status of the accelerator complex status of the
play

Status of the Accelerator Complex Status of the Accelerator Complex - PowerPoint PPT Presentation

Status of the Accelerator Complex Status of the Accelerator Complex Ioanis Kourbanis Main Injector Department Fermilab Users Meeting June 2, 2010 Overview Overview Summer 09 shutdown. Proton Source performance and Issues. Main


  1. Status of the Accelerator Complex Status of the Accelerator Complex Ioanis Kourbanis Main Injector Department Fermilab Users’ Meeting June 2, 2010

  2. Overview Overview  Summer 09 shutdown.  Proton Source performance and Issues.  Main Injector high power operation and NuMI.  Collider Run Plan and Performance. 2 2010 Fermilab Users' Meeting – Kourbanis

  3. Summer 09 shutdown Summer 09 shutdown Successfully completed a 12 week summer shutdown.  Removed the berm at two MI locations (MI-10, MI-40) in  order to install penetrations required for NOvA running.  Seven gap clearing kickers were installed in MI that can become operation al after this coming shutdown. The rest of the Booster corrector magnets were installed.  Extensive TeV repairs were performed.   8 housed were warmed at room temperature to fix vacuum leaks  88 TeV magnets were unrolled or moved. Pbar fixed a couple of magnets and installed new 4-8GHz  kickers in the Accumulator. NuMI fixed horn 2 water leak, replaced target and the  hadron monitor. 3 2010 Fermilab Users' Meeting – Kourbanis

  4. MI Penetrations MI Penetrations MI-40 MI-10 Kicker penetrations MI-14 Service Building Penetrations for kicker cooling 4 2010 Fermilab Users' Meeting – Kourbanis

  5. MI Tunnel Penetrations MI Tunnel Penetrations Recycler MI Magnets at MI-10 covered with lead blankets for personnel protection Recycler magnets MI penetrations 5 2010 Fermilab Users' Meeting – Kourbanis

  6. MI MI-40 Gap Clearing Kickers 40 Gap Clearing Kickers 6 2010 Fermilab Users' Meeting – Kourbanis

  7. Proton Source Performance Proton Source Performance • For pbar stacking and NuMI we need 5Hz and 7.7E16 P/h. • RF and beam losses is limiting the rep rate and the total protons per hour. • Had to reduce the rep rate while running without spare rf station. • Problems with the proton source affected both the protons per hour and the beam quality out of Booster. • We have started to see the effect of the Booster correctors. • More stable conditions for tuning • Better working point • For NOvA we will need 9Hz rep rate and 1.4E7P/h. MISSING RF STATION 7 2010 Fermilab Users' Meeting – Kourbanis

  8. Booster Neutrino Beam Booster Neutrino Beam Increased rep rate No spare Booster RF H- Source station Problems 8 2010 Fermilab Users' Meeting – Kourbanis

  9. Fermilab Fermilab Pre Pre-Injectors Injectors I- H- • Two Cockroft-Walton pre-injectors each with a magnetron H- source. • Only one source and one Cockcroft-Walton operational at any one time. • We have been operating with one pre-Injector for almost a year. 9 2010 Fermilab Users' Meeting – Kourbanis

  10. I- Source Problems Source Problems • Had to build a new accelerating column. • Problems with die off of sources after that. • Spend almost a year without it. • It now up and running (run with it the last 21/2 months) 10 2010 Fermilab Users' Meeting – Kourbanis

  11. H- Source Problems Source Problems • H- source has been un-stable since start-up • The source has been taken out and rebuilt twice. • The ion pump has been replaced • Improved regulation • It is running better since March 11 2010 Fermilab Users' Meeting – Kourbanis

  12. Future Source Future Source • Replace the Cockcroft-Walton with a 200MHz RFQ. • Replace the present magnetron source with a new one with a circular aperture. • Similar to the BNL current per-accelerator 12 2010 Fermilab Users' Meeting – Kourbanis

  13. Booster RF Booster RF Booster is currently RF limited.  We are still using the original Booster cavities.  Currently we have one of the spare RF cavities installed in the  tunnel as a “hot spare” (cavity 19). A ceramic leak on cavity 19 forced us to have no “hot spare” for  almost 3 months. We are working on improving the reliability of the Booster RF  cavities with the Solid State Upgrade. • History of the Booster rf voltage. The voltage varies depending how many rf stations are ON. 13 2010 Fermilab Users' Meeting – Kourbanis

  14. Booster RF Cavities Booster RF Cavities Power tetrodes • Original Booster rf station. The whole driver section of the final tetrode is in the tunnel. It includes 14 parallel connected tetrodes with water cooling. • Booster rf station with Solid State Upgrade. Only the final power tube is in the tunnel. • Plan to upgrade the rest of the 16 Booster stations. 14 2010 Fermilab Users' Meeting – Kourbanis

  15. MI Beam Power MI Beam Power GOAL MI Beam Power from 08/2008-04/09 • We have achieved 95% of the design MI power at 120 GeV. • Losses in MI are currently preventing us of achieving 400KW. • To address the losses we need the clearing gap kickers to become operational. • MI uptime is 95%. • RF Cavity water leaks are a source of concern. 15 2010 Fermilab Users' Meeting – Kourbanis

  16. Beam to Beam to NuMI NuMI • Have delivered more that 2.2E20 protons this year and more than 1E21P so far! • No component failures in the NuMI beam line and better MI performance. Horn 1 Horn 2 replacement replacement Switched to SS for NuMI 16 2010 Fermilab Users' Meeting – Kourbanis

  17. MI RF water leaks MI RF water leaks MI is using the old Main Ring RF cavities.  The driver section of all the MI cavities has been replaced  with solid state drivers (Solid State Upgrade) greatly increasing the reliability. Lately we dealing with more and more water leaks in the RF  cavities. For the first time in MI we had to take a cavity out of the  tunnel in order to replace a water leak.  One of the spare MI cavities that has been re-furbished for NOvA replaced the leaking cavity. We plan to proactively address the cavity cooling problems.  We are working on a new RF cavity prototype for MI  (Project X). 17 2010 Fermilab Users' Meeting – Kourbanis

  18. MI RF Cavity water leak MI RF Cavity water leak Cavity water leak MI Spare Cavity refurbished for NOvA operation 18 2010 Fermilab Users' Meeting – Kourbanis

  19. Collider Run Plan Collider Run Plan  Emphasis is placed on optimizing Integrated Luminosity.  All major upgrades have been completed  Complex is more stable, conditions are more reproducible.  Use operational model based on recent data to model the Accelerator performance and find the optimum Pbar initial conditions for maximizing integrated Luminosity.  We are working on 3 major improvements  Maximize Pbar production  Reduction of the time we spend in HEP shot set-up  Increase of the proton Brightness 19 2010 Fermilab Users' Meeting – Kourbanis

  20. Response of the model Response of the model • 30 e10/hr Pbar production rate 90 • 20 e10/hr Pbar production rate Driven By Pbar Production rate and Luminosity 80 Intergrated lum. pb-1 lifetime Driven By Number of Pbars 70 60 Driven By Collider Shot Setup Time 50 40 Driven By 30 Pbars/luminosity lifetime & Pbar Production Rate 20 10 0 0 100 200 300 400 500 600 700 Number Of Pbars (Stash size) E10 20

  21. Maximizing Pbar Production Maximizing Pbar Production 168  Maximize Pbar production Downtime • Shorting Pbar transfer to Recycler (maximizing 144 Hours 1% effective stacking rate) Study Hours – TLG modification 15% 120 Set-up Hours per week – Reducing interruption to stacking Hours Stacking 96 » Interruption to stack was ~1 hour a 1.5 years Hours ago now it 15 sec 72 – Improving Recycler Lifetime » Adjusted the incoming beam parameter to maximize cooling efficiency of the machine 48 24 0 2005 2009 Items addressed • Reduced Shot setup time • Optimize number of stacking cycles • Increased Proton on Target Along with a long list of machine improvements 21

  22. Shot Setup Time Reduction Shot Setup Time Reduction 22

  23. Optimizing Proton Brightness Optimizing Proton Brightness Done by scraping the Proton halo in the Main Injector at 8 GeV  Improved Initial Luminosity ~3-4%  Transfer/Acceleration efficiency improvement  Improves Tevatron dynamic aperture of the machine, reduced  quenching Defined as:  Bunch Intensity/ ( Avg. Transverse Emittance X Longitudinal emittance) Instantaneous Luminosity E30 400 350 pre scraping stores y = -0.0011x 2 + 1.2996x 300 Post scrape Store Poly. (pre scraping 250 stores) Poly. (Post scrape y = -0.0011x 2 + 1.2533x Store) 200 Pbars E10 150 0 100 200 300 400 500 23

  24. Effects of the Source problems Effects of the Source problems 24

  25. Results to the improvements Results to the improvements Record initial luminosity 7.5% Sum of improvements made to the complex we see 7.5% improvement to initial luminosity for the same number of protons and pbars used 25

  26. TeV TeV Reliability Reliability Avg Store re Hrs/Week eek Norm rmal al %Norm rmal l Year ar Store ores (out utside ide of plann nned ed Term rmin inat ations ions Term rmin inat ations ions shut hutdow owns ns) 2003 186 55 30% - FY04 162 106 65% 100 Improving Reliabilit y FY05 211 145 69% 110 FY06 163 101 62% 100 FY07 235 187 80% 110 FY08 304 242 80% 106 FY09 293 253 86% 108 FY10 272 234 86% 124

  27. Collider Performance Collider Performance • Integrated Luminosity above the red line. • Averaging 58 1/pb per week. 27 2010 Fermilab Users' Meeting – Kourbanis

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend