Aggregate Pier Design & Construction Wentworth Institute of - - PowerPoint PPT Presentation

aggregate pier design construction
SMART_READER_LITE
LIVE PREVIEW

Aggregate Pier Design & Construction Wentworth Institute of - - PowerPoint PPT Presentation

haywardbaker.com Aggregate Pier Design & Construction Wentworth Institute of Technology | Beatty Hall | Boston, MA Kevin Dawson, PE, Vice President, New England Area Manager Presentation Outline What Wrap Up Why How When Design


slide-1
SLIDE 1

haywardbaker.com

Aggregate Pier Design & Construction

Wentworth Institute of Technology | Beatty Hall | Boston, MA

Kevin Dawson, PE, Vice President, New England Area Manager

slide-2
SLIDE 2 90

Presentation Outline

What Why When How

  • Design
  • Installation

Wrap Up

slide-3
SLIDE 3 91

What

slide-4
SLIDE 4 92

Vibro Piers = Aggregate Piers

  • Also known by names such as GeoPier, Rammed

Aggregate Pier, Short Aggregate Pier, Compacted Aggregate Piers, Stone Column and others

  • Piers or columns of dense aggregate installed as

foundation elements to support light to medium loads

  • Often referred to as an intermediate foundation

system, i.e. not shallow but also not deep

  • Usually about 24 to 42 inches in diameter and

about 10 to 30 feet deep

slide-5
SLIDE 5 93
slide-6
SLIDE 6 94

Aggregate Piers: How they work

  • Aggregate piers form a composite

system with the surrounding soil

  • When confined laterally, the

aggregate pier is much stronger and stiffer than the surrounding soil

  • Higher modulus columns attract

load and dissipate it gradually with depth

slide-7
SLIDE 7 95

This Not This

slide-8
SLIDE 8 96

Why

slide-9
SLIDE 9 97

reduce total & differential settlement Increase allowable bearing capacity

slide-10
SLIDE 10 98

When

slide-11
SLIDE 11 99

Selection of Ground Improvement Techniques

Soil Type Governs the Ground Improvement Technique

Mine Spoils Loose Sand Undocumented Fill Low Strength Cohesive Soils

slide-12
SLIDE 12 100

Commercial & Industrial Historic Land Use

slide-13
SLIDE 13 101

Filled Land & Former Industrial & Commercial Land Use

slide-14
SLIDE 14 102

Private Industrial Site Redevelopment

slide-15
SLIDE 15 103

Public Redevelopment – Filled Industrial Land

slide-16
SLIDE 16 104

When Summary

  • Undocumented fill or loose soil less than 30’ thick
  • Appropriate loads (deep foundations or alternate ground

improvement technique not required)

  • Less expensive alternate ground improvement techniques not

viable

  • Cost/schedule impact of excavation and replacement not viable
slide-17
SLIDE 17 105

How; Design

slide-18
SLIDE 18 106

Aggregate Pier Design Methodology Design based on spring analogy:

– Rigid footing: aggregate pier deflection equals matrix soil deflection – Stiff spring (aggregate pier) takes more load than the soft spring (matrix soil)

slide-19
SLIDE 19 107

www.HaywardBaker.com

slide-20
SLIDE 20 108

Total Settlement = Settlement from the Improved Zone + Settlement from the Unimproved Zone

IMPROVED ZONE UNIMPROVED ZONE

slide-21
SLIDE 21 109

Pier Testing: Modulus Verification Test

Testing done either with a load frame and anchors or utilizing the vibratory rig as a counterweight

slide-22
SLIDE 22 110

How; Installation

slide-23
SLIDE 23 111
slide-24
SLIDE 24 112
slide-25
SLIDE 25 113
slide-26
SLIDE 26 114

Wrap Up

  • Cost effective intermediate foundation solution

for fill & loose native soil sites

  • Know the limits of the system
  • Alternate ground improvement systems or deep

foundations may be best match for thick soft soil deposits or if improvement depth > 30’

  • Market is extending the use of aggregate piers
  • Understand the risk/reward relationship