AST Rule Summary Mountaineer Gas Company Presentation January 10, - - PowerPoint PPT Presentation

ast rule summary
SMART_READER_LITE
LIVE PREVIEW

AST Rule Summary Mountaineer Gas Company Presentation January 10, - - PowerPoint PPT Presentation

AST Rule Summary Mountaineer Gas Company Presentation January 10, 2017 Ruth Porter, Tanks Program Manager Joe Sizemore, Assistant Chief Inspector www.dep.wv.gov/tanks WV Code Chapter 22, Article 30 AST Act Originally established via


slide-1
SLIDE 1

AST Rule Summary

Ruth Porter, Tanks Program Manager

Joe Sizemore, Assistant Chief Inspector

Mountaineer Gas Company Presentation January 10, 2017

slide-2
SLIDE 2

www.dep.wv.gov/tanks

slide-3
SLIDE 3

WV Code Chapter 22, Article 30

  • “AST Act”
  • Originally established via Senate Bill

373 in the 2014 Legislative Session

  • Revised via Senate Bill 423 in the

2015 Legislative Session

  • Response to the Freedom Industries

Spill

slide-4
SLIDE 4

Risk Based Program

  • Level 1 ASTs

– Located in a zone of critical concern (ZCC), source water protection area (SWPA); or – 50,000 gallons or greater; or – Contains a substance from EPA’s List of List at concentration of 1% or greater

  • Level 2 ASTs

– Located in a zone of peripheral concern (ZPC) and not a Level 1

  • Register and Label ASTs

SJM1

slide-5
SLIDE 5

AST Rules

  • 47 CSR 63 – AST Rule

– Specific tank operation and management requirements

  • 47 CSR 64 – AST Fee Rule

– Annual fees for regulated tanks

  • 47 CSR 65 – Administrative Penalty Rule

– Resolution of enforcement actions and assessment of penalties

slide-6
SLIDE 6

AST Rule

  • Operation & Maintenance

–Registration, construction, installation, upgrades, inspection, maintenance, testing, and closure of tank systems.

  • Twelve (12) Sections
slide-7
SLIDE 7

Section 3‐ Registration

  • It is unlawful to operate an AST after July 1,

2015 unless it is “properly” registered and registration fees are paid.

  • An Owner must register within thirty (30) days

after installation or acquiring an AST, but can’t operate the AST until it is properly registered.

slide-8
SLIDE 8

Section 4‐ Certificate to Operate, Permits/Plans & Siting Requirements

  • Applies only to Level 1 & Level 2 ASTs
  • Certificate to Operate

– Renewed automatically – Annual basis

  • Allows for ASTs to be regulated under existing

permit.

  • Siting requirements for ASTs with flammable or

combustible liquids.

slide-9
SLIDE 9

Section 5‐ Operation and Maintenance

  • Secondary Containment Inspections

– Level 1 every 14 days – Level 2 once a month

  • Monthly AST system visual inspection

– Level 1 & Level 2 ASTs

slide-10
SLIDE 10

Section 5‐ Operation and Maintenance

  • Annual Inspections & Certifications

– Level 1 & Level 2 ASTs – By January 28, 2017 and on or before January 1, 2018 and then on or before January 1 of each year thereafter. – Every 3 years for Level 1 AST ( PE, API or STI certified inspector) – Every 5 years for Level 2 AST ( PE, API or STI certified inspector)

SJM2

slide-11
SLIDE 11

AST Inspection Certification Frequencies

(47 CSR 63‐5.2)

Enter AST Registration Date:

1/10/2017 Level 1 Level 2

PE, API, STI Certification Due*

1/28/2017

PE, API, STI Certification Due*

1/28/2017

Owner Certification Due

1/1/2018

Owner Certification Due

1/1/2018

Owner Certification Due

1/1/2019

Owner Certification Due

1/1/2019

PE, API, STI Certification Due

1/1/2020

Owner Certification Due

1/1/2020

Owner Certification Due

1/1/2021

Owner Certification Due

1/1/2021

Owner Certification Due

1/1/2022

PE, API, STI Certification Due

1/1/2022

PE, API, STI Certification Due

1/1/2023

Owner Certification Due

1/1/2023

Owner Certification Due

1/1/2024

Owner Certification Due

1/1/2024

Owner Certification Due

1/1/2025

Owner Certification Due

1/1/2025

PE, API, STI Certification Due

1/1/2026

Owner Certification Due

1/1/2026

Owner Certification Due

1/1/2027

PE, API, STI Certification Due

1/1/2027

Owner Certification Due

1/1/2028

Owner Certification Due

1/1/2028

PE, API, STI Certification Due

1/1/2029

Owner Certification Due

1/1/2029

slide-12
SLIDE 12

Section 5‐ Operation and Maintenance

  • Internal Inspections (STI SP001 or API 653)

– Not required for ASTs ≤ 30,000 gallons

  • Spill Prevention Response Plan (SPRP)

– Tank owner/operator can certify they have an approved SPCC or GPP – Required by December 9, 2015 – Updated every 5 years or sooner if certain triggers reached

slide-13
SLIDE 13

Section 6‐ Reporting and Recordkeeping

  • Owners/operators must keep records for:

– Financial Responsibility – Inspections – Leak Detection – Corrosion protection – Secondary containment checks – Documentation of repairs – Closures

slide-14
SLIDE 14

Section 6‐ Reporting and Recordkeeping

  • Confirmed, Suspected or Threatened Releases

– Notify WVDEP immediately for Confirmed Release – Notify within 24 hours for Suspected or Threatened Release unless a false alarm

slide-15
SLIDE 15

Section 7‐ Corrective Action

  • Release response requirements

– Notify WVDEP – Contain the release – Perform corrective action

slide-16
SLIDE 16

Section 8‐ AST Design, Construction, and Installation

  • AST must be used for what they were designed for
  • Foundation and support requirements
  • Tightness testing of ASTs at install and/or

reconstruction

  • All new Level 1 tanks installed shall be double walled,

double bottomed, or installed with a Release Prevention Barrier

slide-17
SLIDE 17

Section 9‐ Corrosion and Deterioration Prevention

  • Acceptable corrosion methods are:

– Cathodic protection systems (galvanic or impressed current) – Exterior Coatings – Interior linings and coatings – ASTs constructed of noncorrodible materials – Storage in a manner prevents metal contact with an electrolyte

slide-18
SLIDE 18
  • Cathodic protection system must be designed

by a NACE certified (or equivalent) corrosion expert.

  • Cathodic protection systems must be tested

within 6 months of installation and every 3 years thereafter ‐ NACE certified CP tester.

Section 9‐ Corrosion and Deterioration Prevention

slide-19
SLIDE 19
  • Impressed current systems must have the

rectifier inspected every sixty (60) days.

  • All impressed current systems shall be tested

by a NACE certified CP tester every twelve (12) months as part of a preventative maintenance program to minimize in‐service failure.

Section 9‐ Corrosion and Deterioration Prevention

slide-20
SLIDE 20

Section 9‐ Corrosion and Deterioration Prevention

  • The impressed current source shall not be de‐

energized at any time, including periods when the facility is closed:

– except during power failures or – during service work on the regulated AST or impressed current system).

slide-21
SLIDE 21

Section 9‐ Corrosion and Deterioration Prevention

  • The criteria for determining the effectiveness
  • f cathodic protection (‐850 mV with the CP

current applied).

  • Alternatively, a negative potential of at least

850 millivolts from instant off reading or a 100 mV shift from the instant off position is acceptable for impressed current systems.

slide-22
SLIDE 22

Section 10‐ Release Prevention, Leak Detection, & Secondary Containment

  • Spill and overfill

– Overfill and spill equipment must be properly installed, operated, inspected, tested, and maintained in accordance with the manufacturer’s specifications – For sites receiving deliveries, ASTs must have overfill device or deliveries must be constantly monitored – For sites not receiving deliveries, owner/operators must monitor the AST to ensure that spill and overfills don’t occur

slide-23
SLIDE 23

Section 10‐ Release Prevention, Leak Detection, & Secondary Containment

  • Secondary containment for existing AST

systems needs to hold a released substance for a minimum of seventy‐two (72) hours.

  • Secondary containment for new LEVEL 1 AST

systems must have a permeability less than 1 x 10‐7 cm/sec.

slide-24
SLIDE 24

Section 10‐ Release Prevention, Leak Detection, & Secondary Containment

– Existing Level 1 & Level 2 ASTs must perform leak detection monthly by a method listed below:

  • Visual
  • Automatic tank gauging
  • Statistical inventory reconciliation
  • Interstitial monitoring
  • Soil vapor monitoring within secondary containment
  • Volumetric or mass measurements
  • Acoustic measurements
  • Inventory control with tank tightness
  • Other forms approved by the Secretary
slide-25
SLIDE 25

Section 11‐ Closure of ASTs

– Permanent Closure

  • Requires notification
  • Closure plan submittal (method of closure and

proposed sampling

  • Dismantle the AST or render it incapable of

holding fluids

  • Closure report
slide-26
SLIDE 26

Section 12‐ Financial Responsibility (FR)

– Financial responsibility required for taking corrective action from an AST Release:

  • Thirty party insurance
  • Surety or Collateral Bonds
  • Cash deposits
  • Collateral securities
  • Escrow accounts
  • Performance bonds
  • Trust funds
  • Financial test of self insurance
  • Proof of assets
slide-27
SLIDE 27

Phase In Dates

  • Level 1

– Secondary Containment

  • Nov. 1, 2016

– Venting

  • Dec. 31, 2016

– Corrosion Protection June 30, 2017 – Overfill June 30, 2017 – Leak Detection June 30, 2017

  • Level 2

– Secondary Containment

  • Feb. 1, 2017

– Venting

  • June. 30, 2017

– Corrosion Protection

  • Dec. 31, 2017

– Overfill

  • Dec. 31, 2017

– Leak Detection June 30, 2018

slide-28
SLIDE 28

Thank You!!

Questions????????