aggregate pier design construction
play

Aggregate Pier Design & Construction Wentworth Institute of - PowerPoint PPT Presentation

haywardbaker.com Aggregate Pier Design & Construction Wentworth Institute of Technology | Beatty Hall | Boston, MA Kevin Dawson, PE, Vice President, New England Area Manager Presentation Outline What Wrap Up Why How When Design


  1. haywardbaker.com Aggregate Pier Design & Construction Wentworth Institute of Technology | Beatty Hall | Boston, MA Kevin Dawson, PE, Vice President, New England Area Manager

  2. Presentation Outline What Wrap Up Why How When •Design •Installation 90

  3. What 91

  4. Vibro Piers = Aggregate Piers • Also known by names such as GeoPier, Rammed Aggregate Pier, Short Aggregate Pier, Compacted Aggregate Piers, Stone Column and others • Piers or columns of dense aggregate installed as foundation elements to support light to medium loads • Often referred to as an intermediate foundation system, i.e. not shallow but also not deep • Usually about 24 to 42 inches in diameter and about 10 to 30 feet deep 92

  5. 93

  6. Aggregate Piers: How they work • Aggregate piers form a composite system with the surrounding soil • When confined laterally, the aggregate pier is much stronger and stiffer than the surrounding soil • Higher modulus columns attract load and dissipate it gradually with depth 94

  7. This Not This 95

  8. Why 96

  9. reduce total & differential settlement Increase allowable bearing capacity 97

  10. When 98

  11. Selection of Ground Improvement Techniques Soil Type Governs the Ground Improvement Technique Mine Spoils Undocumented Fill Low Strength Cohesive Soils Loose Sand 99

  12. Commercial & Industrial Historic Land Use 100

  13. Filled Land & Former Industrial & Commercial Land Use 101

  14. Private Industrial Site Redevelopment 102

  15. Public Redevelopment – Filled Industrial Land 103

  16. When Summary • Undocumented fill or loose soil less than 30’ thick • Appropriate loads (deep foundations or alternate ground improvement technique not required) • Less expensive alternate ground improvement techniques not viable • Cost/schedule impact of excavation and replacement not viable 104

  17. How; Design 105

  18. Aggregate Pier Design Methodology Design based on spring analogy: – Rigid footing: aggregate pier deflection equals matrix soil deflection – Stiff spring (aggregate pier) takes more load than the soft spring (matrix soil) 106

  19. 107 www.HaywardBaker.com

  20. Total Settlement = Settlement from the Improved Zone + Settlement from the Unimproved Zone IMPROVED ZONE UNIMPROVED ZONE 108

  21. Pier Testing: Modulus Verification Test Testing done either with a load frame and anchors or utilizing the vibratory rig as a counterweight 109

  22. How; Installation 110

  23. 111

  24. 112

  25. 113

  26. Wrap Up • Cost effective intermediate foundation solution for fill & loose native soil sites • Know the limits of the system • Alternate ground improvement systems or deep foundations may be best match for thick soft soil deposits or if improvement depth > 30’ • Market is extending the use of aggregate piers • Understand the risk/reward relationship 114

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend