BART Capacity Overview for Click to edit Master title style UCLA Lake Arrowhead Conference October 18, 2010 0 BART Basics 360,000 daily riders 104 miles 43 stations 1.3 billion annual passenger miles 1 Transits Green


slide-1
SLIDE 1

Click to edit Master title style

BART Capacity Overview for UCLA Lake Arrowhead Conference

October 18, 2010

slide-2
SLIDE 2

1

BART Basics

  • 360,000 daily riders
  • 104 miles
  • 43 stations
  • 1.3 billion annual

passenger miles

slide-3
SLIDE 3

2

Transit’s Green Challenge

  • Regional planning focus on smart

growth/sustainable communities

  • Expectation that transit ridership

will increase as a result

2

  • Many rail systems are already experiencing

capacity problems

  • Rail transit infrastructure requires long lead times to

implement, and substantial investment to build, maintain and operate

slide-4
SLIDE 4

3

Downtown SF

Capacity Outlook

  • BART not out of capacity today
  • Near-term growth can be managed:
  • service adjustments
  • station crowd management
  • targeted ticket pricing measures
  • Long-term growth requires major capital

improvements

  • Investments require substantial lead time
  • Capacity improvements unfunded
  • State-of-Good Repair largely unfunded
slide-5
SLIDE 5

4

Priority Development Areas

slide-6
SLIDE 6

5

San Francisco San Jose Oakland

5

Population 2035

  • 2 million more
  • 37% of regional growth

in SJ,SF and OAK

  • 2/3rd of regional in

“Urban Core” (around Bay) Employment 2035

  • 1.8 million more
  • Of top 10 growth areas,

2/3rd of regional growth will be in SJ, SF and OAK Bay Area 2035

Forecast Growth

slide-7
SLIDE 7

6

BART Ridership and SF Job Growth

100000 200000 300000 400000 500000 600000 700000 800000 900000 1969 1974 1979 1984 1989 1994 1999 2004 2009 2014 2019 2024 2029 2034 Year SF Jobs ( 1) 100000 200000 300000 400000 500000 600000 700000 Daily BART Ridership SF Jobs Historic BART Ridership BART FY08 SRTP (FY09 - FY16) MTC T2035 w/o Project MTC T2035 w/ Project

SF Jobs (1)

2035 Low: 536,000 2035 High: 660,000

Daily BART Riders

(1) US Bureau of Labor Statistics

BART Average Daily Ridership

Historic Trends and Projections

slide-8
SLIDE 8

7

SPUR Future of Downtown Report

East Bay Commute is the Most Constrained

Line-Haul Only

slide-9
SLIDE 9

8

Where Do Patrons Enter and Exit?

Patrons Entering & Exiting BART (15-Minute Intervals)

500 1000 1500 2000 2500 3000 3500 4:00 6:00 8:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00

Time of Day Patrons (per 15 minute interval)

Embarcadero Montgomery Powell Civic Center Balboa Park 12th Street Source: BART DAS data, April 2008

slide-10
SLIDE 10

9

BART Ridership

Current Travel Markets

Transbay West Bay East Bay

Weekday Trips by Sub-Area

  • 48%: Transbay
  • 28%: intra-West Bay
  • 24%: intra-East Bay

2/3rds of BART trips to/from Market Street stations

slide-11
SLIDE 11

10

Capacity Limiters

  • San Francisco station dwell times limit

Transbay throughput

  • Platform and onboard crowding
  • Stairs and escalators
  • Current car design – 2 doors per side
  • Transbay Tube - train control system
  • Oakland Wye junction – conflicting

movements

  • Lack of crossovers, turnback tracks,

storage tracks

slide-12
SLIDE 12

11

Transit Capacity Increases

  • Easier to increase capacity on bus systems

quickly, but trade-offs may be operational efficiency.

  • Capital – buses, transit lanes/busways, bus stop improvements,

maintenance facilities

  • Operating costs
  • Rail systems require much longer lead times to

increase capacity.

  • Capital – Additional tracks, civil structures (tunnels, elevated

sections), station improvements, maintenance facilities, right-of- way, vehicles, power and signaling systems

  • Operating costs
slide-13
SLIDE 13

12

Embarcadero Capacity

slide-14
SLIDE 14

BART in MTC Regional Rail Plan

13

slide-15
SLIDE 15

BART Capital Program for Core System

Major Funding Shortfalls

14

$0 $2 $4 $6 $8 $10 $12 $14 Core Infrastructure Renovation Existing Fleet Replacement Capacity Modifications $ billion

BART Capital Program (a) ($billion)

Shortfall Funded (b)

(a) Not shown are $30 million in Security improvements and $30 million in Quality Enhancements (b) Funding as "programmed" in MTC 2035 Regional Transportation Plan

slide-16
SLIDE 16

15

Examples from Other Cities

  • Paris RER System – “Regional

Express Metro” overlaid on top of Paris Metro system – 40+ years to develop

  • New York Subway – major lines built
  • riginally as 4-track lines with express

train capability

  • US commuter rail – conversion to

double deck equipment

slide-17
SLIDE 17

16

JR Railway (Japan)

Supply-Side Strategy

slide-18
SLIDE 18

Capacity Overview

Questions?

17

slide-19
SLIDE 19

18

Capacity Constraints

Where Could BART See Problems in the Future?

  • On-Board Train Crowding

 Passenger per Seat or per Car (Load Factors)  Train Control System  Vehicles

  • SF Downtown Stations

 Platform Crowding (PM)  Stair, Escalator & Faregate Queuing (AM)  Emergency Exiting

  • Yards & Shops
  • Station Access
slide-20
SLIDE 20

19

Transbay Corridor Management

Illustrative – Phased Improvements over 50 Years

  • Max. Load Point in peak direction

(future peak hour increase)

Short < 2,500 Medium 2,500 – 7,500 Long 7,500 – 12,000 BART Remove Train Seats  Demand Management Strategies    Station Access    Station Capacity   3-Door Train Fleet  Train Control Improvements  Expand Train Fleet   Construct New Transbay Tube + Stations  Bus Transbay Terminal  Bay Bridge Contra-Flow Lane 

slide-21
SLIDE 21

20

BART Transit Supply

Capacity Thresholds (peak hour)

20

Projected Peak Hour Future Capacity

Constraint 2009 Actual Ridership

Baseline (23 trains/hr) 1

% Additional Growth

Enhanced (31 trains/hr) 2

% Additional Growth Tube (one direction) 17,750 24,600 39% 33,150 87% Embarcadero 10,000 13,000 30% 14,000 40% Montgomery 9,500 14,250 50% 15,000 58%

Source: Arup, Capacity Scenarios for DMS Modeling Memo, May 19, 2009

1

23 trains / hr assumes No Delay scenario.

2

31 trains / hr assumes Delay scenario, and improved train control system

Preliminary Analysis