haywardbaker.com
Aggregate Pier Design & Construction
Wentworth Institute of Technology | Beatty Hall | Boston, MA
Kevin Dawson, PE, Vice President, New England Area Manager
Aggregate Pier Design & Construction Wentworth Institute of - - PowerPoint PPT Presentation
haywardbaker.com Aggregate Pier Design & Construction Wentworth Institute of Technology | Beatty Hall | Boston, MA Kevin Dawson, PE, Vice President, New England Area Manager Presentation Outline What Wrap Up Why How When Design
haywardbaker.com
Aggregate Pier Design & Construction
Wentworth Institute of Technology | Beatty Hall | Boston, MA
Kevin Dawson, PE, Vice President, New England Area Manager
Presentation Outline
What Why When How
Wrap Up
Vibro Piers = Aggregate Piers
Aggregate Pier, Short Aggregate Pier, Compacted Aggregate Piers, Stone Column and others
foundation elements to support light to medium loads
system, i.e. not shallow but also not deep
about 10 to 30 feet deep
Aggregate Piers: How they work
system with the surrounding soil
aggregate pier is much stronger and stiffer than the surrounding soil
load and dissipate it gradually with depth
This Not This
reduce total & differential settlement Increase allowable bearing capacity
Selection of Ground Improvement Techniques
Soil Type Governs the Ground Improvement Technique
Mine Spoils Loose Sand Undocumented Fill Low Strength Cohesive Soils
Commercial & Industrial Historic Land Use
Filled Land & Former Industrial & Commercial Land Use
Private Industrial Site Redevelopment
Public Redevelopment – Filled Industrial Land
When Summary
improvement technique not required)
viable
Aggregate Pier Design Methodology Design based on spring analogy:
– Rigid footing: aggregate pier deflection equals matrix soil deflection – Stiff spring (aggregate pier) takes more load than the soft spring (matrix soil)
www.HaywardBaker.com
Total Settlement = Settlement from the Improved Zone + Settlement from the Unimproved Zone
IMPROVED ZONE UNIMPROVED ZONE
Pier Testing: Modulus Verification Test
Testing done either with a load frame and anchors or utilizing the vibratory rig as a counterweight
Wrap Up
for fill & loose native soil sites
foundations may be best match for thick soft soil deposits or if improvement depth > 30’