arrowhead forward
play

ARROWHEAD FORWARD New Elementary School at Arrowhead April 21st, - PowerPoint PPT Presentation

ARROWHEAD FORWARD New Elementary School at Arrowhead April 21st, 2020 Board Update TONIGHTS AGENDA PROPOSED ARROWHEAD 1. Land Development Recap 2. Review of site improvements 3. Review of building improvements 4. Project Schedule Land


  1. ARROWHEAD FORWARD New Elementary School at Arrowhead April 21st, 2020 Board Update

  2. TONIGHT’S AGENDA PROPOSED ARROWHEAD 1. Land Development Recap 2. Review of site improvements 3. Review of building improvements 4. Project Schedule Land Development • Schedule Act 34 Hearing Schedule • Construction Schedule • 5. Budget update 6. Next steps 2

  3. LAND DEVELOPMENT RECAP 1. Kick-off Township Meeting (December 20, 2019) 2. Met with Fire Marshal (March 3, 2020) 3. Prelim/Final Plan Submission Submitted (March 13, 2020) 4. NPDES Submitted (March 30, 2020) 5. Planning Commission Meeting (April 22, 2020) 6. Prelim/Final Plan Submission #2 (May 15, 2020) 7. Planning Commission Meeting ( July 22, 2020) 8. Anticipated NPDES Approval (September 2020) 3

  4. EXISTING SITE & SETBACKS 50’ SETBACK 4

  5. EXISTING SITE & SETBACKS NEIGHBORS WATER VAULT TREE LINE NEIGHBORS 5

  6. EXISTING SITE & SETBACKS REMOVE EXISTING MODULARS 6

  7. PROPOSED SITE PLAN FULL SIZE FIELD MAIN ENTRY * SERVICE ACCESS * PLAY FIRE LANE * LEARNING EQUIP. 7

  8. PROPOSED ARROWHEAD ELEMENTARY K-4 ELEMENTARY 5 CLASSROOMS PER GRADE TOTAL CAPACITY: 625 FIRST FLOOR: 57,987 SF SECOND FLOOR: 27,309 SF TOTAL: 85,296 SF ACADEMIC: 15 CLASSROOMS, 900 SF, NO TOILETS 10 CLASSROOMS, 835 SF, SINGLE-USE TOILET IN CLASSROOM 8 SPECIAL EDUCATION, 660-900 SF COLLABORATION: LIBRARY, 2000 SF + STEM 1200 SF 5 SMALL GROUP INSTRUCTION ROOMS, 350 SF 2 INNOVATION SPACES, 850 SF COMMUNITY: CAFETERIA, 2400 SF GYM, 5800 SF STAGE, 950 SF 8

  9. ARROWHEAD ELEMENTARY

  10. PROPOSED ARROWHEAD ELEMENTARY FIRST FLOOR 57,987 SF SECOND FLOOR 27,309 SF STAGE GYM TOTAL 85,296 SF ADMIN. KITCHEN COMMUNITY CAFETERIA LOBBY NURSE LEARNING INSTRUM. MUSIC FIRE FACULTY SUPPORT ROOM ROOM SEPERATION OT/PT 1 st GRADE EMOTIONAL SUPPORT ACADEMIC LIBRARY KINDERGARTEN STEM SGI SGI INNOVATION OFFICE SPACE SPEECH ELL 1 st GRADE KINDERGARTEN FIRST FLOOR PLAN 10

  11. PROPOSED ARROWHEAD ELEMENTARY FIRST FLOOR 57,987 SF SECOND FLOOR 27,309 SF TOTAL 85,296 SF LOBBY 2 nd GRADE 2 nd GRADE 4 th GRADE LIBRARY ACADEMIC (BELOW) ART 3 rd GRADE SGI SGI SGI INNOVATION TV SPACE GIFTED READ. 4 th GRADE 3 rd GRADE SECOND FLOOR PLAN 11

  12. PARKING & PLAY

  13. FRONT ENTRY 13

  14. FRONT ANIMATION 14

  15. ADMINISTRATION + LOBBY SECURE VESTIBULE RECEPTION WORK ROOM CONFERENCE PRINCIPAL SCHOOL PSYCOLOGIST NURSE’S SUITE SCHOOL COUNSELOR 15

  16. 1 RECEPTION 16

  17. RECEPTION ANIMATION 17

  18. MAIN LOBBY 18

  19. GYMNASIUM OFFICE GYM OFFICE STORAGE 1,200 SF INCREASE RETRACTABLE BLEACHERS ACCOMODATING LARGER 42’ LONG COURT + BLEACHERS 80 SEATS 50X74 COURT 8’ RUN OFF 4’ SIDELINES STAGE ACCESS RAMP SOUND ROOM 19

  20. CAFETERIA KITCHEN CONSULTANT ALL EXISTING NEEDS SINGLE SERVE LINE + ACCOMODATIONS FOR THE POPULATION INCREASE LOADING ZONE RECEIVING/RECEIVING OFFICE SINGLE-SERVICE LINE 192 SEATS 16 TABLES 192 SEATING CAPACITY REUSE OF EXISTING TABLES 20

  21. LOBBY ANIMATION 21

  22. LIBRARY + STEM STEM WORKSPACE OFFICE LIBRARY +1000 LINEAR INCHES OF SHELVING CLASSROOM SPACE COPY ROOM 22

  23. 1 LIBRARY ENTRY 23

  24. LIBRARY ANIMATION 24

  25. LIBRARY 25

  26. LIBRARY 26

  27. STEM CLASSROOM 27

  28. STEM ANIMATION 28

  29. SMALL GROUP INSTRUCTION + INNOVATION SPACE SGI SGI TEACHING WALL INNOVATION SPACE (25-50 STUDENTS) FLEXIBLE FURNITURE 29

  30. SMALL GROUP INSTRUCTION TEACHING WALL TEACHING WALL BASE CABINETS (LOCKABLE) TEACHING WALL BASE CABINETS (LOCKABLE) 30

  31. INNOVATION COMMONS 31

  32. 5 9 1 INNOVATION COMMONS 32

  33. CLASSROOM ENTRY TACK SURFACE FOR CLASSROOM IDENTITY GROUPED ENTRY FOR SUPERVISION LOCKERS FOR EASY ACCESS BUILT-IN BENCH FOR SEATING 33

  34. TYPICAL CLASSROOM (K-1) TEACHING WALLS 34

  35. TYPICAL CLASSROOM (K-1) CASEWORK - BASEBID 35

  36. TYPICAL CLASSROOM (K-1) CASEWORK – ALTERNATE 1 36

  37. TYPICAL CLASSROOM (K-1) CASEWORK – ALTERNATE 2 37

  38. TYPICAL CLASSROOM (2-4) TEACHING WALLS 38

  39. TYPICAL CLASSROOM (2-4) CASEWORK – BASE BID 39

  40. TYPICAL CLASSROOM (2-4) CASEWORK – ALTERNATE 1 40

  41. TYPICAL CLASSROOM (2-4) CASEWORK – ALTERNATE 2 41

  42. EXPANDED CLASSROOM 660 CLASSROOM EXPANSION FOR 900 SF CLASSROOM 42

  43. SECOND FLOOR ANIMATION 43

  44. ART + COLLABORATION ART CLASSROOM TV STUDIO LIBRARY BELOW SGI COPY ROOM 44

  45. SMALL GROUP INSTRUCTION 45

  46. BUDGET SUMMARY 46

  47. NEW SCHOOL OPTION – CAPACITY 625 Proposed New Construction (84,000sf @ $270/sf) $22,680,000 Site work required for new construction (18%) $4,082,400 Demo of existing school building (52,534sf @ $8/sf) $420,272 Design/Bidding Contingency - 3% $815,480 TOTAL CONSTRUCTION COST $27,998,152 Construction Contingency - 5% $1,399,908 $3,639,760 Soft Costs - 13% (Fees, Permits, etc.) $750,000 Budget: FF&E Allowance ($1200/student) TOTAL PROJECT COST $33,787,820 January 2020 (Schematic Design Estimate) 47

  48. NEW SCHOOL OPTION – CAPACITY 625 Proposed New Construction (84,000sf @ $270/sf) $22,680,000 Site work required for new construction (18%) $4,082,400 Demo of existing school building (52,534sf @ $8/sf) $420,272 Design/Bidding Contingency - 3% $815,480 TOTAL CONSTRUCTION COST $27,998,152 Changes that reflect cost: Construction Contingency - 5% $1,399,908 $3,639,760 Soft Costs - 13% (Fees, Permits, etc.) • Removed basement mechanical space (eliminated rock excavation) -200sf $750,000 Budget: FF&E Allowance ($1200/student) • Continued to reduce overall size of the school for most cost effective plan -184sf TOTAL PROJECT COST $33,787,820 • Increased the size of the gym to accommodate more seating (bleachers) +1200sf • Expanded one 660sf classroom on each floor to full 900sf for learning support +480sf 1680sf increase of educational space Only 1296sf building increase January 2020 (Schematic Design Estimate) 48

  49. NEW SCHOOL OPTION – CAPACITY 625 Proposed New Construction (85,296sf* @ $270/sf) $23,029,920 Site work required for new construction (18%) $4,145,386 Demo of existing school building (52,534sf @ $8/sf) $420,272 Design/Bidding Contingency - 3% $827,867 TOTAL CONSTRUCTION COST $28,423,445 Construction Contingency - 5% $1,421,172 $3,695,048 Soft Costs - 13% (Fees, Permits, etc.) $750,000 Budget: FF&E Allowance ($1200/student) TOTAL PROJECT COST $34,289,665** *Includes 1680sf net educational space increase with only 1296sf total building increase **Original estimate presented to board 8/20/2019 was $34,347,783 March 2020 (50% Design Development Estimate) 49

  50. • DESIGN DEVELOPMENT PRESENTATION TO SCHOOL BOARD MAY 19 TH WILL INCLUDE THIRD PARTY COST ESTIMATE • ACT 34 HEARING - BOARD APPROVAL TO ADVERTISE 7/21 - ACT 34 HEARING 9/8 - 30 DAY COMMENT PERIOD ENDS = 10/8 • BID PERIOD 10/13 – 11/10 - BOARD REVIEW BIDS 11/17 - BOARD VOTE TO AWARD BIDS 11/24 50

  51. Timeline….. • BOARD PRESENTATION MAY - APPROVAL TO COMPLETE CONSTRUCTION DOCUMENTATION • BOARD REVIEW ACT 34 IN JULY - TO ADVERTISE HEARING • BOARD VOTES TO AWARD CONSTRUCTION BIDS NOV. ‘20 • START CONSTRUCTION DEC. ‘20 • OPEN SCHOOL AUGUST 2022 51

  52. DISCUSSION 52

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend