7

slide-8
SLIDE 8

KEY AREAS

  • Construction, maintenance, upgrading and rehabilitation of new and

existing infrastructure in education including district and circuit accommodation;

  • Provide infrastructure to match curriculum requirements;
  • Replace inappropriate schools;
  • Provision of basic services;
  • Address damage to infrastructure caused by natural disasters;
  • Extend existing schools with additional classrooms/facilities;
  • Address achievement of the targets set out in the minimum norms and

standards for school infrastructure; and

  • Enhance capacity to deliver infrastructure in education.

8

slide-9
SLIDE 9

TOTAL INFRASTRUCTURE BUDGET – 2019/20 FY

EIG 73.8% ES 12% SIBG 14.2% EIG, R 10.514 bn ES, R 1.713 bn SIBG, R 2.027 bn

Total Budget = R 14. 255bn

EIG = Education Infrastructure Grant ES = Equitable Share SIBG = Schools Infrastructure Backlog Grant

9

slide-10
SLIDE 10

10

PROVINCIAL INFRASTRUCTURE PROGRAMME

slide-11
SLIDE 11

2019 EIG MTEF ALLOCATIONS

Provinces

Allocation MTEF Estimates

2019/20 2020/21 2021/22 R'000 R'000 R'000 Eastern Cape 1 585 532 1 564 208 1 685 128 Free State 833 485 722 425 778 272 Gauteng 1 474 715 1 440 169 1 551 501 KwaZulu-Natal 2 187 162 2 013 405 2 169 050 Limpopo 1 050 160 1 175 467 1 266 336 Mpumalanga 731 792 819 111 882 432 Northern Cape 639 817 505 649 544 738 North West 902 484 1 010 169 1 088 260 Western Cape 1 109 331 1 031 186 1 110 902 Unallocated

  • 1 184 844

1 250 010 Total 10 514 478 11 466 632 12 326 629

11

slide-12
SLIDE 12

INFRASTRUCTURE ALLOCATIONS 2019/20

12

Provinces EIG Equitable Share Total % of equitable share to total budget

Eastern Cape

1,585,532 1,585,532 0%

Free State

833,485 16,378 849,863 1.9%

Gauteng

1,474,715 474,821 1,949,536 24.4%

KwaZulu-Natal

2,187,162 359,210 2,546,372 14.1%

Limpopo

1,050,160 1,826 1,051,986 0.2%

Mpumalanga

731,792 202,727 934,519 21.7%

North West

902,484 2,228 904,712 0.2%

Northern Cape

639,817 7,720 647,537 1.2%

Western Cape

1,109,331 648,843 1,758,174 36.9% 10,514,478 1,713,753 12,228,231

slide-13
SLIDE 13

TARGETS FOR THE 2019/20 FY

13

No. PROGRAMME

Target 2019/20

EC FS GP KZN LP MP NC NW WC 1 Full Service Schools 1 1 5 2 Provision/replacement of Sanitation 178 73 13 150 13 85 14 12 14 3 Provision/upgrade of Water 178 10 13 150 22 3 9 10 14 4 Provision/upgrade of Electricity 5 10 13 100 1 1 11 14 5 Maintenance Projects 20 27 40 370 34 29 36 48 173 6 Libraries Project 5 1 13 12 2 3 4 7 7 Laboratories Projects 5 4 13 12 1 8 7 8 School Halls 1 13 2 5 7 9 Technical Workshops 2 10 Nutrition Centres 5 7 13 10 9 3 5 5 15 11 Additional Classrooms 285 39 350 210 22 104 43 26 68 12 Grade R Classrooms 13 18 200 50 23 3 8 10 73 13 Administration Blocks 5 4 13 10 3 5 4 7 15 14 Provision/upgrade of fence 302 9 13 40 1 15 5 15 15 Provision/upgrade of sport field 13 9 1 3 5 8 15 16 Special Schools 1 2 1 17 Boarding Schools 2 19 18 Guard House 13 9 4 1 7 19 Natural Disasters Projects 2 150

slide-14
SLIDE 14

NEW & REPLACEMENT SCHOOLS – 5 YEAR PERIOD

14

PROVINCE

FINANCIAL YEARS

TOTAL 2019/20 2020/21 2021/22 2022/23 2023/24 Eastern Cape 1 5 3 9 Free State 6 3 2 4 2 17 Gauteng 7 8 7 6 6 34 KwaZulu-Natal 7 5 1 13 Limpopo 12 4 14 9 11 50 Mpumalanga 2 6 7 5 2 22 Northern Cape 3 2 11 3 5 24 North West 14 3 11 12 1 41 Western Cape 13 7 10 10 10 50 ASIDI 40 31 29 100 TOTAL 104 70 97 52 37 376

slide-15
SLIDE 15

OVERALL INFRASTRUCTURE EXPENDITURE – SEPTEMBER 2019

15

Total Infrastructure Spending as at end September 2019 PROVINCE Allocated Budget 2019/20 ('000) Total Spent as at end September 2019 ('000) % Spent of Allocated Budget Eastern Cape 1,585,532 876,882 55% Free State 849,863 337,569 40% Gauteng 1,949,536 476,773 24% KwaZulu-Natal 2,546,372 1,281,619 50% Limpopo 1,051,986 254,945 24% Mpumalanga 934,519 545,389 58% North West 904,712 183,984 20% Northern Cape 647,537 263,316 41% Western Cape 1,758,174 781,989 44% TOTAL 12 228 231 5 002 466 41%

slide-16
SLIDE 16

EDUCATION INFRASTRUCTURE GRANT SEPTEMBER 2019

16

Education Infrastructure Grant Expenditure as at end September 2019 PROVINCE Allocated Budget 2019/20 ('000) EIG Transfers to PEDs ('000) Total Spent as at end September 2019 ('000) % Spent of the transferred Amount % Spent of Allocated Budget Eastern Cape 1,585,532 990,958 876,668 88% 55% Free State 833,485 520,928 330,546 63% 40% Gauteng 1,474,715 921,697 428,981 47% 29% KwaZulu-Natal 2,187,162 1,367,157 1,164,205 85% 53% Limpopo 1,050,160 656,350 254,937 39% 24% Mpumalanga 731,792 457,370 504,643 110% 69% North West 902,484 564,052 183,139 32% 20% Northern Cape 639,817 399,886 260,064 65% 41% Western Cape 1,109,331 693,332 453,018 65% 41% TOTAL 10 514 478 6 571 730 4 456 201 68% 42%

slide-17
SLIDE 17

MAINTENANCE – SEPTEMBER 2019

17

Prov

  • No. of

Maint’nce Projects in 2019/20 FY Overall Adjusted Infrastructure Budget ('000) Maint’nce Budget ('000) %ge Maint’nce Budget to Total Total Expenditure as at end September 2019 ('000) %ge Expenditure

  • n Maint’nce

Relative to Maint’nce Budget Eastern Cape 454 R 1,585,532 R 255,716 16% R 130,786 51% Free State 27 R 849,863 R 158,668 19% R 39,540 25% Gauteng 144 R 1,949,536 R 1,083,137 56% R 240,909 22% KwaZulu-Natal 445 R 2,546,372 R 944,228 37% R 304,308 32% Limpopo 119 R 1,051,986 R 360,106 34% R 27,249 8% Mpumalanga 118 R 934,519 R 131,468 14% R 94,759 72% North West 62 R 904,712 R 114,097 13% R 33,575 29% Northern Cape 113 R 647,537 R 181,294 28% R 79,729 44% Western Cape 173 R 1,758,174 R 646,215 37% R 287,283 44% TOTAL 1 655 12 228 231 3 874 929 32% 1 238 138 32%

slide-18
SLIDE 18

PROGRESS – NEW AND REPLACEMENT SCHOOLS

18

SUMMARY OF PROJECTS COMPLTED FOR THE 2019/20 FINANCIAL YEAR Province TARGET 2018/19 NEW SCHOOLS TARGET 2018/19 REPLACEMENT SCHOOLS TOTAL SCHOOLS TARGETED TOTAL COMPLETED PROGRESS FIRST QUARTER SECOND QUARTER THIRD QUARTER FOURTH QUARTER TOTAL FIRST QUARTER SECOND QUARTER THIRD QUARTER FOURTH QUARTER TOTAL Number of Schools

Eastern Cape 1 4 5 0% Free State 7 2 1 3 3 10 3 30% Gauteng 4 1 1 2 1 5 2 40% Kwazulu Natal 5 1 1 2 1 1 7 2 29% Limpopo 4 1 5 6 4 1 6 7 8 13 163% Mpumalanga 3 3 3 1 1 1 4 4 100% Northern Cape 2 2 4 0% North West 2 5 7 0% Western Cape 4 2 2 9 1 1 13 3 23% Total Number of schools 32 9 8 17 31 2 8 10 63 27 43%

slide-19
SLIDE 19

IDMS REPORT 2nd QUARTER OF 2019/20 PER PROVINCE

19

Programme Total Targets for 2019/20 Q2 EC FS GP KZN LP MP NC NW WC Total Number of New Schools 32 1 1 1 5 8 Replacement schools 31 1 6 1 8 Full Service Schools 13 2 2 Provision/replacement of Sanitation 776 2 2 19 46 23 11 103 Provision/upgrade of Water 515 2 2 64 17 5 1 91 Provision/upgrade of Electricity 133 2 2 1 5 Maintenance Projects 727 2 25 4 14 9 15 69 Libraries Project 45 2 4 7 1 14 Laboratories Projects 51 2 3 2 9 16 School Halls 30 8 1 2 11 Technical Workshops 8 5 5 Nutrition Centres 51 4 1 5 Additional Classrooms 1020 12 69 34 21 7 15 158 Grade R Classrooms 266 3 4 4 5 4 4 2 26 Administration Blocks 52 1 6 55 1 2 65 Provision/upgrade of fence 387 1 1 30 16 2 3 53 Provision/upgrade of sport field 28 Special Schools 3 Boarding Schools 31 1 1 Guard House 30 2 1 3 Natural Disasters Projects 185 17 4 21

slide-20
SLIDE 20

PROJECT DISTRIBUTION

20

Prov

  • No. of Projects

Budgeted for PROGRESS Planning Construction Close-out EC 2,916 1,197 445 1274 FS 152 40 112 GT 290 216 61 13 KZ 1,311 520 420 371 LP 682 174 387 121 MP 624 409 140 75 NC 405 235 140 30 NW 265 93 64 108 WC 98 69 26 3 TOTAL 6,743 2,953 1,795 1,995 37% 35% 28%

slide-21
SLIDE 21

HUMAN RESOURCES

21

Provnce No of Approved Posts Filled Not Filled Progress % Eastern Cape 63 42 21 67% Free State 78 50 28 64% Gauteng 101 83 18 82% KwaZulu-Natal 74 71 3 96% Limpopo 65 49 16 75% Mpumalanga 113 97 16 86% North West 54 30 24 56% Northern Cape 81 43 38 53% Western Cape 54 45 9 83% Total Weight 683 510 173 75%

slide-22
SLIDE 22

CAPACITATION PLANS – REQUIRED SKILLS SET

Quantity Surveyors 11% Architects 9% Elec.Engineers 2% Civil Engineers 3% GIS Specialists 1% Town & Regional Planners 5%

  • Ed. Facility

Planners 9% Works Inspectors 33% Finance and administration 27%

22

slide-23
SLIDE 23

23 Reports Submission Date Compliance Final U-AMP for 2019/20 Due 30 March 2019 This is the final plan for all programmes to be implemented over the period of at least 10 years. Monthly IRM reports 22 Day of each month This report captures all infrastructure projects being implemented in the financial year and seeks to present the financial and non financial progress of projects End of Year Reports for 2018/19 Due 31 May 2019 The main purpose of the end-of-year report is to measure progress made by the programme against the objectives and outcomes set, focusing mainly on the previous financial year Draft U-AMP 2020/21 Due 28 June 2019 This is a draft plan for all infrastructure programmes to be implemented

  • ver the period of at least 10 years.

Infrastructure Programme Management Plan (IPMP) & CPS Due 30 August 2019 The IPMP & CPS is an infrastructure programme management plan which includes the construction procurement strategy for infrastructure programmes or projects envisaged to commence within the period for the medium term expenditure framework (MTEF period). The plan specifies how the infrastructure programme will be executed, monitored and controlled. Human Resource Reports 22 Days after end of each Quarter This report seeks to measure progress of the implementation of the DoRA Human Resource Strategy. It report provides progress on the filling

  • f posts on the approved establishment for the infrastructure unit of the

affected provincial department Non-Financial Performace Reports Due 30 days after end of each Quarter The purpose of this report is to measure quarterly progress made by the programme against the objectives and outcomes set for the specific financial year.

MONITORING OF THE PROVINCIAL PROGRAMME

slide-24
SLIDE 24

24

PBS 2019/20 ASSESSMENT PROCESS

Weighting for the 2019/20 assessment process (R1.185 billion)

Focus Area Documents / Reports Weight End of the year evaluation report 20% Human Resource Capacitation 5% Infrastructure Reporting Model 40% User-Asset Management Plans 15% Infrastructure Programme Management Plans and; Construction Procurement Strategy Performance Planning 20% TOTAL WEIGHT 100%

slide-25
SLIDE 25

PROJECT COMPLETIONS | STORMS RIVER PRIMARY

25

Implementing Agent: Department of Public Works Allocated budget: R 51.1 million Construction Period: 33 months Project completed: January 2019

slide-26
SLIDE 26

PROJECT COMPLETIONS | SIVE SPECIAL SCHOOL

26

Implementing Agent: Independent Development Trust Allocated budget: R124 million Construction Period: 54 months Project completed: June 2018

slide-27
SLIDE 27

NOKUTHULA LSEN SCHOOL

27

slide-28
SLIDE 28

OLIVENHOUTBOSCH SECONDARY SCHOOL

28

slide-29
SLIDE 29

MANDLA MTHETHWA SCHOOL OF EXCELLENCE

29

slide-30
SLIDE 30

Thembisa Special School

  • Project experiencing intermittent stoppages

30

COMMUNITY DISRUPTIONS

slide-31
SLIDE 31

31

slide-32
SLIDE 32

32

2019/20

2020/21 2021/22 R'000 R'000 R'000 ASIDI 1 327 048 996 036 1 038 937 SAFE 700 000 800 000 1 300 000

TOTAL 2 027 048 1 796 036 2 338 937

MTEF BUDGET ALLOCATIONS

slide-33
SLIDE 33

OVERALL PERFORMANCE

33 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 TargetedCompleted Q1 Q2 Q3 Q4 Deviation Inapp Structures

  • 17

36 59 52 16 14 21 229 40 14 8 6

  • 26

Sanitation 41 89 161 152 38 41 32 207 834 311 73 46 27

  • 238

Water 16 64 135 317 90 35 42 205 957 432 53 39 14

  • 379

Electricity 148 101 39 18 66 372 Past Performance Electricity Scope Completed Current Financial Year 2019/20 Sub- Programme Complete d since Inception

slide-34
SLIDE 34

DU NOON PRIMARY

34

slide-35
SLIDE 35

PHOTOS : CLARKSON/AMAMFENGU

35

slide-36
SLIDE 36

|

3 6

CONSTRUCTION PROGRESS – ASIDI 15

Siyavuya JPS Sihlahleni JSS Mbekweni HS

Sifonondile JPS

slide-37
SLIDE 37

|

3 7

CONSTRUCTION PROGRESS – ASIDI FREE STATE

BHEKIZULU JSS HERMANA PS EBENHAUSER INTERMEDIATE

TWEESPRUIT PS

slide-38
SLIDE 38

2019/20 APP : PROGRAMME 4

Strategic Objective Programme Performance Indicator Medium-term targets

2019/20 2020/21 2021/22 4.2 Provide basic infrastructure services (water, sanitation, electricity) and replace schools built using inappropriate materials

  • n an annual basis in
  • rder to improve the

conditions under which learners are taught 4.2.1 Number of new schools built and completed through ASIDI

40 31 29

4.2.2 Number of schools provided with sanitation facilities through ASIDI.

717 691 995

4.2.3 Number of schools provided with water through ASIDI.

225 125

38

slide-39
SLIDE 39

2019/20 APP : PROGRAMME 4 QUARTERLY TARGETS

39

Quarterly Targets Programme Performance Indicator Annual Target 2019/20 1st 2nd 3rd 4th

Number of new schools built and completed through ASIDI 40 8 5 12 15 Number of schools provided with sanitation facilities through ASIDI 717 120 147 210 240 Number of school provided with water through ASIDI 225 147 25 35 18

slide-40
SLIDE 40

INAPPROPRIATE STRUCTURES

40

<25% 25%-49% 50%-74% >75%

DBSA 114 3 4 5 2 2 13 98 IDT 31 3 5 3 8 20 CDC 31 2 2 1 2 7 24 DRPW 16 16 NDPW 20 1 3 2 2 7 14 5 DBE# 29 29 29 DBE# 57 57 27 5 8 4 8 25 5 Sub-Total

  • 298

63 14 17 14 22 67 168 IDT 6

  • 2

2 4 DBSA 19

  • 1

1 18 FSDoE 5

  • 2

3

  • 5

Sub-Total

  • 30

2 3 3 8 22 KZN Adopt-A-School 3

  • 3

WC WCED 25

  • 25

MP DBSA 5

  • 5

NW DBSA 2

  • 2

NC DBSA 1

  • 1

LP DBSA 3

  • 3

Total 367 63 14 19 17 25 75 229 Projects in Construction No of Projects Complete d FS Provinces Implementing Agents (IA) Projects being Implement ed Construction Progress Design & Procur ement EC Tender Cancelled. Projects to be Re-Tendered

slide-41
SLIDE 41

SANITATION PROGRESS

41 <25 % 25% - 49% 50% - 74% >75% LP 437

  • - 2 18 37 57 380

EC 298 17 6 1 14 17 38 243 FS 39 27

  • - - - - 12

KZN 116

  • 3 3 4 - 11 105

NC 13 - - - - - - 13 NW 18 8

  • - - - - 10

GP 14 - - - - - - 14 MP 38 - - - - - - 38 WC 19 - - - - - - 19 TOTALS 992 52 9 6 36 54 106 834 No of Projects Completed Construction Progress Planning, Design & Procurement Projects being Implemented PROVINCES Projects in Construction

slide-42
SLIDE 42

WATER PROGRESS

42

<25 % 25% - 49% 50% - 74% >75% EC 520 21 1 - 7 150 158 341 MP 36

  • - - - - - 36

FS 67 14

  • - - - - 53

GP

  • - - - - - -

KZN 224 6 3 1

  • - 4 214

LP 364

  • 2 14 12 35 62 302

NC 5

  • - - - - 5

NW 3

  • - - - - - 3

WC 3

  • - - - - 3

TOTALS 1 222 41 6 15 19 185 224 957 No of Projects Completed Construction Progress Planning, Design & Procurement Projects being implemented PROVINCES Projects in Construction

slide-43
SLIDE 43
  • Effective monitoring of the provision of infrastructure Professional Service

Providers (PSP’s) and Implementing Agents (IA’s) that the Department of Basic Education and provinces are utilizing for the implementation of the infrastructure programme.

  • Monitoring addresses planning, budgeting, expenditure, procurement and

project management. These are interrogated and a sample of projects are

  • visited. Based on the findings from these visits, remedial actions are

devised with the province and monitored by the DBE.

  • Monitoring deals with both programme and project matters;
  • Programme matters include:
  • The pattern of overall expenditure being achieved;
  • Comparisons of expenditure to projected cash flows;
  • Progress being made with key groups of projects [eg. Water, sanitation,

libraries, laboratories, Grade R]

  • Management of the portfolio of projects [ie evidence that the programme
  • f projects is being managed effectively through the project cycle];

MONITORING

43

slide-44
SLIDE 44
  • At the Project level the focus is on ensuring:
  • that PSP appointments are being made;
  • that planning and design processes are progressing;
  • that the tender process for the appointment of contractors is progressing, that

construction is progressing satisfactorily, [i.e. on programme, on budget, at acceptable quality…]; and

  • that projects are being handed over and closed out and that final accounts are

being wrapped up.

MONITORING (CONT.…)

44

slide-45
SLIDE 45

CHALLENGES & REMEDIAL ACTIONS

45

CHALLENGE NATURE OF CHALLENGE REMEDIAL ACTION

1.

  • Declining/ no allocation of the Equitable

Share toward Infrastructure Delivery poses pressure on the Education Infrastructure Grant.

  • Delay payment to contractors resulting in

sites been abandon. Budget/ Finance

  • PEDs are to allocate Equitable Share.
  • Delay projects on pre-construction stage to

commence to construction, whilst awaiting for adjustments.

  • Monitor the submission of the invoices of the

work done by the IA to ensure that work on ground is equivalent to the expenditure.

  • PEDs and the IA to reconcile figures on monthly

bases. 2.

  • Lack of Programme Management System

with reliable data information to enhance the planning and delivery of the required Infrastructure timeously IT

  • Deployment and the implementation of a

transversal system (EFMS) by all the PEDs to manage the data.

  • PEDs to increase the IT capacity to house the

system. 3.

  • Excessive number of schools requiring

maintenance Planning

  • Re-alignment and reprioritisation of all the

projects earmarked for maintenance to comply with the DoRA condition of the 30% allocation towards the programme.

  • PEDs to ensure that projects are assessed to

avoid duplications or over emphasis on the same schools. 4.

  • Non- compliance with SCM processes

resulting in irregular expenditure by the Implementing Agent Procurement

  • PEDs to conduct quarterly audits to ensure

compliance on all the process.

slide-46
SLIDE 46

CHALLENGES & REMEDIAL ACTION (….CONTINUE)

46

CHALLENGE NATURE OF CHALLENGE REMEDIAL ACTION

5.

  • Late appointment of service providers

(contractors) by the Implementing Agent for projects that were already planned and designed in previous financial years.

  • IA’s lack of capacity resulting in extension
  • f times, variations orders and delayed
  • ccupation of the asset,
  • Inaccurate reporting and poor project and

programme management.

  • Contractors lack of capacity resulting in

poor quality of infrastructure.

  • The IAs not meeting the milestone and

expenditure targets as per IPIPs

  • The contractual obligations not carried out

as per the signed SLA with the implementing agents Programme/ Project Management

  • Approval of projects for implementation by the

PED’s prior to the commencement of implementation.

  • The internal capacity through works inspectors

closely monitors the projects under implementation.

  • Monthly progress meeting with IA’s to improve on

reporting and to mitigate any challenges.

  • Stricter enforcement of timeframes as proposed

by FIPDM schedule and the projects reassigned to IA’s that have the capacity to delivery.

  • Amendment of the SLA’s to ensure that all

engagements are regulated in order to be able to enforce of penalties on non-performing.

  • Withdrawing and re-allocation of projects to
  • ther performing Implementing Agents.
  • Project disruptions by Business Forums

and Local Communities

  • Volatility of the construction industry

leading to many companies going under and others filing for Business Rescue Programme/ Project Management

  • Continuous engagement with Local Community

and Political Leadership to address the identified challenges.

  • Effective and close project monitoring and

forecasting of trends

slide-47
SLIDE 47
slide-48
SLIDE 48

BACKGROUND

  • The audit revealed that 3898 (desktop study) schools

still have inappropriate sanitation facilities.

  • An allocation of R2.8 billion has been allocated for the

SAFE Initiative over the MTEF as follows: – 2019/20 : R700 000 000.00 – 2010/21 : R800 000 000.00 – 2021/22 : R1 300 000 000.00

  • The SAFE Initiative will be implemented through:

– Provincial EIG allocation – Partnerships/Donations – SAFE Initiative Allocation

48

slide-49
SLIDE 49

49

AUDIT (PIT LATRINES)

slide-50
SLIDE 50

AUDIT: KWAZULU-NATAL

slide-51
SLIDE 51

AUDIT: EASTERN CAPE

slide-52
SLIDE 52

FINANCIAL REPORT – SAFE ALLOCATION

52

IA

  • No. of

Projects Estimated Total Budget Paid to date Invoice at hand Comments DBSA 240 R 256, 197,789.95 R 0 R 126 410 728.11 Awaiting supporting documents from the IA. (Tranche payment) DEA 58 R 63 729 187.69 R 0 R0 DEA is awaiting for National Treasury to approve deviation from normal procurement process before any invoice can be generated. The Mvula Trust 187 R 268 531 197.17 R 0 R 11 847 646.58 Awaiting supporting documents from the IA. (Assessment reports - Planning) NECT 121 R 100 685 316.15 R 0 R 40 274 126 .46 Awaiting National Treasury approval to extend the scope of work for NECT. (Tranche payment) TOTAL 606 R 689 143 490.96 R 0 R 178 532 501.15 26% of invoice at hand

slide-53
SLIDE 53

PROGRESS ON VERIFICATION

53

Province

  • No. of

Schools Verification Balance Comments Verified PIT Proper Sanitation EC 1598 359 305 54 1239 Further verification to commence mid October. FS 156

  • 156*

No verification will be carried-out as the province is implementing all the projects. KZN 1365 335 255 80 668 (1030) 362 Schools will not be verified, the province has allocated the projects to be implemented with EIG allocation. LP 507 259 217 42 248 All the schools will be verified by the end of October MP 127 88

  • 39*

39 Schools will not be verified, the province is implementing all the projects with EIG allocation. NW 145 137 66 71 8 Verification to be completed by 8 October. TOTAL 3898 1205 843 247 2136

  • FS & MP all the schools will be implemented with the EIG.
  • 606 of the 843 schools are currently under implementation.
slide-54
SLIDE 54

PROJECTS UNDER IMPLEMENTATION SAFE ALLOCATION & EIG

54

Province

  • No. of Projects

Planning Construction

EC 262 262 FS 148 80 68 KZN 402 372 30 LP 162 162 MP 33 4 29 Total 1007 880 127

  • 880 Projects are currently under planning and design phase.
  • 127 Projects are currently under construction.
slide-55
SLIDE 55

COMPLETED PROJECTS

Province

  • No. of Projects

Donor EIG & ASIDI

EC 11 4 7 FS 29 29 KZN 93 2 91 LP 35 3 32 MP 20 9 11 TOTAL 188 18 170

55

  • To date 188 Schools have been provided with adequate sanitation.
slide-56
SLIDE 56

CHALLENGES / REMEDIAL ACTIONS

CHALLENGES REMEDIAL ACTION

  • Planning and implementing within

the same year is the major cause of delay.

  • All the projects for the next financial

year will be allocated to the IAs at the beginning of the fourth quarter, for planning to commence within the current financial year.

  • To ensure that implementation

commences at the beginning of the financial year.

  • The procurement process is delaying

the commencement of construction.

  • Project monitoring to ensure that all

projects are completed in time and the quality is up to standard.

  • Increase the capacity to monitor

project implementation.

slide-57
SLIDE 57

57

SEKANEKAMOYI PRIMARY SCHOOL

PROJECT PHOTOS

slide-58
SLIDE 58

58

MAMAILA PRIMARY SCHOOL

PROJECT PHOTOS

slide-59
SLIDE 59

59

PAAPA PRIMARY SCHOOL

PROJECT PHOTOS

slide-60
SLIDE 60

60

TSHINANGE PRIMARY SCHOOL

PROJECT PHOTOS

slide-61
SLIDE 61

61

RAMOTLHATSWANE PRIMARY SCHOOL

PROJECT PHOTOS

slide-62
SLIDE 62

62

SEKANEKAMOYI PRIMARY SCHOOL

PROJECT PHOTOS

slide-63
SLIDE 63

DEDENI JSS - SANITATION

63

slide-64
SLIDE 64

64

ASSUPOL DONATION

Ntlhodumela PS Maaphoko LPS Govani Govani PS

slide-65
SLIDE 65

PLANNING, DELIVERY AND MAINTANANCE ▪ Integrated National School Infrastructure Sector Plan: All schools in the country profiled in terms of their infrastructure needs in line with Norms and Standards; ▪ Revise Education Infrastructure Delivery Model: This delivery model will address:

▪ Expediting delivery of infrastructure projects, ▪ Controlling the cost of providing education infrastructure and; ▪ Improve Contracts Management Processes;

  • Standard Floor Layout Plans and Technical Specifications : Develop standardised plans

and specifications for all Education Facilities (Primary Schools, Secondary Schools, Learner Boarding Facilities, District and Circuit Offices);

  • Establishment of an Education Infrastructure Planning & Management Agency / Bureau:

Infra Bureau/Agency to be set up at national level to centrally facilitate and co-ordinate all the macro and micro planning processes, implementation, monitoring and evaluation of all infrastructure projects in the Basic Education Sector.

PLANS TO IMPROVE INFRASTRUCTURE PLANNING AND DELIVERY

65

slide-66
SLIDE 66
  • Revise project prioritization model to use condition

assessment as a determinant for Project Priority List.

  • Utilization of data from STATS SA , like population trends

at a local level, to ensure that size of schools built addresses the current and future population dynamics;

  • Review of SLA’s/MOA’s with IA’s to impose penalties for

non-compliance with progress delivery, deduct management fees for non compliance or withdraw projects as a result of poor performance.

  • Strengthen

Contract Management and Monitoring processes on infrastructure delivery.

PLANNING, DELIVERY AND MAINTANANCE

66

slide-67
SLIDE 67
  • Strengthen internal Technical Capacity to implement projects, ensuring:
  • Qualified and Professionally Registered key personnel;
  • Accredited Project Managers;
  • Employee retention strategies for attracting and retention of built

environment professionals:

– Revise remuneration scales for professionals; – Improve working conditions and provision of tools of trade;

  • Increase the use of alternative building technologies for quicker

construction;

  • Benchmark with other role players like independent schools to reduce

the cost of building schools;

PLANNING, DELIVERY AND MAINTANANCE

67

slide-68
SLIDE 68

FUNDING AND PARTNERSHIPS

  • Provinces to ensure that sufficient funding is allocated to the Equitable Share

and ring fence such funding for infrastructure;

  • Condition Grant allocations (EIG) to be ring-fenced and used solely for the

intended purpose, as a condition of the grant;

  • EIG Funding allocations to be per project on the basis of an approved Business

Case and progress on projects implemented;

  • Diversified funding modalities for school infrastructure:
  • Public-Private Partnerships (Build, Operate & Transfer – BOT);
  • Donor and Grant funding;
  • Rand-for-Rand Public-Private Partnerships;
  • Partnerships with Institutions of Higher Learning and Non-governmental Organizations.

68

slide-69
SLIDE 69

RECOMMENDATION It is recommended that the Portfolio Committee discusses the progress report

  • n

Infrastructure planning and delivery as well as SAFE.

69

slide-70
SLIDE 70

70