accelerator complex
play

Accelerator Complex Ioanis Kourbanis June 12-13, 2013 Outline - PowerPoint PPT Presentation

Status of the Fermilab Accelerator Complex Ioanis Kourbanis June 12-13, 2013 Outline Evolution of the Fermilab Accelerator Complex. Proton Improvements Plan (PIP) Upgrades. Proton Source Throughput. ANU Upgrades.


  1. Status of the Fermilab Accelerator Complex Ioanis Kourbanis June 12-13, 2013

  2. Outline • Evolution of the Fermilab Accelerator Complex. Proton Improvements Plan (PIP) Upgrades. • • Proton Source Throughput. ANU Upgrades. • • Muon Campus. • Start-up Plans. Proton Projections. • • Conclusions. 2 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  3. Evolution of the Accelerator Complex (through 2020) 2013-2017: 2012-2016: Reconfigure P- Proton bar for mu2e/g-2 Improvement Plan 2012: Shutdown Tevatron 2012-2013: Accelerator Upgrades for NOvA 3 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  4. Accelerator complex in the Intensity Frontier • Increase the Booster Beam Power by a factor of 2.2 by running the Booster at 15 Hz Proton improvement plan provides the necessary  upgrades assuring high machine availability and low residual activation. • Increase the MI beam power by 1.7 to 700 KW by utilizing the Recycler as a proton accumulator with stacking. ANU Plan provides the Recycler upgrades  Need to commission slip stacking in the Recycler.  • Reconfigure the pbar source into a muon campus for mu2e/g-2. Series of AIPs/GPPs provide the necessary modifications  required for both experiments. 4 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  5. Proton Improvement Plan (PIP) Upgrades • Loss reduction • Orbit Control Lower linac emittance Magnetic Cogging   RFQ & linac lattice improvements Prerequisite for other • • work Apertures & alignment  • Loss Control Comprehensive survey of apertures • Alignment where necessary (including Rework of notching in •  within girders) Booster Opening apertures where possible • Perform earlier in cycle • Optics adjustment  New notch kickers and • Comprehensive survey of lattice and absorber • coupling Exploration of full or • partial notching in Linac Control of tunes and chromaticity • Automated orbit and optics smoothing Collimation system •  RF improvements Run beam near primary  • scatterer Increased voltage from amplifiers • Optimize primary scatter Cavity modification/replacements • • thickness Instabilities  Operate as true, two- • Dampers stage system • Injection painting Adjust radiation shielding   where advantageous 5 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  6. New RFQ Injector RFQ Ion Source New RFQ Injector New RFQ Injector 6 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  7. Loss Control and Aperture Improvements Booster Aperture Scan Booster Notch Beam Absorber 7 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  8. Booster Solid State Upgrade • Completed May 2013 Major benefits to reliability and the cost of operation • Solid State PA Booster Solid State RF Station 8 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  9. Booster Cavity Refurbishment Process Weeks Re-Assemble Cool-down Rebuild - Cones & Tuners Remove Tuners 15 Hz Test Rebuild Stem/Connections Cavity Removal Tuners Rebuild Cavity Removal - Stripping Rebuild and Test 9 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  10. Proton Source Throughput 90 KW TOTAL (15 Hz) ANU Shutdown 56 KW required for 700 KW NOvA Operation 41 KW (6.8 Hz) g-2 12 KW Mu2e 8KW 10 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  11. Booster is up and running Beam Intensity (E12) 11 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  12. Accelerator and NuMI Upgrades for NOvA • Recycler Ring, RR New injection line into RR • New extraction line from RR • New 53 MHz RF system • Instrumentation Upgrades • New abort kickers • Decommissioning of pbar components • • Main Injector Two 53 MHz cavities • Quad Power Supply Upgrade • Low Level RF System • NuMI • Change to medium energy n beam • configuration (new target, horn, configuration) Cooling & power supply upgrades • 12 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  13. Pictures of Recycler ANU Installation New Recycler Injection Line New Recycler Extraction Line 13 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  14. Recycler 53 MHz Cavities • Optimized for Slip Stacking (R/Q~20 Ohms) • Re-use the PAs from the TeV Cavities 14 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  15. MI Operation for NOvA Current MI Ramp • MI Cycle Reduced from 2.2 140 Momentum (GeV/c) sec (33 Booster Ticks) to 120 100 1.33 sec (20 Booster 80 60 Ticks). 40 20 • MI Beam Intensity 0 0 0.5 1 1.5 2 2.5 increased by 9% (per Time (sec) bunch intensity remains the same). MI Ramp for NOvA No Instability Issues are • 140 anticipated. Momentum (GeV/c) 120 100 Loss control is the major • 80 Issue (Power loss is 60 40 increased by 80%). 20 0 0 0.5 1 1.5 2 2.5 Time (sec) 15 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  16. Recycler Operation for NOvA • Injection of 12 high intensity Booster Batches for slip stacking. Recycler Beam Current Recycler MI MI Momentum • Up to 8 additional Booster Main Injector batches cab be injected in Recycler for delivery to the modified p-bar Rings (Mu2e, g-2 experiments) 16 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  17. Recycler operation for Mu2e and g-2 Protons to Mu2e Main Injector Energy Booster Cycles Protons to NOvA Protons to g-2 Protons to MicroBooNE 17 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  18. MI Injector Power vs. Energy after ANU Upgrades MI Power (KW) 800.00 700.00 B e a 600.00 m P o 500.00 w e r MI Cycle time 400.00 ( equals Recycler K W cycle time ) 300.00 200.00 0 20 40 60 80 100 120 140 MI Beam Momentum (GeV/c) 18 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  19. 19 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  20. Start-up Plans (MI/RR) • Beam to NuMI Target for tuning within 1 week from start-up (June 24?). Start SY120 beam studies after 1 week from • start-up. Reach 300 KW beam power after 1 month. • 6 Booster batches in MI, 1.7 sec ramp, no slip stacking.  • Reach 500 KW beam power in 5 months. Using slip stacking in the Recycler.  Assuming 7 Hz Booster operation.  20 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  21. Proton Projections 600 6 Average Power (kW) Integrated POT (e20) 500 5 400 4 300 3 200 2 100 1 0 0 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 • Takes into account a 10% timeline use for SeaQuest operations 21 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  22. Conclusions • With the completion of the current shutdown the Accelerator Complex enters the Intensity Frontier. • The Proton Improvement Plan will enable the Booster to reliably run at 15 Hz. RF cavity refurbishment is the critical path  The ANU Upgrades will enable Main Injector to • provide 700 KW of beam power from 80-120 GeV. Plans are in place for transforming the pbar • source into a muon campus for g-2/mu2e. 22 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  23. EXTRA SLIDES 23 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  24. Booster Losses Losses at injection • Poorly captured beam  Notch creation • Gap for extraction  Created with a kicker  Lost in gradient magnet  • Slow losses at high- energy Optics issues  RF variation  • Transition Occasionally significant,  but can usually be tuned away 24 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  25. Recycler Operation for Mu2e 25 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  26. Proton Source Yearly and Integrated Output (E19) Neutrino Program Integrated Protons Yearly Protons 400 70 Proton Source (to 2012) Booster Collimators FY04 350 60 Booster Low Level/Damping FY04 300 50 Integrated E19 New Booster Injection Line FY FY06 Annual E19 250 40 MiniBooNE Started 2001 Removal of L13 Extraction Region FY07 200 Linac Quad PS FY07 30 Cycle rate up to 5 Hz 150 Linac Low Energy Low Level FY08 20 100 New Ramped Correctors FY09 Numi Started in 2005 10 50 Cycle rate ~ 5 Hz 0 0 Year Loss Limit Typical Non - neutrino HEP Program Proton Source to 2012 Fixed Target ≤ 11 cycle/60 sec Recent rate 1/60 sec Pbar Production ≤ 2 cycles/2.2 sec 26 I. Kourbanis Fermilab Users Meeting June 12-13 2013

  27. 27 I. Kourbanis Fermilab Users Meeting June 12-13 2013

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend