Status of the Accelerator Complex Status of the Accelerator Complex - - PowerPoint PPT Presentation
Status of the Accelerator Complex Status of the Accelerator Complex - - PowerPoint PPT Presentation
Status of the Accelerator Complex Status of the Accelerator Complex Ioanis Kourbanis Main Injector Department Fermilab Users Meeting June 2, 2010 Overview Overview Summer 09 shutdown. Proton Source performance and Issues. Main
Overview Overview
- Summer 09 shutdown.
- Proton Source performance and Issues.
- Main Injector high power operation and NuMI.
- Collider Run Plan and Performance.
2010 Fermilab Users' Meeting – Kourbanis
2
Summer 09 shutdown Summer 09 shutdown
- Successfully completed a 12 week summer shutdown.
- Removed the berm at two MI locations (MI-10, MI-40) in
- rder to install penetrations required for NOvA running.
- Seven gap clearing kickers were installed in MI that can become
- peration al after this coming shutdown.
- The rest of the Booster corrector magnets were installed.
- Extensive TeV repairs were performed.
- 8 housed were warmed at room temperature to fix vacuum leaks
- 88 TeV magnets were unrolled or moved.
- Pbar fixed a couple of magnets and installed new 4-8GHz
kickers in the Accumulator.
- NuMI fixed horn 2 water leak, replaced target and the
hadron monitor.
2010 Fermilab Users' Meeting – Kourbanis
3
MI Penetrations MI Penetrations
2010 Fermilab Users' Meeting – Kourbanis
4
Kicker penetrations Penetrations for kicker cooling MI-14 Service Building
MI-40 MI-10
MI Tunnel Penetrations MI Tunnel Penetrations
2010 Fermilab Users' Meeting – Kourbanis
5
Recycler MI Magnets at MI-10 covered with lead blankets for personnel protection Recycler magnets MI penetrations
MI MI-40 Gap Clearing Kickers 40 Gap Clearing Kickers
2010 Fermilab Users' Meeting – Kourbanis
6
Proton Source Performance Proton Source Performance
2010 Fermilab Users' Meeting – Kourbanis
7
MISSING RF STATION
- For pbar stacking and NuMI we
need 5Hz and 7.7E16 P/h.
- RF and beam losses is limiting the
rep rate and the total protons per hour.
- Had to reduce the rep rate while
running without spare rf station.
- Problems with the proton source
affected both the protons per hour and the beam quality out of Booster.
- We have started to see the effect of
the Booster correctors.
- More stable conditions for
tuning
- Better working point
- For NOvA we will need 9Hz rep
rate and 1.4E7P/h.
Booster Neutrino Beam Booster Neutrino Beam
2010 Fermilab Users' Meeting – Kourbanis
8
H- Source Problems Increased rep rate No spare Booster RF station
Fermilab Fermilab Pre Pre-Injectors Injectors
2010 Fermilab Users' Meeting – Kourbanis
9
- Two Cockroft-Walton pre-injectors each with a magnetron H- source.
- Only one source and one Cockcroft-Walton operational at any one time.
- We have been operating with one pre-Injector for almost a year.
I- H-
I- Source Problems Source Problems
2010 Fermilab Users' Meeting – Kourbanis
10
- Had to build a new accelerating
column.
- Problems with die off of sources
after that.
- Spend almost a year without it.
- It now up and running (run with it
the last 21/2 months)
H- Source Problems Source Problems
2010 Fermilab Users' Meeting – Kourbanis
11
- H- source has been un-stable since start-up
- The source has been taken out and rebuilt
twice.
- The ion pump has been replaced
- Improved regulation
- It is running better since March
Future Source Future Source
2010 Fermilab Users' Meeting – Kourbanis
12
- Replace the Cockcroft-Walton with a 200MHz RFQ.
- Replace the present magnetron source with a new one with a circular aperture.
- Similar to the BNL current per-accelerator
Booster RF Booster RF
- Booster is currently RF limited.
- We are still using the original Booster cavities.
- Currently we have one of the spare RF cavities installed in the
tunnel as a “hot spare” (cavity 19).
- A ceramic leak on cavity 19 forced us to have no “hot spare” for
almost 3 months.
- We are working on improving the reliability of the Booster RF
cavities with the Solid State Upgrade.
2010 Fermilab Users' Meeting – Kourbanis
13
- History of the Booster rf
- voltage. The voltage varies
depending how many rf stations are ON.
Booster RF Cavities Booster RF Cavities
2010 Fermilab Users' Meeting – Kourbanis
14
- Booster rf station with Solid State Upgrade.
Only the final power tube is in the tunnel.
- Plan to upgrade the rest of the 16 Booster
stations.
- Original Booster rf station. The whole driver
section of the final tetrode is in the tunnel. It includes 14 parallel connected tetrodes with water cooling.
Power tetrodes
MI Beam Power MI Beam Power
2010 Fermilab Users' Meeting – Kourbanis
15
- We have achieved 95% of the design MI power at 120 GeV.
- Losses in MI are currently preventing us of achieving 400KW.
- To address the losses we need the clearing gap kickers to become
- perational.
- MI uptime is 95%.
- RF Cavity water leaks are a source of concern.
MI Beam Power from 08/2008-04/09
GOAL
Beam to Beam to NuMI NuMI
2010 Fermilab Users' Meeting – Kourbanis
16
Switched to SS for NuMI Horn 1 replacement Horn 2 replacement
- Have delivered more that 2.2E20 protons this
year and more than 1E21P so far!
- No component failures in the NuMI beam line
and better MI performance.
MI RF water leaks MI RF water leaks
- MI is using the old Main Ring RF cavities.
- The driver section of all the MI cavities has been replaced
with solid state drivers (Solid State Upgrade) greatly increasing the reliability.
- Lately we dealing with more and more water leaks in the RF
cavities.
- For the first time in MI we had to take a cavity out of the
tunnel in order to replace a water leak.
- One of the spare MI cavities that has been re-furbished for NOvA
replaced the leaking cavity.
- We plan to proactively address the cavity cooling problems.
- We are working on a new RF cavity prototype for MI
(Project X).
2010 Fermilab Users' Meeting – Kourbanis
17
MI RF Cavity water leak MI RF Cavity water leak
2010 Fermilab Users' Meeting – Kourbanis
18
Cavity water leak
MI Spare Cavity refurbished for NOvA operation
Collider Run Plan Collider Run Plan
- Emphasis is placed on optimizing Integrated
Luminosity.
- All major upgrades have been completed
- Complex is more stable, conditions are more reproducible.
- Use operational model based on recent data to
model the Accelerator performance and find the
- ptimum Pbar initial conditions for maximizing
integrated Luminosity.
- We are working on 3 major improvements
- Maximize Pbar production
- Reduction of the time we spend in HEP shot set-up
- Increase of the proton Brightness
2010 Fermilab Users' Meeting – Kourbanis
19
Response of the model Response of the model
10 20 30 40 50 60 70 80 90 100 200 300 400 500 600 700 Number Of Pbars (Stash size) E10
Intergrated lum. pb-1
Driven By Number of Pbars Driven By Pbars/luminosity lifetime & Pbar Production Rate
- 30 e10/hr Pbar production rate
- 20 e10/hr Pbar production rate
Driven By Pbar Production rate and Luminosity lifetime Driven By Collider Shot Setup Time
20
Maximizing Pbar Production Maximizing Pbar Production
24 48 72 96 120 144 168 2005 2009 Hours per week Downtime Hours Study Hours Set-up Hours Stacking Hours
15% 1% Items addressed
- Reduced Shot setup time
- Optimize number of stacking cycles
- Increased Proton on Target
Along with a long list of machine improvements
21
- Maximize Pbar production
- Shorting Pbar transfer to Recycler (maximizing
effective stacking rate) – TLG modification – Reducing interruption to stacking
» Interruption to stack was ~1 hour a 1.5 years ago now it 15 sec
– Improving Recycler Lifetime
» Adjusted the incoming beam parameter to maximize cooling efficiency of the machine
Shot Setup Time Reduction Shot Setup Time Reduction
22
Optimizing Proton Brightness Optimizing Proton Brightness
- Done by scraping the Proton halo in the Main Injector at 8 GeV
- Improved Initial Luminosity ~3-4%
- Transfer/Acceleration efficiency improvement
- Improves Tevatron dynamic aperture of the machine, reduced
quenching
- Defined as:
Bunch Intensity/ ( Avg. Transverse Emittance X Longitudinal emittance)
y = -0.0011x2 + 1.2533x y = -0.0011x2 + 1.2996x 150 200 250 300 350 400 100 200 300 400 500 pre scraping stores Post scrape Store
- Poly. (pre scraping
stores)
- Poly. (Post scrape
Store)
23
Pbars E10 Instantaneous Luminosity E30
Effects of the Source problems Effects of the Source problems
24
Results to the improvements Results to the improvements
25
7.5%
Sum of improvements made to the complex we see 7.5% improvement to initial luminosity for the same number of protons and pbars used
Record initial luminosity
TeV TeV Reliability Reliability
Year ar Store
- res
Norm rmal al Term rmin inat ations ions %Norm rmal l Term rmin inat ations ions Avg Store re Hrs/Week eek (out utside ide of plann nned ed shut hutdow
- wns
ns)
2003 186 55 30%
- FY04
162 106 65% 100 FY05 211 145 69% 110 FY06 163 101 62% 100 FY07 235 187 80% 110 FY08 304 242 80% 106 FY09 293 253 86% 108 FY10 272 234 86% 124
Improving Reliability
Collider Performance Collider Performance
2010 Fermilab Users' Meeting – Kourbanis
27
- Integrated Luminosity
above the red line.
- Averaging 58 1/pb per
week.
1 2 3 4 5 6 7 8 9 10 11 12 13
Luminosity Projection through FY11 Luminosity Projection through FY11
FY11 start Real data for FY02-FY09 12 fb-1 10 fb-1
Highest Int. Lum Lowest Int. Lum
FY10 start
Integrated luminosity (fb-1)
The green line assumes the same rate for delivered luminosity as in FY09, 50 pb-1/week
Summary Summary
- Successfully completed a 12 week long shutdown.
- Finished the installation of the Booster correctors.
- Finished the MI penetrations for NOvA and installed the
Gap Clearing Kickers.
- Very good overall performance of the accelerator
complex despite problems with aging systems.
- Record beam delivered to NuMI target.
- Record integrated and initial luminosity for Collider.
- We are developing a plan to upgrade our proton
source in order to meet the increasing proton demands.
2010 Fermilab Users' Meeting – Kourbanis
29