ACC Expansion Considering the options to add fan modules to the - - PowerPoint PPT Presentation

acc expansion considering the options to add fan modules
SMART_READER_LITE
LIVE PREVIEW

ACC Expansion Considering the options to add fan modules to the - - PowerPoint PPT Presentation

ACC Expansion Considering the options to add fan modules to the Matimba ACC's. Hein Goldschagg, ESKOM ACCUG Nevada Conference 2013 Contents Background Nature of performance losses Low cost options to improve air flow (wind)


slide-1
SLIDE 1

ACC Expansion Considering the options to add fan modules to the Matimba ACC's.

Hein Goldschagg, ESKOM ACCUG Nevada Conference 2013

slide-2
SLIDE 2

2

Contents

  • Background
  • Nature of performance losses
  • Low cost options to improve air flow (wind)
  • High Cost options to improve performance (temp & wind)
  • Determining the performance benefits of the options
  • Focus on worst performing Units
slide-3
SLIDE 3

Background

  • At the time of its construction, the Matimba was 10 times larger than

the largest existing air cooled power station in the world.

  • Turbines with air cooled condensers do not have a constant output as

the output is directly related to the ambient temperature. The amount

  • f over(winter)/under(summer) ACC capacity is determined by the

capital cost and the reserve margin of the grid to compensate for under- capacity

  • A station is licenced for a fixed rated output derived from its design

points and vacuum related outputs lower than the rated output are considered to be “load losses” by the Grid Control

  • The effect of atmospheric ambiences related to temperature, such as

adverse wind conditions and inversion were not extensively incorporated in the design of Matimba

  • It is therefore an anomaly that the largest ACC in the world was built a

bit too compact and small!

3

slide-4
SLIDE 4

4

890 900 910 920 930 940 950 960 0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 45.0 50.0 ACC pressure, kPa Heat rejected, M 610 620 630 640 650 660 670 680 Turbine output, M Matimba Heat Rejected, MW Matimba Turbine Output, MW

Bow-tie curve for ACC Turbine/ACC characteristic “bow tie” curve

slide-5
SLIDE 5

5

Nature of performance losses

  • Averaged annual ACC losses per Unit (18 years data)
  • Unit 1 & 6: 48% of losses
  • Unit 2 & 5: 33% of losses
  • Unit 3 & 4: 19% of losses

Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Unit 6 MWHr pa

The particular pattern is caused by a combination of adverse winds and high temperature

slide-6
SLIDE 6

U6 Load loss curves based on observation.

Use to predict output from weather forecasts

6

slide-7
SLIDE 7

CFD pressure field simulation

7

The CFD pressure field just below the fans indicates a lower fan inlet pressure at Unit 1 and 6. It shows that Unit 2 should be the best performing Unit while that honour belongs to Unit 3 . The CFD simulations are run as steady state conditions and at do not cater for the transient .conditions typical with

  • wind. It is a useful tool but

can not solely be used to guarantee performance increase expectations.

slide-8
SLIDE 8

Low Cost Options; air flow improvement modifications implemented

8

Cladding on turbine hall walls and ACC removed to create air passage to U6 fans with westerly winds

Cladding removed

slide-9
SLIDE 9

Low pressure below U1 and U6

  • uter fans remain significant.

Current configuration Westerly wind 6m/s

Wind direction

Low pressure (-150Pa) Low pressure (-120Pa) 9

slide-10
SLIDE 10

One remaining low cost option

The extent of the modifications already implemented is not sufficient to eradicate wind problems. An experimental project is initiated to modify the U6 turbine hall roof to create a larger passage for the westerly winds. The success of the Unit 6 roof modification will determine if the rest of the Units will be modified as well.

10

PROPOSED TURBINE HALL ROOF MODIFICATION

ACC Aux Boiler house Bay Turbine Hall

slide-11
SLIDE 11

Options for further improvement

 Increase the number of fans and heat exchangers:

– This gives more mass flow rate due to higher number of fans – It also increases heat transfer Area

Q m c T T UA m c

a pa s a a pa

in

= − − −            

( ) exp

1 More fans would result in an even lower pressure under the platform and could therefore cause more hot air recirculation? - Simulate to get indication

slide-12
SLIDE 12

High cost option 1: 8 x additional 9

meter fans

12

Advantages: Wide platform

  • verhang inhibits

recirculation, and also allow for increased number of bundles per fan Disadvantages: Construction works required close and over HV lines. Additional columns to be constructed

slide-13
SLIDE 13

High Cost Option 2: 16 x

additional 9m fans added

13

Advantages: Gives highest MW increase in

  • utput

Disadvantages: Requires additional columns, 400kV lines in construction area, additional duct required to prevent very high steam velocities and tube inlet erosion

slide-14
SLIDE 14

Construction Obstacle

14

A major disadvantage of options 1 and 2 is the position of the generator transformers and 400kV lines coming from below the ACC platform. Constructions should ideally take place while the Units remain in operation.

slide-15
SLIDE 15

Option 3: 14 Additional 7m fans

supported on turbine hall wall

15

Design checks indicate turbine hall wall can support additional fan modules. Advantages: No support columns required, short steam ducting, dephlegmators remains in middle of ACC, steam velocities not significantly

  • affected. Construction
  • ut of HV line way

Disadvantages: Not accessible with tower crane to construct, maintenance access very restricted

slide-16
SLIDE 16

Unit specific Option: Add 12 larger

10m fans to Unit 1 and Unit 6

16

U6 ACC

U1 ACC

Unit 1 and 6 ACC platforms can be extended to the north and south without interference from the HV equipment. Larger sized fan modules are considered and simulated as the “worst case” that may negatively affect the fan performance of the existing ELF fans

slide-17
SLIDE 17

Calculated Back pressure improvement per Option for the ambient temp range (GEA)

17

slide-18
SLIDE 18

Ambient temperature distribution – hours per annum

18

Hours per annum Ambient Temperature range °C

slide-19
SLIDE 19

Info required to calculate MWhr Gain at constant steam flow for each option

19 y = 0.0002x3 + 0.0011x2 + 0.2015x + 11.898 y = 0.0134x2 + 0.0013x + 9.7092

  • 5.0

5.0 15.0 25.0 35.0 45.0 55.0 65.0

  • 8.0

2.0 12.0 22.0 32.0 42.0

MWhr = Σ (MW increase per kPa decrease x Ambient temp distribution per °C)

slide-20
SLIDE 20

Indicative MWhr gained per option wrt ambient temp distribution profile

20

Advantage in coal saving & carbon footprint Advantage in load loss reduction

slide-21
SLIDE 21

Evaluation of an ACC enlargement project

  • Increasing the size of an ACC includes elements of both efficiency

improvement and capacity increase . Environmental aspects such as reduction in carbon footprint is also lately becoming more prominent Economic evaluation of a project to enlarge the ACC depends on how the project is viewed by the utility.

  • If the project is considered a capacity increase venture then a levelised

cost model may be used to compare the increased capacity with other green fields projects. An environmental assessment will normally be required for a capacity increase project.

  • Should the project be considered an efficiency increase project a

different economic model is used that compares the cost of generation at different power stations of the utility at normal and peak time to determine the viability of the project

  • Ideally the evaluation should consider both aspects but may become

quite complex to model.

21

slide-22
SLIDE 22

Aknowledgements

  • Thanks to:
  • Eskom Management
  • Dr F du Preez
  • Dr JP Pretorius
  • GEA Air Cooled Systems
  • Aerotherm

22

slide-23
SLIDE 23

THANK YOU