AST Rule Summary Mountaineer Gas Company Presentation January 10, - - PowerPoint PPT Presentation
AST Rule Summary Mountaineer Gas Company Presentation January 10, - - PowerPoint PPT Presentation
AST Rule Summary Mountaineer Gas Company Presentation January 10, 2017 Ruth Porter, Tanks Program Manager Joe Sizemore, Assistant Chief Inspector www.dep.wv.gov/tanks WV Code Chapter 22, Article 30 AST Act Originally established via
www.dep.wv.gov/tanks
WV Code Chapter 22, Article 30
- “AST Act”
- Originally established via Senate Bill
373 in the 2014 Legislative Session
- Revised via Senate Bill 423 in the
2015 Legislative Session
- Response to the Freedom Industries
Spill
Risk Based Program
- Level 1 ASTs
– Located in a zone of critical concern (ZCC), source water protection area (SWPA); or – 50,000 gallons or greater; or – Contains a substance from EPA’s List of List at concentration of 1% or greater
- Level 2 ASTs
– Located in a zone of peripheral concern (ZPC) and not a Level 1
- Register and Label ASTs
SJM1
AST Rules
- 47 CSR 63 – AST Rule
– Specific tank operation and management requirements
- 47 CSR 64 – AST Fee Rule
– Annual fees for regulated tanks
- 47 CSR 65 – Administrative Penalty Rule
– Resolution of enforcement actions and assessment of penalties
AST Rule
- Operation & Maintenance
–Registration, construction, installation, upgrades, inspection, maintenance, testing, and closure of tank systems.
- Twelve (12) Sections
Section 3‐ Registration
- It is unlawful to operate an AST after July 1,
2015 unless it is “properly” registered and registration fees are paid.
- An Owner must register within thirty (30) days
after installation or acquiring an AST, but can’t operate the AST until it is properly registered.
Section 4‐ Certificate to Operate, Permits/Plans & Siting Requirements
- Applies only to Level 1 & Level 2 ASTs
- Certificate to Operate
– Renewed automatically – Annual basis
- Allows for ASTs to be regulated under existing
permit.
- Siting requirements for ASTs with flammable or
combustible liquids.
Section 5‐ Operation and Maintenance
- Secondary Containment Inspections
– Level 1 every 14 days – Level 2 once a month
- Monthly AST system visual inspection
– Level 1 & Level 2 ASTs
Section 5‐ Operation and Maintenance
- Annual Inspections & Certifications
– Level 1 & Level 2 ASTs – By January 28, 2017 and on or before January 1, 2018 and then on or before January 1 of each year thereafter. – Every 3 years for Level 1 AST ( PE, API or STI certified inspector) – Every 5 years for Level 2 AST ( PE, API or STI certified inspector)
SJM2
AST Inspection Certification Frequencies
(47 CSR 63‐5.2)
Enter AST Registration Date:
1/10/2017 Level 1 Level 2
PE, API, STI Certification Due*
1/28/2017
PE, API, STI Certification Due*
1/28/2017
Owner Certification Due
1/1/2018
Owner Certification Due
1/1/2018
Owner Certification Due
1/1/2019
Owner Certification Due
1/1/2019
PE, API, STI Certification Due
1/1/2020
Owner Certification Due
1/1/2020
Owner Certification Due
1/1/2021
Owner Certification Due
1/1/2021
Owner Certification Due
1/1/2022
PE, API, STI Certification Due
1/1/2022
PE, API, STI Certification Due
1/1/2023
Owner Certification Due
1/1/2023
Owner Certification Due
1/1/2024
Owner Certification Due
1/1/2024
Owner Certification Due
1/1/2025
Owner Certification Due
1/1/2025
PE, API, STI Certification Due
1/1/2026
Owner Certification Due
1/1/2026
Owner Certification Due
1/1/2027
PE, API, STI Certification Due
1/1/2027
Owner Certification Due
1/1/2028
Owner Certification Due
1/1/2028
PE, API, STI Certification Due
1/1/2029
Owner Certification Due
1/1/2029
Section 5‐ Operation and Maintenance
- Internal Inspections (STI SP001 or API 653)
– Not required for ASTs ≤ 30,000 gallons
- Spill Prevention Response Plan (SPRP)
– Tank owner/operator can certify they have an approved SPCC or GPP – Required by December 9, 2015 – Updated every 5 years or sooner if certain triggers reached
Section 6‐ Reporting and Recordkeeping
- Owners/operators must keep records for:
– Financial Responsibility – Inspections – Leak Detection – Corrosion protection – Secondary containment checks – Documentation of repairs – Closures
Section 6‐ Reporting and Recordkeeping
- Confirmed, Suspected or Threatened Releases
– Notify WVDEP immediately for Confirmed Release – Notify within 24 hours for Suspected or Threatened Release unless a false alarm
Section 7‐ Corrective Action
- Release response requirements
– Notify WVDEP – Contain the release – Perform corrective action
Section 8‐ AST Design, Construction, and Installation
- AST must be used for what they were designed for
- Foundation and support requirements
- Tightness testing of ASTs at install and/or
reconstruction
- All new Level 1 tanks installed shall be double walled,
double bottomed, or installed with a Release Prevention Barrier
Section 9‐ Corrosion and Deterioration Prevention
- Acceptable corrosion methods are:
– Cathodic protection systems (galvanic or impressed current) – Exterior Coatings – Interior linings and coatings – ASTs constructed of noncorrodible materials – Storage in a manner prevents metal contact with an electrolyte
- Cathodic protection system must be designed
by a NACE certified (or equivalent) corrosion expert.
- Cathodic protection systems must be tested
within 6 months of installation and every 3 years thereafter ‐ NACE certified CP tester.
Section 9‐ Corrosion and Deterioration Prevention
- Impressed current systems must have the
rectifier inspected every sixty (60) days.
- All impressed current systems shall be tested
by a NACE certified CP tester every twelve (12) months as part of a preventative maintenance program to minimize in‐service failure.
Section 9‐ Corrosion and Deterioration Prevention
Section 9‐ Corrosion and Deterioration Prevention
- The impressed current source shall not be de‐
energized at any time, including periods when the facility is closed:
– except during power failures or – during service work on the regulated AST or impressed current system).
Section 9‐ Corrosion and Deterioration Prevention
- The criteria for determining the effectiveness
- f cathodic protection (‐850 mV with the CP
current applied).
- Alternatively, a negative potential of at least
850 millivolts from instant off reading or a 100 mV shift from the instant off position is acceptable for impressed current systems.
Section 10‐ Release Prevention, Leak Detection, & Secondary Containment
- Spill and overfill
– Overfill and spill equipment must be properly installed, operated, inspected, tested, and maintained in accordance with the manufacturer’s specifications – For sites receiving deliveries, ASTs must have overfill device or deliveries must be constantly monitored – For sites not receiving deliveries, owner/operators must monitor the AST to ensure that spill and overfills don’t occur
Section 10‐ Release Prevention, Leak Detection, & Secondary Containment
- Secondary containment for existing AST
systems needs to hold a released substance for a minimum of seventy‐two (72) hours.
- Secondary containment for new LEVEL 1 AST
systems must have a permeability less than 1 x 10‐7 cm/sec.
Section 10‐ Release Prevention, Leak Detection, & Secondary Containment
– Existing Level 1 & Level 2 ASTs must perform leak detection monthly by a method listed below:
- Visual
- Automatic tank gauging
- Statistical inventory reconciliation
- Interstitial monitoring
- Soil vapor monitoring within secondary containment
- Volumetric or mass measurements
- Acoustic measurements
- Inventory control with tank tightness
- Other forms approved by the Secretary
Section 11‐ Closure of ASTs
– Permanent Closure
- Requires notification
- Closure plan submittal (method of closure and
proposed sampling
- Dismantle the AST or render it incapable of
holding fluids
- Closure report
Section 12‐ Financial Responsibility (FR)
– Financial responsibility required for taking corrective action from an AST Release:
- Thirty party insurance
- Surety or Collateral Bonds
- Cash deposits
- Collateral securities
- Escrow accounts
- Performance bonds
- Trust funds
- Financial test of self insurance
- Proof of assets
Phase In Dates
- Level 1
– Secondary Containment
- Nov. 1, 2016
– Venting
- Dec. 31, 2016
– Corrosion Protection June 30, 2017 – Overfill June 30, 2017 – Leak Detection June 30, 2017
- Level 2
– Secondary Containment
- Feb. 1, 2017
– Venting
- June. 30, 2017
– Corrosion Protection
- Dec. 31, 2017
– Overfill
- Dec. 31, 2017
– Leak Detection June 30, 2018