agata week legnaro
play

Agata Week Legnaro 12 th 15 th November 2007 Mechanical Update - PowerPoint PPT Presentation

Agata Week Legnaro 12 th 15 th November 2007 Mechanical Update John Strachan 1 Contents of talk Main Topics. Flanges Single Flange Flange Array Tooling requirements Detector Measurements Adjustment Mechanism Transportation frame


  1. Agata Week Legnaro 12 th – 15 th November 2007 Mechanical Update John Strachan 1

  2. Contents of talk Main Topics. Flanges Single Flange Flange Array Tooling requirements Detector Measurements Adjustment Mechanism Transportation frame Main Support Structure Liquid Nitrogen System Future Involvement 2

  3. Prototype Measurement Measurement Aim. To assess if the production method proposed would produce flanges accurately enough to allow for the production of a 15 flange 1 π ball arrangement. Single Flange Prototype made at Legnaro, and measured with a CMM at Daresbury. 3

  4. Measurement Results θ 0.0521°error = 0.25mm 0.0214°error = 0.25mm Ω 0.0313°error = 0.15mm 670 0.0128° error = 0.15mm 0.0209°error = 0.1mm 0.0086°error = 0.1mm 0.0104°error = 0.05mm 0.0043°error = 0.05mm Measured deviation: Measured deviation: -0.004,+0.002,+0.007,+0.008,+0.013 -0.011,+0.0001,+0.0002,+0.0003,+0.0007 Conclusion. The prototype flange machined by LNL was well machined, Congratulations are deserved, care should be taken to maintain the accuracies achieved. 4

  5. Single Flange Manufacture Images of single flanges being manufactured 5

  6. Flange Array Measurement Measurement Aim. To assess if the flanges could be assembled accurately enough to allow for the production of a 15 flange 1 π ball arrangement. 6

  7. Flange Array Measurement Results Flange 3 Flange 2 Flange 5 Flange 4 Flange 1 Conclusion. Tooling will be required to improve positioning of flanges. 7

  8. Flange Array Tooling Requirements 3 1 2 4 5 6 8

  9. Flange Array Tooling Requirements 8 9 7 11 12 10 9

  10. Flange Array Tooling Requirements 15 13 14 16 17 18 10

  11. Flange Array Tooling Requirements 19 20 21 Tooling pieces order 22 placed. Delivery expected: Early December 23 11

  12. Detector Measurements Romer Arm Measurement Aim. Detector end cap To assess if the production End cap method proposed would sealing plate produce detector assemblies accurately Support tube enough to allow for the production of a 15 flange Mounting 1 π ball arrangement. flange Adapter plates Location spigots M10 studs 12

  13. Overlay of Detector Measurements This images show the process of relating the measured points to the CAD geometry. 13

  14. Results of Detector Measurements Level adjustment required Lateral adjustment required Conclusion Adjustment will be required for the first detectors 14

  15. Vacuum deformation of Detector Measurements Measured by CMM. FEA analysis. Using DTIs. 15

  16. 16 Detector Adjustment Adjustment for Alignment detector gauge

  17. 17 Detector Adjustment attached to main 1 st Adjustment Guide rods (as support rods Detector flanges) Plate

  18. 18 Detector Adjustment 2 nd Adjustment Locking screws Yaw adjusters X and Y adjusters Plate

  19. Detector Adjustment 3 rd Adjustment Plate Z, pitch and roll adjusters Locking screws Detector support rods secured to this flange 19

  20. 20 Alignment Gauge Spaced 1mm clear 3 precision plates of detector

  21. Detector Adjustment Progress Drawings of detector adjustment system are being checked prior to quotation and manufacture. Drawings of alignment gauge are in Progress. Expect all drawings to be complete early December. Plan to have a complete assembly mid to late January 2008. 21

  22. Transportation frame progress Drawings of transportation frame to be completed by end of December Plan to have a complete assembly mid to late February 2008. 22

  23. Support Structure progress Drawings of support structure have been completed and issued to Legnaro for manufacture. 23

  24. Liquid Nitrogen support progress Drawings of Liquid Nitrogen support structure have been completed and issued to Legnaro for manufacture. 24

  25. Future plans The UK is currently bidding to provide the mechanical design for installation of AGATA at both GANIL and GSI Milestones: Sept 2008 Agree design specification for the mechanical support for GANIL. May 2009 Finish design of the mechanical support for GANIL. Begin procurement. Oct 2009 Trial assembly of the mechanical support for GANIL. Dec 2009 Installation of the structure in GANIL. Jan 2010 Agree design specification for the mechanical support for GSI. Nov 2010 Finish design of the mechanical support for GSI. Begin procurement. Apr 2011 Trial assembly of the mechanical support for GSI. Jun 2011 Installation of the structure in GSI 25

  26. Acknowledgements Thanks to everyone who was involved in the Mechanical Installation over the last period, a special thanks to: Simone Coelli (INFN-MI) Bart Bruyneel (Cologne Uni.) Denis Conventi (INFN-LNL) Juergen Eberth (Cologne Uni.) Claudio Fanin (INFN-PD) Herbert Hess (Cologne Uni.) Andres Gadea (INFN) Peter Reiter (Cologne Uni.) Ernest Grodner (LNL) Andreas Wiens (Cologne Uni.) Loris Ramina (INFN-PD) Heinz-Georg (CTT) Massimo Rebeschini (INFN-PD) Michel Ozille (GANIL) Javier Valiente (LNL) Michel Tripon (GANIL) Ennio Viscione (INFN-MI) Benuard Remy (GANIL) Tobias Engert (GSI) Rob Griffiths (STFC) Alan Austin (STFC) 26

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend