A CASE FOR ENERGY STORAGE IN KENYA PRESENTATION BY KENYA POWER ROLE - - PowerPoint PPT Presentation

a case for energy storage in kenya
SMART_READER_LITE
LIVE PREVIEW

A CASE FOR ENERGY STORAGE IN KENYA PRESENTATION BY KENYA POWER ROLE - - PowerPoint PPT Presentation

ENERGY STORAGE WORKSHOP SAFARI PARK HOTEL, NAIROBI 24-25 MAY 2018 A CASE FOR ENERGY STORAGE IN KENYA PRESENTATION BY KENYA POWER ROLE OF KPLC Purchasing System Op Operator, bulk el bu electricity Di Dispatch fu function & sup


slide-1
SLIDE 1

PRESENTATION BY KENYA POWER ENERGY STORAGE WORKSHOP

SAFARI PARK HOTEL, NAIROBI 24-25 MAY 2018

A CASE FOR ENERGY STORAGE IN KENYA

slide-2
SLIDE 2

ROLE OF KPLC

Purchasing bu bulk el electricity sup supply (Sin (Single le Buy Buyer) Bu Build ilding an and mai aintaining a a rob

  • bust

po power ne netw twork System Op Operator, Di Dispatch fu function & Retailer of

  • f El

Electric icity Cu Customer Ser Service

slide-3
SLIDE 3

3

Key stakeholder in:

  • Demand forecasting
  • Generation planning
  • Transmission planning
  • Transmission planning

Procuring generation capacity:

  • Negotiate PPAs
  • Facilitate project development
  • Facilitate operation of IPPs

ROLE OF KPLC

slide-4
SLIDE 4

GENERATION CAPACITY AND ENERGY MIX

  • Geothermal currently provides about 47% of energy requirements.
  • Over 75% of country’s energy is supplied from renewable energy sources.
  • The installed capacity and generation mix contribution from wind and solar

expected to grow from ongoing and planned projects.

19% 34% 16% 3% 11% 10% 8%

Projected Installed Capacity Mix 2023

Hydro Geothermal Wind Biomass Solar Thermal Import 35.41% 47.80% 15.49% 0.01% 0.36% 0.00% 0.93%

Generation mix- April 2018

Hydro Geothermal Diesel Biomass Wind Solar Imports

Generation Capacity

slide-5
SLIDE 5

PEAK DEMAND AND LOAD CURVE

  • Current Peak demand is 1,770MW

recorded on 17th January, 2018

  • Projected demand growth rate of

between 6% and 10%

1,609 1,618 1,636 1,640 1,650 1,665 1,710 1,727 1,754 1,770

1,768

1,540 1,560 1,580 1,600 1,620 1,640 1,660 1,680 1,700 1,720 1,740 1,760 1,780 1,800

Peak Demand (MW)

200 400 600 800 1000 1200 1400 1600 1800 Load, MW Time, Hr

  • Peak demand falls between 6.00pm

and 10.00pm

  • Off-peak

period is between 12.00am to 05.00 am

slide-6
SLIDE 6

ISSUES TO CONSIDER IN THE STUDY

  • Situation analysis -circumstances
  • Sizing of storage
  • Cost of storage and benefits compared to other options
  • Comparison with other technologies –GTs, pumped storage
  • Location of storage in the network
  • Functionality –primary or secondary reserves?
  • Best practices
slide-7
SLIDE 7

RE & SYSTEM PLANNING CONSIDERATIONS

  • Integration of intermittent renewable energy and characteristics- solar, wind
  • LTWP requirements –single largest wind power plant
  • Regulation/ load following capacity
  • Flexible generation plant – storage

capability

  • Fast ramping capability
  • Low capital cost – lower utilization

requirements

  • Hydro, Gas turbines
  • Peaking capacity
  • Fast start-up and shut down
  • Low capital cost
  • High variable cost
  • Thermal (MSD), Gas turbines
  • Operating reserve capacity
  • Primary reserve
  • Secondary reserve
  • Tertiary reserve
  • Base load capacity
  • Low or no variable cost
  • High capital/ fixed cost
  • Geothermal, coal, hydro, non-

conventional renewable energy plant - solar, wind, biogas etc.

slide-8
SLIDE 8
  • Power system stability
  • Frequency stability
  • Load / generation imbalance
  • Frequency variation
  • Transient stability
  • Reduced system inertia (displacement of

conventional plant)

  • RE plants affected by system disturbances

(disconnect during faults and voltage dips)

  • Increased possibility of cascade of outages

& loss of synchronism during system disturbances

8

RE GRID INTEGRATION CHALLENGES

slide-9
SLIDE 9

ENERGY STORAGE PROJECT GOALS

Provide Spinning Reserve to the system Supply Power during Peak Load To mitigate curtailment of RES production curtailments when production is high. Reduce Transmission System Congestion where there are constraints Stabilization of energy injection profiles .i,e wind gusts, for output stabilization.

slide-10
SLIDE 10

SUCCESS INDICATORS FOR ENERGY STORAGE

  • A more stable system which survives large

disturbances (loss of generators and loads)

  • Reduced load shedding –have sufficient capacity

at peak

  • Reduced fuel consumption -running less thermal

power plants during peak

  • Reduced load shedding –less transmission system

constraints

  • Reduced system losses
slide-11
SLIDE 11

Thank you