A Winding Road: Building a Sustainable Sanitary Sewer Stream - - PowerPoint PPT Presentation

a winding road building a
SMART_READER_LITE
LIVE PREVIEW

A Winding Road: Building a Sustainable Sanitary Sewer Stream - - PowerPoint PPT Presentation

A Winding Road: Building a Sustainable Sanitary Sewer Stream Crossing in Emergency Conditions APWA Mid-Atlantic Conference Virginia Beach, VA May 10, 2013 Outline Background Site Conditions Immediate Response Temporary


slide-1
SLIDE 1

A Winding Road: Building a Sustainable Sanitary Sewer Stream Crossing in Emergency Conditions

APWA Mid-Atlantic Conference Virginia Beach, VA May 10, 2013

slide-2
SLIDE 2

Outline

 Background  Site Conditions  Immediate Response  Temporary Solution  Permanent Solution  Construction  Questions

slide-3
SLIDE 3

Background – Location

DC Fairfax County Alexandria

slide-4
SLIDE 4

Tropical Storm Lee

DC Fairfax County Alexandria

slide-5
SLIDE 5

Tropical Storm Lee

The Holmes Run Crossing saw 8-10

inches of rain

Parts of Fairfax County received over

5 inches of rain in 5 hours

Rainfall equated to 500-1000 year

storms in parts of Fairfax County

slide-6
SLIDE 6

Outline

 Background  Site Conditions  Immediate Response  Temporary Solution  Permanent Solution  Construction  Questions

slide-7
SLIDE 7

Before Lee

Neighboring Utility Sewer Fairfax County Sewer

slide-8
SLIDE 8

After Lee

Neighboring Utility Sewer Fairfax County Sewer Damaged Sewer

slide-9
SLIDE 9

Site Conditions (After Lee)

County 36” Encased Concrete Sewer Concrete Dam with Z-pile Low Flow weir Cut into Dam Weir Apron

slide-10
SLIDE 10

Apron Void

slide-11
SLIDE 11

Causes for Damaged Pipe

Large high intensity flows in Holmes

Run

Scour caused by high flows  Earthquake?

slide-12
SLIDE 12

Outline

 Background  Site Conditions  Immediate Response  Temporary Solution  Permanent Solution  Construction  Questions

slide-13
SLIDE 13

Immediate Response

By pass pumping in place within 48

hours of discovery of the break

Emergency Contractors  Adjustment of weir boards in an

upstream flow structure

 Working with neighboring agencies to

coordinate pumps and response

slide-14
SLIDE 14

Pumps

 Silent pumps to limit disturbance to surrounding

community

 24 pump monitoring to prevent overflows  High Cost

slide-15
SLIDE 15

Outline

 Background  Site Conditions  Immediate Response  Temporary Solution  Permanent Solution  Construction  Questions

slide-16
SLIDE 16

Temporary Solution

On land connection to the adjacent

trunk sewer

The connection is suitable dry

weather and smaller wet weather storms

 Allowed for time to design a long term

solution

slide-17
SLIDE 17

Connection to Adjacent Sewer

Neighboring Utility Sewer Fairfax County Sewer New Sewer Damaged Sewer

slide-18
SLIDE 18

Temporary Structure Features

Canal Gate  Pipe Slope

slide-19
SLIDE 19

Outline

 Background  Site Conditions  Immediate Response  Temporary Solution  Permanent Solution  Construction  Questions

slide-20
SLIDE 20

Permanent Solution

Drop Manhole  Micropiles Structural Steel  Protecto 401  Stream Bank Protection  Stream Restoration

slide-21
SLIDE 21

Neighboring Utility Sewer Fairfax County Sewer New Sewer New Manhole

Permanent Crossing Overview

slide-22
SLIDE 22

Drop Manhole

 Lowers the elevation of

the pipe in the stream

 Allows for better pipe

protection and armoring

slide-23
SLIDE 23

Micropiles

 14 micropiles in 7 pairs  Core reinforcement,

steel casing, grout

 Drilled into

disintegrated rock

 Drilled and not driven to

protect the weir and stream

slide-24
SLIDE 24

Structural Steel

 Gussett Plate  Lacing  Transversal beam  Longitudinal Beams  Cradle Stiffener Plate  Bents

slide-25
SLIDE 25

Pipe and Protecto 401

36” Diameter Ductile Iron Pipe  Protecto 401 Liner Selected

slide-26
SLIDE 26

Stream Bank Restoration

 Coir Block Soil Lifts at Construction entrances

slide-27
SLIDE 27

Stream Restoration

 Upstream and Downstream of the Weir Apron  Reinforced Bed Mixture  Stream Base Fill  Imbricated Rock

slide-28
SLIDE 28

Stream Restoration - Downstream

slide-29
SLIDE 29

Low Flow Weir Cut Out

slide-30
SLIDE 30

Outline

 Background  Site Conditions  Immediate Response  Temporary Solution  Permanent Solution  Construction  Questions

slide-31
SLIDE 31

Construction

PortaDam  Goose

slide-32
SLIDE 32

Porta Dam

slide-33
SLIDE 33

Porta Dam

slide-34
SLIDE 34

Porta Dam

slide-35
SLIDE 35

Dry Site

slide-36
SLIDE 36

Dry Site

slide-37
SLIDE 37

Goose on Site

slide-38
SLIDE 38

Outline

 Background  Site Conditions  Immediate Response  Temporary Solution  Permanent Solution  Construction  Questions

slide-39
SLIDE 39

Acknowledgements

Jonathan Okafor Jonathan.okafor@fairfaxcounty.gov

Thomas J. Russell Thomas.russell@fairfaxcounty.gov

Sam Shaikh Sam.shaikh@fairfaxcounty.gov

Brendan Schillo Brendan.schillo@fairfaxcounty.gov

Ken Eyre keyre@greeley-hansen.com

Gary Ferrante gferrante@greeley-hansen.com

Ed Gerulat egerulat@greeley-hansen.com

Mike Pekkala

mpekkala@greeley-hansen.com

Clyde Wilber cw@clydewilberllc.com

Carlos Englert cenglert@schnabel-eng.com

Qamar Kazmi qkazmi@schnabel-eng.com

Mohammad Nasim mnasim@schnabel-eng.com

slide-40
SLIDE 40

Questions