ast rule summary
play

AST Rule Summary Mountaineer Gas Company Presentation January 10, - PowerPoint PPT Presentation

AST Rule Summary Mountaineer Gas Company Presentation January 10, 2017 Ruth Porter, Tanks Program Manager Joe Sizemore, Assistant Chief Inspector www.dep.wv.gov/tanks WV Code Chapter 22, Article 30 AST Act Originally established via


  1. AST Rule Summary Mountaineer Gas Company Presentation January 10, 2017 Ruth Porter, Tanks Program Manager Joe Sizemore, Assistant Chief Inspector

  2. www.dep.wv.gov/tanks

  3. WV Code Chapter 22, Article 30 • “AST Act” • Originally established via Senate Bill 373 in the 2014 Legislative Session • Revised via Senate Bill 423 in the 2015 Legislative Session • Response to the Freedom Industries Spill

  4. SJM1 Risk Based Program • Level 1 ASTs – Located in a zone of critical concern (ZCC), source water protection area (SWPA); or – 50,000 gallons or greater; or – Contains a substance from EPA’s List of List at concentration of 1% or greater • Level 2 ASTs – Located in a zone of peripheral concern (ZPC) and not a Level 1 • Register and Label ASTs

  5. AST Rules • 47 CSR 63 – AST Rule – Specific tank operation and management requirements • 47 CSR 64 – AST Fee Rule – Annual fees for regulated tanks • 47 CSR 65 – Administrative Penalty Rule – Resolution of enforcement actions and assessment of penalties

  6. AST Rule • Operation & Maintenance – Registration, construction, installation, upgrades, inspection, maintenance, testing, and closure of tank systems. • Twelve (12) Sections

  7. Section 3 ‐ Registration • It is unlawful to operate an AST after July 1, 2015 unless it is “properly” registered and registration fees are paid. • An Owner must register within thirty (30) days after installation or acquiring an AST, but can’t operate the AST until it is properly registered.

  8. Section 4 ‐ Certificate to Operate, Permits/Plans & Siting Requirements • Applies only to Level 1 & Level 2 ASTs • Certificate to Operate – Renewed automatically – Annual basis • Allows for ASTs to be regulated under existing permit. • Siting requirements for ASTs with flammable or combustible liquids.

  9. Section 5 ‐ Operation and Maintenance • Secondary Containment Inspections – Level 1 every 14 days – Level 2 once a month • Monthly AST system visual inspection – Level 1 & Level 2 ASTs

  10. SJM2 Section 5 ‐ Operation and Maintenance • Annual Inspections & Certifications – Level 1 & Level 2 ASTs – By January 28, 2017 and on or before January 1, 2018 and then on or before January 1 of each year thereafter. – Every 3 years for Level 1 AST ( PE, API or STI certified inspector) – Every 5 years for Level 2 AST ( PE, API or STI certified inspector)

  11. AST Inspection Certification Frequencies (47 CSR 63 ‐ 5.2) 1/10/2017 Enter AST Registration Date: Level 1 Level 2 1/28/2017 1/28/2017 PE, API, STI Certification Due* PE, API, STI Certification Due* 1/1/2018 1/1/2018 Owner Certification Due Owner Certification Due 1/1/2019 1/1/2019 Owner Certification Due Owner Certification Due 1/1/2020 1/1/2020 PE, API, STI Certification Due Owner Certification Due 1/1/2021 1/1/2021 Owner Certification Due Owner Certification Due 1/1/2022 1/1/2022 Owner Certification Due PE, API, STI Certification Due 1/1/2023 1/1/2023 PE, API, STI Certification Due Owner Certification Due 1/1/2024 1/1/2024 Owner Certification Due Owner Certification Due 1/1/2025 1/1/2025 Owner Certification Due Owner Certification Due 1/1/2026 1/1/2026 PE, API, STI Certification Due Owner Certification Due 1/1/2027 1/1/2027 Owner Certification Due PE, API, STI Certification Due 1/1/2028 1/1/2028 Owner Certification Due Owner Certification Due 1/1/2029 1/1/2029 PE, API, STI Certification Due Owner Certification Due

  12. Section 5 ‐ Operation and Maintenance • Internal Inspections (STI SP001 or API 653) – Not required for ASTs ≤ 30,000 gallons • Spill Prevention Response Plan (SPRP) – Tank owner/operator can certify they have an approved SPCC or GPP – Required by December 9, 2015 – Updated every 5 years or sooner if certain triggers reached

  13. Section 6 ‐ Reporting and Recordkeeping • Owners/operators must keep records for: – Financial Responsibility – Inspections – Leak Detection – Corrosion protection – Secondary containment checks – Documentation of repairs – Closures

  14. Section 6 ‐ Reporting and Recordkeeping • Confirmed, Suspected or Threatened Releases – Notify WVDEP immediately for Confirmed Release – Notify within 24 hours for Suspected or Threatened Release unless a false alarm

  15. Section 7 ‐ Corrective Action • Release response requirements – Notify WVDEP – Contain the release – Perform corrective action

  16. Section 8 ‐ AST Design, Construction, and Installation • AST must be used for what they were designed for • Foundation and support requirements • Tightness testing of ASTs at install and/or reconstruction • All new Level 1 tanks installed shall be double walled, double bottomed, or installed with a Release Prevention Barrier

  17. Section 9 ‐ Corrosion and Deterioration Prevention • Acceptable corrosion methods are: – Cathodic protection systems (galvanic or impressed current) – Exterior Coatings – Interior linings and coatings – ASTs constructed of noncorrodible materials – Storage in a manner prevents metal contact with an electrolyte

  18. Section 9 ‐ Corrosion and Deterioration Prevention • Cathodic protection system must be designed by a NACE certified (or equivalent) corrosion expert. • Cathodic protection systems must be tested within 6 months of installation and every 3 years thereafter ‐ NACE certified CP tester.

  19. Section 9 ‐ Corrosion and Deterioration Prevention • Impressed current systems must have the rectifier inspected every sixty (60) days. • All impressed current systems shall be tested by a NACE certified CP tester every twelve (12) months as part of a preventative maintenance program to minimize in ‐ service failure.

  20. Section 9 ‐ Corrosion and Deterioration Prevention • The impressed current source shall not be de ‐ energized at any time, including periods when the facility is closed: – except during power failures or – during service work on the regulated AST or impressed current system).

  21. Section 9 ‐ Corrosion and Deterioration Prevention • The criteria for determining the effectiveness of cathodic protection ( ‐ 850 mV with the CP current applied). • Alternatively, a negative potential of at least 850 millivolts from instant off reading or a 100 mV shift from the instant off position is acceptable for impressed current systems.

  22. Section 10 ‐ Release Prevention, Leak Detection, & Secondary Containment • Spill and overfill – Overfill and spill equipment must be properly installed, operated, inspected, tested, and maintained in accordance with the manufacturer’s specifications – For sites receiving deliveries, ASTs must have overfill device or deliveries must be constantly monitored – For sites not receiving deliveries, owner/operators must monitor the AST to ensure that spill and overfills don’t occur

  23. Section 10 ‐ Release Prevention, Leak Detection, & Secondary Containment • Secondary containment for existing AST systems needs to hold a released substance for a minimum of seventy ‐ two (72) hours. • Secondary containment for new LEVEL 1 AST systems must have a permeability less than 1 x 10 ‐ 7 cm/sec.

  24. Section 10 ‐ Release Prevention, Leak Detection, & Secondary Containment – Existing Level 1 & Level 2 ASTs must perform leak detection monthly by a method listed below: • Visual • Automatic tank gauging • Statistical inventory reconciliation • Interstitial monitoring • Soil vapor monitoring within secondary containment • Volumetric or mass measurements • Acoustic measurements • Inventory control with tank tightness • Other forms approved by the Secretary

  25. Section 11 ‐ Closure of ASTs – Permanent Closure • Requires notification • Closure plan submittal (method of closure and proposed sampling • Dismantle the AST or render it incapable of holding fluids • Closure report

  26. Section 12 ‐ Financial Responsibility (FR) – Financial responsibility required for taking corrective action from an AST Release: • Thirty party insurance • Surety or Collateral Bonds • Cash deposits • Collateral securities • Escrow accounts • Performance bonds • Trust funds • Financial test of self insurance • Proof of assets

  27. Phase In Dates • Level 1 – Secondary Containment Nov. 1, 2016 – Venting Dec. 31, 2016 – Corrosion Protection June 30, 2017 – Overfill June 30, 2017 – Leak Detection June 30, 2017 • Level 2 – Secondary Containment Feb. 1, 2017 – Venting June. 30, 2017 – Corrosion Protection Dec. 31, 2017 – Overfill Dec. 31, 2017 – Leak Detection June 30, 2018

  28. Thank You!! Questions????????

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend