Accelerator Complex Ioanis Kourbanis June 12-13, 2013 Outline - - PowerPoint PPT Presentation

accelerator complex
SMART_READER_LITE
LIVE PREVIEW

Accelerator Complex Ioanis Kourbanis June 12-13, 2013 Outline - - PowerPoint PPT Presentation

Status of the Fermilab Accelerator Complex Ioanis Kourbanis June 12-13, 2013 Outline Evolution of the Fermilab Accelerator Complex. Proton Improvements Plan (PIP) Upgrades. Proton Source Throughput. ANU Upgrades.


slide-1
SLIDE 1

Status of the Fermilab Accelerator Complex

Ioanis Kourbanis June 12-13, 2013

slide-2
SLIDE 2

Outline

  • Evolution of the Fermilab Accelerator Complex.
  • Proton Improvements Plan (PIP) Upgrades.
  • Proton Source Throughput.
  • ANU Upgrades.
  • Muon Campus.
  • Start-up Plans.
  • Proton Projections.
  • Conclusions.
  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

2

slide-3
SLIDE 3

Evolution of the Accelerator Complex (through 2020)

3

2012: Shutdown Tevatron 2012-2016: Proton Improvement Plan 2012-2013: Accelerator Upgrades for NOvA 2013-2017: Reconfigure P- bar for mu2e/g-2

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013
slide-4
SLIDE 4

Accelerator complex in the Intensity Frontier

  • Increase the Booster Beam Power by a factor of 2.2

by running the Booster at 15 Hz

  • Proton improvement plan provides the necessary

upgrades assuring high machine availability and low residual activation.

  • Increase the MI beam power by 1.7 to 700 KW by

utilizing the Recycler as a proton accumulator with stacking.

  • ANU Plan provides the Recycler upgrades
  • Need to commission slip stacking in the Recycler.
  • Reconfigure the pbar source into a muon campus

for mu2e/g-2.

  • Series of AIPs/GPPs provide the necessary modifications

required for both experiments.

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

4

slide-5
SLIDE 5

Proton Improvement Plan (PIP) Upgrades

  • Loss reduction
  • Lower linac emittance
  • RFQ & linac lattice improvements
  • Apertures & alignment
  • Comprehensive survey of apertures
  • Alignment where necessary (including

within girders)

  • Opening apertures where possible
  • Optics adjustment
  • Comprehensive survey of lattice and

coupling

  • Control of tunes and chromaticity
  • Automated orbit and optics smoothing
  • RF improvements
  • Increased voltage from amplifiers
  • Cavity modification/replacements
  • Instabilities
  • Dampers
  • Injection painting
  • Orbit Control
  • Magnetic Cogging
  • Prerequisite for other

work

  • Loss Control
  • Rework of notching in

Booster

  • Perform earlier in cycle
  • New notch kickers and

absorber

  • Exploration of full or

partial notching in Linac

  • Collimation system
  • Run beam near primary

scatterer

  • Optimize primary scatter

thickness

  • Operate as true, two-

stage system

  • Adjust radiation shielding

where advantageous

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

5

slide-6
SLIDE 6

New RFQ Injector

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

6

New RFQ Injector New RFQ Injector

Ion Source RFQ

slide-7
SLIDE 7

Booster Aperture Scan

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

Booster Notch Beam Absorber

7

Loss Control and Aperture Improvements

slide-8
SLIDE 8

Booster Solid State Upgrade

  • Completed May 2013
  • Major benefits to reliability and the cost of operation
  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

8

Solid State PA Booster Solid State RF Station

slide-9
SLIDE 9

Booster Cavity Refurbishment Process

Cavity Removal - Stripping Tuners Rebuild Rebuild and Test

Cavity Removal

Weeks

Cool-down Remove Tuners Rebuild - Cones & Tuners Rebuild Stem/Connections Re-Assemble

15 Hz Test

9

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013
slide-10
SLIDE 10

Proton Source Throughput

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

10 90 KW TOTAL (15 Hz) 56 KW required for 700 KW NOvA Operation g-2 12 KW Mu2e 8KW ANU Shutdown 41 KW (6.8 Hz)

slide-11
SLIDE 11

Booster is up and running

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

11 Beam Intensity (E12)

slide-12
SLIDE 12

Accelerator and NuMI Upgrades for NOvA

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

12

  • Recycler Ring, RR
  • New injection line into RR
  • New extraction line from RR
  • New 53 MHz RF system
  • Instrumentation Upgrades
  • New abort kickers
  • Decommissioning of pbar components
  • Main Injector
  • Two 53 MHz cavities
  • Quad Power Supply Upgrade
  • Low Level RF System
  • NuMI
  • Change to medium energy n beam

configuration (new target, horn, configuration)

  • Cooling & power supply upgrades
slide-13
SLIDE 13

Pictures of Recycler ANU Installation

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

13

New Recycler Injection Line New Recycler Extraction Line

slide-14
SLIDE 14

Recycler 53 MHz Cavities

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

14

  • Optimized

for Slip Stacking (R/Q~20 Ohms)

  • Re-use the

PAs from the TeV Cavities

slide-15
SLIDE 15

MI Operation for NOvA

  • MI Cycle Reduced from 2.2

sec (33 Booster Ticks) to 1.33 sec (20 Booster Ticks).

  • MI Beam Intensity

increased by 9% (per bunch intensity remains the same).

  • No Instability Issues are

anticipated.

  • Loss control is the major

Issue (Power loss is increased by 80%).

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

15

20 40 60 80 100 120 140 0.5 1 1.5 2 2.5 Momentum (GeV/c) Time (sec)

Current MI Ramp

20 40 60 80 100 120 140 0.5 1 1.5 2 2.5 Momentum (GeV/c) Time (sec)

MI Ramp for NOvA

slide-16
SLIDE 16

Recycler Operation for NOvA

  • Injection of 12 high intensity

Booster Batches for slip stacking.

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

16 MI Recycler

MI Momentum Beam Current

Main Injector Recycler

  • Up to 8 additional Booster

batches cab be injected in Recycler for delivery to the modified p-bar Rings (Mu2e, g-2 experiments)

slide-17
SLIDE 17

Recycler operation for Mu2e and g-2

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

17

Main Injector Energy Booster Cycles Protons to NOvA Protons to g-2 Protons to MicroBooNE Protons to Mu2e

slide-18
SLIDE 18

MI Injector Power vs. Energy after ANU Upgrades

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

18

200.00 300.00 400.00 500.00 600.00 700.00 800.00 20 40 60 80 100 120 140 B e a m P

  • w

e r ( K W ) MI Beam Momentum (GeV/c)

MI Power (KW) MI Cycle time equals Recycler cycle time

slide-19
SLIDE 19
  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

19

slide-20
SLIDE 20

Start-up Plans (MI/RR)

  • Beam to NuMI Target for tuning within 1 week

from start-up (June 24?).

  • Start SY120 beam studies after 1 week from

start-up.

  • Reach 300 KW beam power after 1 month.
  • 6 Booster batches in MI, 1.7 sec ramp, no slip stacking.
  • Reach 500 KW beam power in 5 months.
  • Using slip stacking in the Recycler.
  • Assuming 7 Hz Booster operation.
  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

20

slide-21
SLIDE 21

Proton Projections

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

21

1 2 3 4 5 6 100 200 300 400 500 600 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Average Power (kW) Integrated POT (e20)

  • Takes into account a 10% timeline use for SeaQuest operations
slide-22
SLIDE 22

Conclusions

  • With the completion of the current shutdown the

Accelerator Complex enters the Intensity Frontier.

  • The Proton Improvement Plan will enable the

Booster to reliably run at 15 Hz.

  • RF cavity refurbishment is the critical path
  • The ANU Upgrades will enable Main Injector to

provide 700 KW of beam power from 80-120 GeV.

  • Plans are in place for transforming the pbar

source into a muon campus for g-2/mu2e.

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

22

slide-23
SLIDE 23

EXTRA SLIDES

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

23

slide-24
SLIDE 24

Booster Losses

  • Losses at injection
  • Poorly captured beam
  • Notch creation
  • Gap for extraction
  • Created with a kicker
  • Lost in gradient magnet
  • Slow losses at high-

energy

  • Optics issues
  • RF variation
  • Transition
  • Occasionally significant,

but can usually be tuned away

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

24

slide-25
SLIDE 25

Recycler Operation for Mu2e

  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

25

slide-26
SLIDE 26
  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

26

10 20 30 40 50 60 70

50 100 150 200 250 300 350 400

Integrated E19

Year Proton Source Yearly and Integrated Output (E19)

Integrated Protons Yearly Protons Annual E19

Booster Collimators FY04 Booster Low Level/Damping FY04 New Booster Injection Line FY FY06 Removal of L13 Extraction Region FY07 Linac Quad PS FY07 Linac Low Energy Low Level FY08 New Ramped Correctors FY09

Typical Non - neutrino HEP Program Proton Source to 2012

Fixed Target ≤ 11 cycle/60 sec Recent rate 1/60 sec Pbar Production ≤ 2 cycles/2.2 sec

Loss Limit

Neutrino Program Proton Source (to 2012) MiniBooNE Started 2001 Cycle rate up to 5 Hz Numi Started in 2005 Cycle rate ~ 5 Hz

slide-27
SLIDE 27
  • I. Kourbanis Fermilab Users Meeting June 12-13 2013

27