a winding road building a
play

A Winding Road: Building a Sustainable Sanitary Sewer Stream - PowerPoint PPT Presentation

A Winding Road: Building a Sustainable Sanitary Sewer Stream Crossing in Emergency Conditions APWA Mid-Atlantic Conference Virginia Beach, VA May 10, 2013 Outline Background Site Conditions Immediate Response Temporary


  1. A Winding Road: Building a Sustainable Sanitary Sewer Stream Crossing in Emergency Conditions APWA Mid-Atlantic Conference Virginia Beach, VA May 10, 2013

  2. Outline  Background  Site Conditions  Immediate Response  Temporary Solution  Permanent Solution  Construction  Questions

  3. Background – Location DC Fairfax County Alexandria

  4. Tropical Storm Lee Fairfax DC County Alexandria

  5. Tropical Storm Lee  The Holmes Run Crossing saw 8-10 inches of rain  Parts of Fairfax County received over 5 inches of rain in 5 hours  Rainfall equated to 500-1000 year storms in parts of Fairfax County

  6. Outline  Background  Site Conditions  Immediate Response  Temporary Solution  Permanent Solution  Construction  Questions

  7. Before Lee Neighboring Utility Sewer Fairfax County Sewer

  8. After Lee Neighboring Utility Sewer Fairfax County Sewer Damaged Sewer

  9. Site Conditions (After Lee) County 36” Encased Concrete Sewer Weir Apron Low Flow weir Cut into Dam Concrete Dam with Z-pile

  10. Apron Void

  11. Causes for Damaged Pipe  Large high intensity flows in Holmes Run  Scour caused by high flows  Earthquake?

  12. Outline  Background  Site Conditions  Immediate Response  Temporary Solution  Permanent Solution  Construction  Questions

  13. Immediate Response  By pass pumping in place within 48 hours of discovery of the break  Emergency Contractors  Adjustment of weir boards in an upstream flow structure  Working with neighboring agencies to coordinate pumps and response

  14. Pumps  Silent pumps to limit disturbance to surrounding community  24 pump monitoring to prevent overflows  High Cost

  15. Outline  Background  Site Conditions  Immediate Response  Temporary Solution  Permanent Solution  Construction  Questions

  16. Temporary Solution  On land connection to the adjacent trunk sewer  The connection is suitable dry weather and smaller wet weather storms  Allowed for time to design a long term solution

  17. Connection to Adjacent Sewer Neighboring Utility Sewer Fairfax County Sewer New Sewer Damaged Sewer

  18. Temporary Structure Features  Canal Gate  Pipe Slope

  19. Outline  Background  Site Conditions  Immediate Response  Temporary Solution  Permanent Solution  Construction  Questions

  20. Permanent Solution  Drop Manhole  Micropiles  Structural Steel  Protecto 401  Stream Bank Protection  Stream Restoration

  21. Permanent Crossing Overview Neighboring Utility Sewer Fairfax County Sewer New Sewer New Manhole

  22. Drop Manhole  Lowers the elevation of the pipe in the stream  Allows for better pipe protection and armoring

  23. Micropiles  14 micropiles in 7 pairs  Core reinforcement, steel casing, grout  Drilled into disintegrated rock  Drilled and not driven to protect the weir and stream

  24. Structural Steel  Gussett Plate  Lacing  Transversal beam  Longitudinal Beams  Cradle Stiffener Plate  Bents

  25. Pipe and Protecto 401  36” Diameter Ductile Iron Pipe  Protecto 401 Liner Selected

  26. Stream Bank Restoration  Coir Block Soil Lifts at Construction entrances

  27. Stream Restoration  Upstream and Downstream of the Weir Apron  Reinforced Bed Mixture  Stream Base Fill  Imbricated Rock

  28. Stream Restoration - Downstream

  29. Low Flow Weir Cut Out

  30. Outline  Background  Site Conditions  Immediate Response  Temporary Solution  Permanent Solution  Construction  Questions

  31. Construction  PortaDam  Goose

  32. Porta Dam

  33. Porta Dam

  34. Porta Dam

  35. Dry Site

  36. Dry Site

  37. Goose on Site

  38. Outline  Background  Site Conditions  Immediate Response  Temporary Solution  Permanent Solution  Construction  Questions

  39. Acknowledgements Jonathan Okafor Mike Pekkala   mpekkala@greeley-hansen.com Jonathan.okafor@fairfaxcounty.gov Clyde Wilber Thomas J. Russell   cw@clydewilberllc.com Thomas.russell@fairfaxcounty.gov Carlos Englert Sam Shaikh   cenglert@schnabel-eng.com Sam.shaikh@fairfaxcounty.gov Qamar Kazmi Brendan Schillo   qkazmi@schnabel-eng.com Brendan.schillo@fairfaxcounty.gov Mohammad Nasim Ken Eyre   mnasim@schnabel-eng.com keyre@greeley-hansen.com Gary Ferrante  gferrante@greeley-hansen.com Ed Gerulat  egerulat@greeley-hansen.com

  40. Questions

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend