7. Construction progress
Works this month
- Works in Paddington Lane to relocate services as they are clashing with retaining wall footing. Traffic
control is in place to ensure safety and authorised access is by permit
- Bulk earthworks excavation in the north and eastern parts of the site including compacting and filling. Any
dust generation is managed by water cart.
- Two piling rigs have commenced works this month near the NRL building. Vibration monitors have been
set up to monitor any vibration in accordance with management plans.
- Intra-respite periods have not been required to date as no works have triggered the respite requirements
- f exceeding 75dBA. This is not expected to be triggered in the coming month.
Works ahead
- With piling activities commencing, work will progress south, to be followed by pouring the concrete slab-
- n-ground structure within the stadium footprint.
- Bulk earthworks are estimated to continue until September 2020.