Variable LOS
Slide #: 1
ACHD Transportation-Land Use Integration Plan (Draft Findings)
ACHD Transportation-Land Use (Draft Findings) ACHD Integration - - PowerPoint PPT Presentation
Variable LOS Transportation-Land Use Integration Plan ACHD Transportation-Land Use (Draft Findings) ACHD Integration Plan (TLIP) Slide #: 1 LOS Background Variable LOS Transportation-Land Use Integration Plan The first effort by ACHD
Variable LOS
Slide #: 1
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Variable LOS
Slide #: 2
ACHD Transportation-Land Use Integration Plan (Draft Findings)
The first effort by ACHD for variable LOS occurred when the impact fee program was established in the early 1990s. At that time various roadways showed the need for additional capacity in the future but a decision was made by ACHD to not alter certain roadways to accommodate capacity (accept congestion) within the Capital Improvements Plan (CIP). Examples of these were: Harrison Blvd, 6th Street, 16th Street and Jefferson Street. ACHD, with the passage of the CIP update in 2006, identified more roadways that would remain in their current configuration despite projected congestion. These were 36th Street from State to Hill and Hill Road. Additional roadways were identified as preservation only, indicating that impacts fees for widening would be collected only for corridor preservation, not construction. These were Overland Road and Franklin Road (which showed the need for 7 lanes), and Ustick from Cole to Curtis (which showed the need for 5 lanes).
Variable LOS
Slide #: 3
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Variable LOS
Slide #: 4
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Meaning there is no more room to build because of various factors (limited right-of-way, developed land use, topography).
Cartwright
from Bogus Basin to Dry Creek
36th Street
from State to Hill Rd
Variable LOS
Slide #: 5
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Meaning the character of the area would be significantly compromised.
Harrison Boulevard Warm Springs
from Broadway to future Parkcenter crossing
Variable LOS
Slide #: 6
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Meaning that the system is complete in a downtown area and expansion would compromise development potential and erode pedestrian level of service.
State Street
Through downtown Eagle Through downtown Meridian – Split Corridor proposed alternative
State St – Glenwood to Downtown Main & Idaho - Downtown
Front/Myrtle constructed as alternative
Variable LOS
Slide #: 7
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Purposely planned for and negotiated by appropriate parties for reasons of feasibility, economic development, land use goals, etc.
McMillan in North Meridian
to accommodate goals for neighborhood centers along the corridor to accommodate goals for neighborhood centers along the corridor
State St – Glenwood to Downtown
Bown Way
to accommodate innovative development
Variable LOS
Slide #: 8
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Arterial Streets
Ada County Street Capacity Guidelines
Arterial Class Lanes C D E
ACHD Principal Arterials
No Left-Turn lane 1 *** 550 690 Continuous Center Left-Turn Lane 1 270 750 880 2 590 1600 1770 3 890 2440 2660 Median Control, Channelized Left-Turn Lanes @ Major Intersections 1 280 790 920 2 620 1680 1860 3 930 2560 2790
ACHD Minor Arterials
No Left-Turn lane 1 *** 550 690 Unrestricted Median, Continuous Center Left-Turn Lane 1 270 720 880 2 590 1540 1770 3 890 2370 2660 Median Control, Channelized Left-Turn Lanes @ Major Intersections 1 280 760 920 2 620 1620 1860 3 930 2490 2790 Level of Service HOURLY VOLUME - PEAK
Variable LOS
Slide #: 9
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Intersections
Table C-5: Intersection Capacity and Analysis Methods
Defined Parameters1 Policy Threshold Sat. Flow. (vphpl) Cycle Length (sec) Min. Left (sec) Lost Time (sec) PHF Capacity: LOS “D” = V/C .90 LOS “E” = 1.00 Method: Intersection v/c = 0.90; AND Lane Group v/c = 1.00 1,900 150 20 3 0.90 Defined parameters are: saturation flow-rate; signal cycle length, minimum left-turn phasing, lost time per phase, and peak hour factor.
Variable LOS
Slide #: 10
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Variable LOS
Slide #: 11
ACHD Transportation-Land Use Integration Plan (Draft Findings)
MOTOR VEHICLE PERFORMANCE MEASURES
Peak Period (one- or two-hour) Level Of Service (LOS) Volume-to-Capacity (V/C)
Jurisdiction
Wilsonville Policy (TSP)
1-Hour PeriodD Possible Exceptions E Lake Oswego
1-Hour PeriodE .90 -.99 Tigard
1-Hour PeriodE .90 -.99 Tualatin Town Center / 2040
1st HrF
2nd HrE Other
1st HrE
2nd HrE Washington County
(AM or PM peak period)Main Streets
2- Hour Period 1st Hr TargetE 0.99
AcceptableE 0.99
2nd Hr TargetD 0.90
AcceptableE 0.99 Urban area
2- Hour Period 1st Hr TargetD 0.90
AcceptableE 0.99
2nd Hr TargetD 0.90
AcceptableD 0.90 METRO RTP - Town Center Mid-Day
PreferredC
AcceptableE 2-Hour AM or PM Peak Period
Preffered 1st HrE
2nd HrE
Acceptable 1st HrF
2nd HrE ODOT (1999 OHP)
Freeway (ramps) 2-Hour0.90
Boones Ferry Rd, Elligsen Rd & Wilsonville Road (Boones Ferry - Town Center Loop W)Motor Vehicle Performance Measures are a technical expresion of the jurisdiction's policy on livability.
Variable LOS
Slide #: 12
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Roadway Level of Service. This is a measure of roadway congestion ranging from… LOS A--least congested -- to LOS F--most congested. LOS is one of the most common terms used to describe how "good" or how "bad" traffic is projected to be. LOS serves as a benchmark to determine whether new development will comply with an existing LOS or if it will exceed the preferred or adopted LOS. Typical Policy Threshold: LOS D
Variable LOS
Slide #: 13
ACHD Transportation-Land Use Integration Plan (Draft Findings)
MOTOR VEHICLE PERFORMANCE MEASURES
Peak Period (one- or two-hour) Level Of Service (LOS) Volume-to-Capacity (V/C)
Jurisdiction
Wilsonville Policy (TSP)
1-Hour Period
D Possible Exceptions E Lake Oswego
1-Hour Period
E .90 -.99 Tigard
1-Hour Period
E .90 -.99 Tualatin Town Center / 2040
1st Hr
F
2nd Hr
E Other
1st Hr
E
2nd Hr
E Washington County
(AM or PM peak period)
Main Streets
2- Hour Period 1st Hr Target
E 0.99
Acceptable
E 0.99
2nd Hr Target
D 0.90
Acceptable
E 0.99 Urban area
2- Hour Period 1st Hr Target
D 0.90
Acceptable
E 0.99
2nd Hr Target
D 0.90
Acceptable
D 0.90 METRO RTP - Town Center Mid-Day
Preferred
C
Acceptable
E 2-Hour AM or PM Peak Period
Preffered 1st Hr
E
2nd Hr
E
Acceptable 1st Hr
F
2nd Hr
E ODOT (1999 OHP)
Freeway (ramps) 2-Hour
0.90
Boones Ferry Rd, Elligsen Rd & Wilsonville Road (Boones Ferry - Town Center Loop W)
Variable LOS
Slide #: 14
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Variable LOS
Slide #: 15
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Variable LOS
Slide #: 16
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Variable LOS
Slide #: 17
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Variable LOS
Slide #: 18
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Variable LOS
Slide #: 19
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Variable LOS
Slide #: 20
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Variable LOS
Slide #: 21
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Local Adoption through
Variable LOS
Slide #: 22
ACHD Transportation-Land Use Integration Plan (Draft Findings)
Tasks
Street Functional Classification & Livable Street Workshops Future Land Use Plans & Policies - Growth Tier System Testing Collector Street Connectivity Impacts on Arterial Streets
City & Impact Area Tiers Regional and Community Activity Centers
Testing Street Level of Service/Performance Measures
Transit Corridors
Products Revised Long-Range Streets Plan
Non-Arterial Street Needs & Costs Revised Street Functional Classification Map & Policy w/ Typologies Revised "Livable" Street Standards* Local Plans & Polcies Corridor Preservation and Access Management Plan Transit-Oriented Design Standards Revised Neighborhood Traffic Management Plan & Policies Local Land Use Plan Refinement Revised LOS Policy and Threshold(s)* (map & table) Adequate Public Facilities Standard - Concurrency Requirements
TRANSPORTATION/LAND USE INTEGRATION PLAN
coordination