A Site Analysis Site Conditions: Seismic Challenges Strong - - PowerPoint PPT Presentation

a site analysis
SMART_READER_LITE
LIVE PREVIEW

A Site Analysis Site Conditions: Seismic Challenges Strong - - PowerPoint PPT Presentation

A Site Analysis Site Conditions: Seismic Challenges Strong Winds Average Temperature 69 San Francisco A Site Analysis A Engineering School of San Francisco Requirements 2015 Innovative Design Gold LEED


slide-1
SLIDE 1
slide-2
SLIDE 2

Site Analysis A

Site Conditions:

  • Seismic Challenges
  • Strong Winds
  • Average Temperature 69’

San Francisco

slide-3
SLIDE 3

Site Analysis A

slide-4
SLIDE 4
  • 2015 Innovative Design
  • Gold LEED Certification
  • Introduce Cloud Computing

[eliminates server rooms]

  • Target Value Design:

Biomimicry, Sustainability, Efficiency and Life Cycle Cost Engineering School of San Francisco Requirements A

slide-5
SLIDE 5

Concept 1: Exoskeleton

  • Coral reefs have an exterior structure or exoskeleton with an interior

core

[Exo]-Skeleton

slide-6
SLIDE 6

First Floor Plan A

[Exo]-Skeleton

slide-7
SLIDE 7

Second Floor Plan A

[Exo]-Skeleton

slide-8
SLIDE 8

Third Floor Plan A

[Exo]-Skeleton

slide-9
SLIDE 9

East-West Section A

[Exo]-Skeleton

slide-10
SLIDE 10

Auditorium + Main Entrance Section A

[Exo]-Skeleton

slide-11
SLIDE 11

Main Entrance [Public Connection] A

[Exo]-Skeleton

slide-12
SLIDE 12

Concept 1 E

16’ 13’ 12’

[Exo]-Skeleton

slide-13
SLIDE 13

Design Loads & Soil Profile E

 GRAVITY LOADS  Soil Conditions  3500psf bearing capacity Water table 14ft below grade  SEISMIC LOADS (governs over wind loads)  Base Shear = 500 kips  Site Class D Floor Dead Loads Live Loads First 75 psf 80 psf Second 75 psf 80 psf Third 67 psf 100 psf

[Exo]-Skeleton

slide-14
SLIDE 14

20’ 20’ 12’

Steel Solution – Typical Member Sizes – First Floor Plan E

 Typical Beam: W12x16  Typical Girder: W16x26  Gravity Columns (not touching Lateral system): HSS8x8x3/8  ConXtech Moment Connections  3” composite Steel Deck with Concrete Fill

[Exo]-Skeleton

slide-15
SLIDE 15

ConX System E

[Exo]-Skeleton

slide-16
SLIDE 16

Steel Solution – Lateral System sizes – First Floor Plan E

 Lateral System  Red: BRBF  Maximum 3 in2 braces  Columns: HSS8x8x1/2  Max beam: W18x65  Teal: SMF  Max Beam: W30x116  Columns: HSS16x16x5/8 (with concrete fill)

[Exo]-Skeleton

slide-17
SLIDE 17

Auditorium E

 Simple W-sections not cost efficient (52’ span)  Truss built from HSS6x6x1/2 sections  Pin Connected to prevent moment in column  Allows for MEP space in trusses

52’

[Exo]-Skeleton

slide-18
SLIDE 18

Curved Column Cantilevers E

 Architectural feature  Truss built from HSS6x6x1/2 sections  Placed on opposite sides – self-supported

78’ 66’ 52’ 4’ 13’ 7’

[Exo]-Skeleton

slide-19
SLIDE 19

Concrete Solution– Typical Member Sizes – First Floor Plan E

 Typical Beam: 18” x 12”

 4 # 8 Rebar

 Typical Girder: 18” x 12”

 4 #8 Rebar

 Gravity Columns (not touching Lateral system): 12” x 12”

 6 #8 Rebar

 8” Post-Tensioned Two-Way Concrete Slab

20’ 12’ 20’ 10’ 52’ 20’ 20’ 12’

[Exo]-Skeleton

slide-20
SLIDE 20

Concrete Solution– Typical Member Sizes – Second Floor Plan E

  • Typ. Beam: 16” x 12”

 4 # 7 Rebar

 Typ.Girder: 16” x 12”

 4 #8 Rebar

7’ Inward offset 7’ Outward Cantilever

 Auditorium (52’) Pre-Stressed Girder 40” x 16” Harped Tendon 12” Eccentricity 18 -1/2” Tendons 20’ 12’ 20’ 10’ 52’ 20’ 20’ 12’

[Exo]-Skeleton

slide-21
SLIDE 21

Concrete Solution– Typical Member Sizes – Third Floor Plan E

  • Typ. Beam: 18” x 12”

 4 # 8 Rebar

  • Typ. Girder: 18” x 12”

 4 #8 Rebar

7’ Inward offset 13’ Outward Cantilever

 Alternative Option: ….(Integration) Steel HSS Trusses 13’ 12’ 20’ 20’ 20’ 12’ 10’

[Exo]-Skeleton

slide-22
SLIDE 22

Concrete Solution – Lateral System E

 Lateral System  Red: Shear Walls  Minimum Thickness: 8”  Teal: SMF  Preliminary Beam: 18” x 22”  Columns: 22” x 22”  Blue: 1st Floor Floor SMF  Height = 16’

[Exo]-Skeleton

slide-23
SLIDE 23

Foundations E

 Isolated Footing  18” Thickness  #8 Rebar at 4.5” center-to-center  Mat Foundation  Ease of Construction  Reduce Formwork

Alternatives

[Exo]-Skeleton

slide-24
SLIDE 24

Gravity Load Path E

[Exo]-Skeleton

slide-25
SLIDE 25

Lateral Load Path E

[Exo]-Skeleton

slide-26
SLIDE 26

Concept 2: Gateway

[Gateway]

slide-27
SLIDE 27

Social Connection A

[Gateway]

slide-28
SLIDE 28

First Floor Plan A

[Gateway]

slide-29
SLIDE 29

Second Floor Plan A

[Gateway]

slide-30
SLIDE 30

Third Floor Plan A

[Gateway]

slide-31
SLIDE 31

Atrium + Entrance Section A

[Gateway]

slide-32
SLIDE 32

Auditorium + Entrance Section A

[Gateway]

slide-33
SLIDE 33

Main Entrance [Public Connection] A

[Gateway]

slide-34
SLIDE 34

Concept 2 E

16’ 13’ 12’

[Gateway]

slide-35
SLIDE 35

Steel Solution – Typical Member Sizes – First Floor Plan E

 Typical Beam: W14x22  Typical Girder: W18x35  Gravity Columns (not touching Lateral system): HSS8x8x1/2  ConXtech Moment Connections  3” composite Steel Deck with Concrete Fill

24.5’ 13.5’

12.75

25.25’ 14.25’ 23.75’ 17.5’ 19’ 29’ 24.5’

[Gateway]

slide-36
SLIDE 36

Steel Solution – Lateral System sizes – First Floor Plan E

 Lateral System  Symmetry to minimize torsion  SMF  Max Beam: W30x116  Columns: HSS16x16x5/8 (with concrete fill)  All connections are moment connections

24.5’ 13.5’

12.75

25.25’ 19’ 29’ 24.5’

[Gateway]

slide-37
SLIDE 37

Cantilever Solution - Steel E

 Truss Beams: W18x35  Truss Columns: HSS 16x16x5/8 (Uses moment frame columns)  Truss Diagonals: HSS 6x6x1/2  Takes advantage of large columns to transfer load to it

[Gateway]

slide-38
SLIDE 38

Gravity Load Path E

[Gateway]

slide-39
SLIDE 39

Gravity Load Path E

[Gateway]

slide-40
SLIDE 40

Concrete Solution– Typical Member Sizes E

 Typical Beam: 20” x 12”

 6 # 8 Rebar

 Typical Girder: 22” x 16”

 6 #8 Rebar

 Gravity Columns: 14” x 14”

 6 #8 Rebar

 8” Post-Tensioned Two-Way Concrete Slab

24.25’ 25’ 13’ 13.5’ 19’ 29’

[Gateway]

slide-41
SLIDE 41

Concrete Solution – Auditorium and Cantilevers E

10’ Cantilever 14’ Cantilever

 Auditorium Beams: (62’)  Pre-Stressed

 48” x 24”  Harped Tendon  15” Eccentricity  30 -1/2” Tendons

Largest Cantilever

  • 19’

 Post-Tensioning for Cantilevered Sections

14.25’ 23.75’ 17.5’ 24.25’ 25’ 13’ 13.5’ 19’ 29’

[Gateway]

slide-42
SLIDE 42

Concrete Solution – Lateral System sizes – First Floor Plan E

 Lateral System  Symmetry to minimize torsion  SMF  Preliminary Beam: 20” x 24”  Columns: 24” x 24”

[Gateway]

slide-43
SLIDE 43

Foundations E

 Isolated Footing  18” Thickness  #8 Rebar at 4.5” center-to-center  Strip Footing  Along Exterior  Spread Footing  For Interior

Alternatives

[Gateway]

slide-44
SLIDE 44

Advantages and Disadvantages E

Steel Advantages Concrete Advantages  Simplified Moment Connections (ConXtech)  Allows for open floor plans  Faster erection time  Simple transition/connection into truss members  Allows for trusses to be erected for cantilevered areas  Slightly cheaper Material  Ease of connecting angular members

[Gateway]

slide-45
SLIDE 45

Site Plan - Excavation C

[Exo]-Skeleton

slide-46
SLIDE 46

Site Conditions C

Site Section View

[General]

slide-47
SLIDE 47

Site Plan – Crane Placement C

Crane has required swing of 125’

[Exo]-Skeleton

slide-48
SLIDE 48

Site Plan – Concrete Pump Truck Placement C

Pump Truck swing 100’

[Exo]-Skeleton

slide-49
SLIDE 49

Site Plan – Excavation C

[Gateway]

slide-50
SLIDE 50

Site Plan – Crane C

Crane has required swing of 125’

[Gateway]

slide-51
SLIDE 51

Site Plan – Concrete Pump Truck C

Pump Truck swing 100’

[Gateway]

slide-52
SLIDE 52

Equipment C

Tower Crane Excavators Dumper

 Weight 12 sh.tn  Bucket 3,3 yd³

Tower Crane or Mobile crane Excavators Wheel loaders Dumper

 Capacity 26 sh.tn  Bucket 16,9 yd³

  • Max. peak load

3 sh.tn  Radius 90-125 foot

 Weight 33 sh.tn  Bucket 2,2 yd³

  • Max. peak load

3,1 sh.tn  Radius 0-210 foot

[General]

slide-53
SLIDE 53

Site Access C

Traffic Pedestrian Critical spots

[General]

slide-54
SLIDE 54

Risks C  Construction

 Keep time for superstructure  Safety on site  Ground water level  Utilities (location and depth)

[General]

slide-55
SLIDE 55

Schedule Skeleton in Concrete C

[Exo]-Skeleton

slide-56
SLIDE 56

Schedule Skeleton in Steel C

[Exo]-Skeleton

slide-57
SLIDE 57

Schedule Gateway in Concrete C

[Gateway]

slide-58
SLIDE 58

Schedule Gateway in Steel C

[Gateway]

slide-59
SLIDE 59

Estimation C

[General]

slide-60
SLIDE 60

Estimation – Target Value C

CI, FC Included CI, FC Separate

$8,500,000 (with contingency)

[General]

slide-61
SLIDE 61

Estimation – Steel Frame C

Target Value Skeleton: $8.42 million Gateway: $8.41 million

[General]

slide-62
SLIDE 62

Estimation – Cast-In Place C

Target Value Skeleton: $8.18 million Gateway: $8.18 million

[General]

slide-63
SLIDE 63

Estimation - Precast C

Target Value Skeleton: $8.41 million Gateway: $8.40 million

[General]

slide-64
SLIDE 64

Cost Comparison C

[General]

slide-65
SLIDE 65

Cost Comparison – Future Costs C

[General]

slide-66
SLIDE 66

Component Comparison – Structural Columns C

Cast-In Place Concrete-filled Steel Wide Flange Precast

M: 15.02 M: 47.68 M: 63.93 M: 148.01 I: 61.20 I: 8.36 I: 8.36 I: 11.54 Total: $76.22/lin. Ft. Total: $56.04/lin. Ft. Total: $72.29/lin. Ft Total: 159.55/lin. Ft.

[General]

slide-67
SLIDE 67

Component Comparison – Exterior Walls C

Cast-In Place Precast (8’x20’) Precast (8’x8’) Tilt-up Stucco (Metal Studs) M: 5.39 M: 25.05 M: 44.28 M: 6.83 M: 2.77 I: 17.64 I: 4.75 I: 4.57 I: 7.56 I: 10.72 T: 23.03/sf T: 29.79/sf T: 48.81/sf T: 14.39/sf T: 13.50/sf

Skeleton Savings Gateway Savings Tilt-Up Cost = $200,000 Tilt-Up Cost = $197,000 Stucco Cost = $188,000 Stucco Cost = $185,000 Savings= $12,000

[General]

slide-68
SLIDE 68

Spring Quarter Considerations C

Benefits over Conventional Steel

  • Significant time gain
  • Less field labor/no welding
  • Lower cost
  • Safer work environment
  • Better Seismic performance
  • Faster inspection

Benefits over Concrete

  • Lower cost
  • Faster construction
  • Significantly lower CO2
  • Lighter

[General]

slide-69
SLIDE 69

Team Process - Communication

slide-70
SLIDE 70

Team Process - Production

slide-71
SLIDE 71

Team Process

Feedback from E, CM Feedback from peers, mentors

[Exo]-Skeleton

slide-72
SLIDE 72

Decision Matrix

 Innovative Design (WOW! Factor)  Functionality/Efficiency  Sustainability

slide-73
SLIDE 73

Decision Matrix

slide-74
SLIDE 74

Pacific Team 2012 Presents…

slide-75
SLIDE 75

Pacific Team 2012

Special Thanks to:  MENTORS: Greg Luth Tim Schrotenboer David Bendet John Nelson  OWNERS: Michael Seaman Maria Selk Renate Fruchter