BART to Antioch (eBART) Capacity Im Improvements BART Board Meeting December 6, 2018 Agenda Overview Station Parking Expansion Change Order for Vehicles Motions December 6, 2018 BART Board Meeting 2 Antio ioch


slide-1
SLIDE 1

BART to Antioch (eBART) Capacity Im Improvements

BART Board Meeting December 6, 2018

slide-2
SLIDE 2

Agenda

▪ Overview ▪ Station Parking Expansion ▪ Change Order for Vehicles ▪ Motions

December 6, 2018 BART Board Meeting 2

slide-3
SLIDE 3

Antio ioch Station Rid idership ip (Exit its): Proje jected and Actual

3 December 6, 2018 BART Board Meeting

1,575 4,100 2,270 3,050 Ridership Forecast for 2015 Opening (2009) Ridership Projection for 2030 (2009) Updated Ridership Forecast for 2018 Opening (2016) Current Ridership 2018

Projected (2009)

2015 - Opening 2030 - Horizon

Projected (2016)

2018 - Opening 2018 - Actual

slide-4
SLIDE 4

Surface Parking Exp xpansion and Other Access Im Improvements

BART Property accommodates approx. 800 spaces ON-SITE IMPROVEMENTS NEW LOT 850 STALLS

4 December 6, 2018 BART Board Meeting

Pedestrian access to station

slide-5
SLIDE 5

On On-sit ite Access ss Im Improvements to th the Exi xistin ing Su Surf rface Lo Lot

5 December 6, 2018 BART Board Meeting

Modifications will:

  • Improve ADA location
  • Improve circulation/

passenger flow

  • Minimize potential

conflicts

slide-6
SLIDE 6

Antio ioch New Parkin ing Lot Addit itional Ele lements

6

▪ Site Lighting ▪ Cameras (CCTV) ▪ Emergency call boxes ▪ Landscaping ▪ Solar Panels/PPA* Solar Panels (PPA)

6 December 6, 2018 BART Board Meeting

* Separate procurement through Purchase Power Agreement (PPA)

Pedestrian access to station

slide-7
SLIDE 7

Envir ironmental Analysis

  • The Addendum to the FEIR for the Revised Project

concluded that there are:

  • No substantial changes to the environment
  • No new or more severe impacts
  • Therefore, the Revised Project does not meet the

conditions that would require a subsequent or supplemental EIR.

December 6, 2018 BART Board Meeting 7

slide-8
SLIDE 8

Projec ject Bu

Budget and Proposed Fundin

ing Plan lan

8

Budget:

  • BART to Antioch Project Original Adjusted Budget: $524.9M
  • Estimated Cost at Completion: $510.7M
  • Remaining Funds: $14.17M
  • Estimated Cost of Surface Lot: Approx. $16.0M

Funding Plan:

December 6, 2018 BART Board Meeting

Agency Funding ($ millions)

BART 4.30 MTC 3.61 CCTA Measure J eBART Category 3.26 East Contra Costa Regional Fee and Financing Authority (ECCRFFA) 3.00 Sub Total 14.17 (remaining funds) CCTA Measure J Access Funds: 1.82 TOTAL 16.00

slide-9
SLIDE 9

Prelim liminary ry Antio ioch Parking Lot Schedule

December 6, 2018 BART Board Meeting 9

  • Winter 2018: Requested Board action
  • Spring 2019: Advertise
  • Summer/Fall 2019: Construction
  • Summer/Fall 2020: Open surface lot
slide-10
SLIDE 10

Vehic icles: Stadler Contract Options Provis isions

  • Stadler’s contract provides options for additional

vehicles that will expire April 2019

  • Two-vehicle option
  • Four-vehicle option
  • Stadler has agreed to extend this period for two

additional years to exercise the options with modified pricing provisions at no additional cost to the District

December 6, 2018 BART Board Meeting 10

slide-11
SLIDE 11

Addit itional Vehicle Needs

  • 2022/2023 – Two (2) new vehicles projected to be needed

no later than this based on updated ridership projections

– Current cost estimate: Approximately $21 M*

  • 2025 – Four (4) additional vehicles projected to be needed

to meet BART switching from 15 to 12 min headways

– Current cost estimate: Approximately $40 M*

  • Funding plan currently envisions partnership with Contra

Costa Transportation Authority (CCTA), Metropolitan Transportation Commission (MTC) and BART.

December 6, 2018 BART Board Meeting 11 * Cost estimate subject to producer price index, exchange rate and additional tariffs

slide-12
SLIDE 12

Motion: Station Parkin ing Exp xpansion

Having reviewed and considered the information contained in the Addendum, and the FEIR, the BART Board of Directors hereby: 1) Adopts the attached Resolution, approving the 4th Addendum to the FEIR and adopting the Revised Project 2) Adopts the attached Resolution of Project Compliance authorizing the filing of an allocation request with the Metropolitan Transportation Commission ($3.61M)

December 6, 2018 BART Board Meeting 12

slide-13
SLIDE 13

Motion: Change Order for Vehic icle les

  • Authorize the General Manager to execute a

Change Order with Stadler to extend the time period to exercise contract options from April 2019 to April 2021

December 6, 2018 BART Board Meeting 13