all souls unitarian universalist church gastingerwalker
play

ALL SOULS UNITARIAN UNIVERSALIST CHURCH GastingerWalker Presentation - PowerPoint PPT Presentation

ALL SOULS UNITARIAN UNIVERSALIST CHURCH GastingerWalker Presentation Excerpts with Additional Explanations Design Concepts 24 July 2016 ALL SOULS PROJECT BUDGET Budget A Budget B Only Capital Capital Campaign + Campaign Bank Loan +


  1. ALL SOULS UNITARIAN UNIVERSALIST CHURCH GastingerWalker Presentation Excerpts with Additional Explanations Design Concepts 24 July 2016

  2. ALL SOULS PROJECT BUDGET Budget A Budget B Only Capital Capital Campaign + Campaign Bank Loan + Funds Endowment Capital campaign pledges $1,200,000 $1,200,000 Capital campaign and renovation $100,000 $100,000 expenses through July Remaining pledges $1,100,000 $1,100,000 $240,000 Additional bank loan $0 Grant from endowment $0 $260,000 Construction project cost $1,100,000 $1,600,000

  3. TYPICAL PROJECT BUDGET Construction Cost: 75 - 80% Owner Expenses: 1 - 2% Soft Costs: 2 - 3% Design Fees: 7 - 8% Contingencies: 12 - 15%

  4. BUDGET A: $1,100,000 Funds Raised

  5. BUDGET B: $1,600,000 Funds Raised + Possible Financing

  6. PROJECT GOALS 1. Improve Functionality 2. Promote Interaction 3. Remove Barriers 4. Control Cost 5. Generate Inspiration

  7. PROJECT PRIORITIES 1. Roofing and Exterior Repairs BUDGET A, $1,100,000 OPTION 1 2. Mechanical Systems Upgrade 3. Repairs and Handrails at Existing Stairs 4. Elevator 5. Repair and Handrail at Warwick Exterior Stair 6. Renovation or Replacement of Administrative Wing 7. Parking Lot Renovation 8. Renovations in Gathering Hall 9. Renovations in Conover 10. Renovations in Bragg Auditorium

  8. PROJECT PRIORITIES 1. Roofing and Exterior Repairs OPTION 2,3 4 BUDGET B, 2. Mechanical Systems Upgrade $1,600,000 3. Repairs and Handrails at Existing Stairs 4. Elevator 5. Repair and Handrail at Warwick Exterior Stair 6. Renovation or Replacement of Administrative Wing 7. Parking Lot Renovation 8. Renovations in Gathering Hall 9. Renovations in Conover 10. Renovations in Bragg Auditorium

  9. PROGRAM AREA PRIORITIES TARGET AREA: 1,800 sf

  10. PROJECT PLAN OPTIONS Repairs (Roof, Extend Music Room HVAC) Elevator Admin Wing Lobby /Chapel Option 1 Yes Yes No work No No Renovate Option 2 Yes Yes No No existing New wing on Option 3 Yes Yes Yes No west New wing on Option 4 Yes Yes Yes Yes south

  11. PROJECT PLAN OPTIONS and CONSTRUCTION BUDGET BUDGET A BUDGET B (Only Pledges) (Pledges + Financing) Option 1 Option 2 Option 3 Option 4 Construction Cost $ 829,520 $1,221,384 $1,313,077 $1,313,077 Other Project Costs $220,000 $365,000 $365,000 $365,000 Total Project Cost $1,049,520 $1,586,384 $1,678,077 $1,678,077 Funded by $1,100,000 $1,100,000 $1,100,000 $1,100,000 Remaining Pledges To be Financed - $0 $486,384 $578,077 $578,077 Bank/Endowment

  12. OPTION 1: REPAIR + ELEVATOR

  13. OPTION 1: REPAIR + ELEVATOR COST = $1,049,520

  14. OPTION 1: REPAIR + ELEVATOR

  15. OPTION 1: REPAIR + ELEVATOR PROS: • Catch up on deferred maintenance • Elevator for increased functionality and accessibility • Improved safety and code compliance • Within budget with current funds CONS: • Does not address other functional needs

  16. OPTION 2: REPAIR + ELEVATOR + RENOVATE EXISTING ADMINISTRATION WING

  17. OPTION 2: REPAIR + RENOVATION EXISTING COST = $1,586,384

  18. OPTION 2: REPAIR + RENOVATION

  19. OPTION 2: REPAIR + RENOVATION PROS: • Under budget • Stabilizes structure CONS: • Little improvement to administration functionality • Does not address goal to improve entry and access • Does not change the exterior appearance (pro?)

  20. OPTION 3: REPAIR + ELEVATOR + NEW WEST ADDITION

  21. OPTION 3: REPAIR + NEW WEST ADDITION COST = $1,678,077

  22. OPTION 3: REPAIR + NEW WEST ADDITION

  23. OPTION 3: REPAIR + NEW WEST ADDITION PROS: • Improves administration functionality • Improves entry and access • Creates a more welcoming exterior CONS: • Over budget • Disruption to operations during construction • No Music Room/Small Chapel

  24. OPTION 4: REPAIR + ELEVATOR + NEW SOUTH ADDITION

  25. OPTION 4: REPAIR + NEW SOUTH ADDITION COST = $1,678,077

  26. OPTION 4: REPAIR + NEW SOUTH ADDITION

  27. OPTION 4: REPAIR + NEW SOUTH ADDITION PROS: • Improves administration functionality • Improves entry and access • Creates a more welcoming exterior • Easier transition for administrative staff during construction • Has Music Room/Small Chapel CONS: • Over budget • Disruption to operations during construction

  28. EXISTING

  29. OPTION 4: NEW SOUTH ADDITION – PHASE 1

  30. OPTION 4: NEW SOUTH ADDITION – PHASE 2

  31. OPTION 4: NEW SOUTH ADDITION – PHASE 3

  32. OPTION 4: NEW SOUTH ADDITION – PHASE 4

  33. OPTION 4: NEW SOUTH ADDITION - PROPOSED

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.