A Winding Road: Building a Sustainable Sanitary Sewer Stream - - PowerPoint PPT Presentation
A Winding Road: Building a Sustainable Sanitary Sewer Stream - - PowerPoint PPT Presentation
A Winding Road: Building a Sustainable Sanitary Sewer Stream Crossing in Emergency Conditions APWA Mid-Atlantic Conference Virginia Beach, VA May 10, 2013 Outline Background Site Conditions Immediate Response Temporary
Outline
Background Site Conditions Immediate Response Temporary Solution Permanent Solution Construction Questions
Background – Location
DC Fairfax County Alexandria
Tropical Storm Lee
DC Fairfax County Alexandria
Tropical Storm Lee
The Holmes Run Crossing saw 8-10
inches of rain
Parts of Fairfax County received over
5 inches of rain in 5 hours
Rainfall equated to 500-1000 year
storms in parts of Fairfax County
Outline
Background Site Conditions Immediate Response Temporary Solution Permanent Solution Construction Questions
Before Lee
Neighboring Utility Sewer Fairfax County Sewer
After Lee
Neighboring Utility Sewer Fairfax County Sewer Damaged Sewer
Site Conditions (After Lee)
County 36” Encased Concrete Sewer Concrete Dam with Z-pile Low Flow weir Cut into Dam Weir Apron
Apron Void
Causes for Damaged Pipe
Large high intensity flows in Holmes
Run
Scour caused by high flows Earthquake?
Outline
Background Site Conditions Immediate Response Temporary Solution Permanent Solution Construction Questions
Immediate Response
By pass pumping in place within 48
hours of discovery of the break
Emergency Contractors Adjustment of weir boards in an
upstream flow structure
Working with neighboring agencies to
coordinate pumps and response
Pumps
Silent pumps to limit disturbance to surrounding
community
24 pump monitoring to prevent overflows High Cost
Outline
Background Site Conditions Immediate Response Temporary Solution Permanent Solution Construction Questions
Temporary Solution
On land connection to the adjacent
trunk sewer
The connection is suitable dry
weather and smaller wet weather storms
Allowed for time to design a long term
solution
Connection to Adjacent Sewer
Neighboring Utility Sewer Fairfax County Sewer New Sewer Damaged Sewer
Temporary Structure Features
Canal Gate Pipe Slope
Outline
Background Site Conditions Immediate Response Temporary Solution Permanent Solution Construction Questions
Permanent Solution
Drop Manhole Micropiles Structural Steel Protecto 401 Stream Bank Protection Stream Restoration
Neighboring Utility Sewer Fairfax County Sewer New Sewer New Manhole
Permanent Crossing Overview
Drop Manhole
Lowers the elevation of
the pipe in the stream
Allows for better pipe
protection and armoring
Micropiles
14 micropiles in 7 pairs Core reinforcement,
steel casing, grout
Drilled into
disintegrated rock
Drilled and not driven to
protect the weir and stream
Structural Steel
Gussett Plate Lacing Transversal beam Longitudinal Beams Cradle Stiffener Plate Bents
Pipe and Protecto 401
36” Diameter Ductile Iron Pipe Protecto 401 Liner Selected
Stream Bank Restoration
Coir Block Soil Lifts at Construction entrances
Stream Restoration
Upstream and Downstream of the Weir Apron Reinforced Bed Mixture Stream Base Fill Imbricated Rock
Stream Restoration - Downstream
Low Flow Weir Cut Out
Outline
Background Site Conditions Immediate Response Temporary Solution Permanent Solution Construction Questions
Construction
PortaDam Goose
Porta Dam
Porta Dam
Porta Dam
Dry Site
Dry Site
Goose on Site
Outline
Background Site Conditions Immediate Response Temporary Solution Permanent Solution Construction Questions
Acknowledgements
Jonathan Okafor Jonathan.okafor@fairfaxcounty.gov
Thomas J. Russell Thomas.russell@fairfaxcounty.gov
Sam Shaikh Sam.shaikh@fairfaxcounty.gov
Brendan Schillo Brendan.schillo@fairfaxcounty.gov
Ken Eyre keyre@greeley-hansen.com
Gary Ferrante gferrante@greeley-hansen.com
Ed Gerulat egerulat@greeley-hansen.com
Mike Pekkala
mpekkala@greeley-hansen.com
Clyde Wilber cw@clydewilberllc.com
Carlos Englert cenglert@schnabel-eng.com
Qamar Kazmi qkazmi@schnabel-eng.com
Mohammad Nasim mnasim@schnabel-eng.com