arlington career center contract award for columbia pike
play

Arlington Career Center Contract Award for Columbia Pike Branch - PowerPoint PPT Presentation

Arlington Career Center Contract Award for Columbia Pike Branch Library Renovation Jeffrey Chambers, Director, Design and Construction School Board Information Item June 25, 2020 Summary On May 7, 2020, the School Board approved a


  1. Arlington Career Center Contract Award for Columbia Pike Branch Library Renovation Jeffrey Chambers, Director, Design and Construction School Board Information Item June 25, 2020

  2. Summary • On May 7, 2020, the School Board approved a construction contract for summer 2020 renovations at the Arlington Career Center and construction is underway • Originally staff intended to complete the consolidation of the Columbia Pike Branch Library on the first floor in order to provide shared APS/County classrooms on the second floor concurrent with the summer 2020 renovations. That work was delayed due to the COVID-19 crisis • After evaluating the current state of the construction market, staff consider it appropriate to proceed with the library conversion construction via a change order to the current construction contract. For staff to proceed, School Board action is required to: • Approve an individual change order that exceeds $100,000; • Establish the revised construction contract sum as the basis to which evaluate future change orders; and • Approve a revised project budget 2

  3. Arlington Tech Expansion • The School Board’s adopted FY 2019-28 Capital Improvement Plan (CIP) includes: • Arlington Tech Expansion for 250 high school seats to be completed by start of school September 2021 for a maximum total project cost of $18,750,000, bringing the total capacity of Arlington Tech to 600 seats • In summer 2017, 2018, and 2019 staff completed projects to accommodate the growing enrollment of Arlington Tech • Construction has started to prepare for Arlington Tech’s enrollment for SY 2020-21, including: • Renovating a portion of the existing school to add a new science lab and right-size several existing classrooms; and • Installing relocatable classrooms on the existing parking lot • A change order to the current construction contract is proposed to consolidate the Columbia Pike Branch Library on the first floor in order to provide shared APS/County classrooms on the second floor 3

  4. Project Budget (Exhibit A) • Of the $18.75 million of funding approved in the FY 2019-28 CIP, all but $5.00 million in bonds have been sold. Of the $13.75 million in bonds already sold, approximately $7.60 million remains to support the project • Proposed construction cost for the library conversion is nearly $0.70 million below the estimated cost in the approved project budget. Staff recommend using the savings to increase project contingencies . At project completion any unspent funds will be available to support future work related to the expansion of Arlington Tech. Current Proposed Budget 2 Budget Package 1 Construction - Summer 2020 2 $ 891,747 $ 891,747 Proposed Construction - Library Conversion $ 3,800,000 $ 3,116,366 Construction Contingency $ 563,000 $ 995,454 Subtotal - Construction (Hard Costs) $ 5,254,747 $ 5,003,567 Notes: Owner (Soft) Costs 1 $ 2,245,253 $ 2,496,433 1. Owner costs include design, project management, and other professional services fees, utility/permitting fees, furniture, and equipment, and additional contingencies. Total Project Costs $ 7,500,000 $ 7,500,000 2. Approved by the School Board on May 7, 2020. 4

  5. Recent Milestones and Next Steps  June 1, 2020 – Construction started on Career Center second floor renovations  June 13, 2020 – County Board action to approve Use Permit amendment increasing capacity of the Career Center  June 22, 2020 – Arlington County approval of building permit for library conversion construction • July 16, 2020 – School Board action on library conversion construction award • August 3, 2020 – begin library conversion on-site construction • August 21, 2020 – complete Career Center second floor renovations • November 2020 – complete library conversion construction Career Center Second Floor Renovations 5

  6. Recommendations The following recommendations are within the current funding approved by the School Board so no change to funding is necessary: • Approve an individual change order for the library conversion in the amount of $3,116,366 to Gilbane Building Company; • Establish the revised construction contract sum of $4,008,113 as the basis of which to evaluate future change orders; and • Approve the proposed project budget as shown in Exhibit A and authorize staff to encumber funds as necessary to meet the project schedule. 6

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend