a14 cambridge to huntingdon improvement scheme
play

A14 Cambridge to Huntingdon improvement scheme Members Briefing - PowerPoint PPT Presentation

A14 Cambridge to Huntingdon improvement scheme Members Briefing Monday, 18 July 2016 Agenda Welcome & introductions Scheme outline and progress Community Fund launch Code of Construction Practice - what it means in practice


  1. A14 Cambridge to Huntingdon improvement scheme Members’ Briefing Monday, 18 July 2016

  2. Agenda § Welcome & introductions § Scheme outline and progress § Community Fund launch § Code of Construction Practice - what it means in practice - Construction routes § On-going Members and community updates § Questions & Answers

  3. Scheme Update Mike Evans Strategic Stakeholder Manager

  4. Development Consent Order § 11 May 2016 Order made by SoS § 1 June 2016 Order in force § 23 May 2016 BICC confirms available funds § 23 June 2016 Legal Challenge Period ends – no challenge

  5. Current state of play § Six months examination § Discharge of DCO requirements § Notice to Proceed § Land acquisition § On-going survey work

  6. DCO Discharge of Requirements § Design of River Great Ouse crossing § Landscaping strategy § Archaeological interests § Air quality monitoring § Traffic monitoring § Brampton Meadows SSSI

  7. Land Acquisition § Temporary licences § Temporary possession § GVD(s)

  8. The next few months § Preparation for construction compounds § Archaeology § Traffic management on A1 from autumn § Start of works exhibitions

  9. S ection 1

  10. Overall Construction Phases 2016 2017 2018 2019 2020 Section Mobilisation S ection 1 – A1 Alconbury –Brampton Hut S ection 2 – A1/ A14 Brampton Hut – East Coast Main Line (ECML) S ection 3 – A14 2020 ECML - S wavesey Construction complete and site S ection 4 – A14 breakdown S wavesey – Girton S ection 5 – A14 Girton - Milton Section 6 - Huntingdon

  11. Community Fund Launch Gerard Smith Legacy Manager

  12. A14 Community Fund Managed by Cambridgeshire Community Foundation (registered charity 1103314)

  13. A14 Community Fund § Grant Programme managed by Cambridgeshire Community Foundation § Ring fenced sum of money to be used to make grants to Not for Profit groups § Grants to support charitable projects with public benefit

  14. Grants Awarded by Cambridgeshire Community Foundation in past 6 years 2 M illions 1.8 1.6 1.4 1.2 1 0.8 0.6 0.4 0.2 0 Mar-11 Mar-12 Mar-13 Mar-14 Mar-15 Mar-16

  15. Ring-fenced Money Ring-fenced sum of money to be used to make grants to Not for Profit groups: § Charities, schools, community groups, parish councils, sports clubs, etc

  16. Grants Grants to support charitable projects with public benefit, which – are within selected themes – take into account the transformation that the A14 Cambridge to Huntingdon improvement scheme will deliver

  17. Themes The Fund will offer support to projects within 8 themes: 1. Environmental improvement 2. Reduce vehicle use/promote cycling, walking and other non-motorised transport 3. Arts, culture & heritage 4. Community involvement 5. Community safety 6. Community health and wellbeing 7. Leisure and tourism 8. Skills, education & employment support

  18. Links Projects need either: § a close geographical link but greater priority to projects that are: § a response to the scheme. For example, – art projects that reflect landscape/ community change brought about by the scheme – projects that build relationships in communities due to new links created by the scheme – projects enhancing the natural environment around the scheme – training projects that enable people employment on the scheme.

  19. Process and timetable § Launch - July 2016 § Grants of up £10,000 available in a series of rounds during 2016/17 and 2017/18 § First deadline 15 Sept 2016 § Application online via CCF website

  20. Recipients § Must be ‘Grant Ready’ § Have 10-20% of project costs from other sources § Must agree to provide monitoring on the change/impact of the grant § Recognise source of funding.

  21. For more information The A14 Community Fund is managed by Cambridgeshire Community Foundation T 01223 410535 E info@cambscf.org.uk www.cambscf.org.uk/A14.html

  22. Code of Construction Practice Construction Routes Julian Lamb Head of Construction (on-line)

  23. Purpose of the Code § Sets out a series of measures and standards of work to; – Control potential impacts on people, businesses and the natural and historical environment – Ensure there are clear methods for engagement during construction

  24. Potential direct impact on residents if not managed § Environmental management and implementation § General site operations § Air quality § Cultural heritage § Community and private assets § Geology and soils § Landscape § Material resources § Nature conservation § Noise and vibration § Road drainage and the water environment § Traffic, transport and road users § Community relations

  25. General site operations § Section 61 (Control of Pollution Act 1974) § Core hours – Weekdays 08:00 to 18:00 – Saturday 08:00 to 16:00 § Start-up and close-down allowed 1 hour either side § Night time works likely – online sections (1, 4 & 5)

  26. S ection 1

  27. Air Quality § Dust and air pollution control plus monitoring during construction § Site compound layout designed to minimise potential impact § Machinery to be modern and switched off when not in use § Temporary stockpiles stabilised or covered

  28. Noise and vibration § Section 61 (Control of Pollution Act 1974) § We will use best practicable means at source to minimise at all times – Equipment – Methodology – Screening

  29. Road drainage and water § Flood risk – no increase during construction § Mains and private supplies § Land drains § Temp construction site drainage system § Early completion of permanent drainage § Prevent site run-off entering watercourses § Pollution prevention plan

  30. Traffic, transport and road users Public Traffic § Retain existing number of lanes during the day (Monday to Friday) § Speed restrictions and speed cameras § Breakdown recovery Site Traffic § Haul roads and plant crossings § Left in, left out at works access points § Recycling to reduce lorry movements § Temporary road closures § Traffic management working group

  31. New A14 alignment Permissible haul routes

  32. Agreed diversion routes

  33. Community and private access § Access to residential areas will be maintained until an alternative has been created – Diversions may be necessary but will be notified in advance § Land owners may have numerous changes

  34. Maintaining community relations Pam Hobson Head of Stakeholder Engagement & Communications

  35. Community Relations § Pro-active, high quality, effective and sustained communication. – Website – Newsletters – Direct mailing – Mobile visitor centre – Social media – Enquiry and complaints handling – How to contact us?

  36. Construction Engagement Team Pam Hobson M ike Evans Anna Smyth Head of S takeholder S trategic Stakeholder Property Assistant Engagement & Manager Project Manager Communications J on Lewell Bob Pettipher J ade Pettit S ect 1 & 2 S ect 4 & 5 S ect 3 S takeholder Manager S takeholder Manager S takeholder Manager

  37. Members engagement during construction § How can we best work with you? ?

  38. Night-time lane closures this week (20:00hrs - 06:00hrs) due to surveys § Monday 18th July – Lane closures on A1307 at Girton. Both directions § Tuesday 19th July – Lane closures on A1307 at Girton. Both directions § Wednesday 20th July – Lane closures on A14 Bar Hill to Dry Drayton Eastbound – Hard shoulder closed M11 Southbound on-slip at Girton § Thursday 21 st July – Lane closures on A1 Alconbury to Brampton Hut. Both directions

  39. What will the road look like?

  40. Questions?

  41. Back up information

  42. General Public Engagement To date we have; ü Hosted numerous forums ü Been the focal point for consistent messages about the scheme ü Issue 20,000 quarterly newsletters During construction § Presentations and site visits § Mobile visitor centre § Volunteering

  43. Construction Compounds

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend