4D Planning

Contemporary Schedule Change Impact Visualisation

time for complex project success

slide-2
SLIDE 2

 Celestino Moreno Fernández  Ingeniero de Caminos, Canales y Puertos (Civil Engineer)  Masters Degree in Management, Purification and treatment of water  Consultant Kingsfield Consulting  Experience in international engineering and construction projects  Areas of particular interest –new technologies applied to project management

Introducing ourselves

slide-3
SLIDE 3

 How can we visualize our project status? (4D planning)  What can 4D do for you?  4D Planning functions  4D Contemporary Change Visualisation  4D Project Controls & Risk Visualisation Reports

Our aims for this presentation

slide-4
SLIDE 4

learn consult plan

How Can Visualise

  • ur Project Status?

BIM – 4D

slide-5
SLIDE 5

BIM and its tool to visualise our Project Status

 BIM is a working Process, a methodology with different levels of collaboration  4D Planning is a software used to implement BIM with a Level 2 collaboration level

slide-6
SLIDE 6

learn consult plan

What is 4D Planning?

slide-7
SLIDE 7

Integration of Schedule with 3D CAD Model

slide-8
SLIDE 8

Integration of Schedule with 3D CAD Model

Primavera Schedule

4D Model

3D CAD Model

Clear Communication

  • f

Schedule Risk

Versions Updates Progress Additions / Deletions Versions Updates

slide-9
SLIDE 9
slide-10
SLIDE 10
slide-11
SLIDE 11
slide-12
SLIDE 12

learn consult plan

What can 4D do for you?

slide-13
SLIDE 13
  • Visualise build sequences
  • Anticipate interfaces and conflicts of resources and

equipment

  • Rehearse optimal installation sequences
  • Integrated 4D Project Controls
  • Visualise the impact of change
  • Management of Project Risk and Change Through

Advanced Forensic Animation

  • Illustrate your claims, reports…

HOW CAN 4D DO THIS FOR YOU?

What can 4D do for you?

slide-14
SLIDE 14

Bring Your Schedule to LIFE…

slide-15
SLIDE 15

Two Dimensional Project Schedules….

slide-16
SLIDE 16

Visualise Your Project Schedule Performance…

slide-17
SLIDE 17

Planned Actual Critical Delay Disruption Resource deployment Risk Opportunity

slide-18
SLIDE 18

Communicate Project Schedules Easily to Your Project Teams

slide-19
SLIDE 19
slide-20
SLIDE 20

Visualise Key Areas

  • f Project Delay and

Disruption

slide-21
SLIDE 21

Delay Disruption

slide-22
SLIDE 22

Align Project Control tools to the Schedule and Maximise Performance

slide-23
SLIDE 23

Schedule Budget Resources Productivity

slide-24
SLIDE 24

learn consult plan

4D Planning Functions

slide-25
SLIDE 25

Isolating Areas of Work

slide-26
SLIDE 26

Navigation & Functionality in the Same Detail as 3D Model

slide-27
SLIDE 27

Select and Locate Activities and 3D Objects

slide-28
SLIDE 28

Planned v Actual Status

slide-29
SLIDE 29

Planned v Actual Status (Piping)

slide-30
SLIDE 30

Critical Areas of Pipework

slide-31
SLIDE 31

Critical Areas of Pipework Isolated

slide-32
SLIDE 32

Actual Progress Indicators

slide-33
SLIDE 33

Heat Map for Resources

slide-34
SLIDE 34

Heat Map for Resources

slide-35
SLIDE 35

learn consult plan

4D Contemporary Change Visualisation

slide-36
SLIDE 36

Change Scenario

 Delay in

subcontractor’s civil works

 Subcontractor

alleged delayed delivery of drawings and work stopped during this time

 Claim for delay and

additional costs

slide-37
SLIDE 37

Contractor Alleges Delay Because of Late Foundations Drawings Issue

Planned Actual

Project Number Contact Reporting Date:

Description Weight 0% 10% 30% 40% 20%

Civil PPPP Civil 100.000% FFFF Civil AAAA General 0.16719644 PPP General 16.720% FFF General 0.16719644 AAA SHOP TANKS 4.196% P 2-Mar-16 22-Mar-16 1-Apr-16 1-May-16 1-Jun-16 Preliminary Loads 4.196% F SHOP TANKS A AIR COOLER 8.264% P 28-Mar-16 6-May-16 26-May-16 25-Jul-16 23-Sep-16 Piping General Documentation 8.264% F AIR COOLER A AIR COOLER 4.259% P 28-Mar-16 17-Apr-16 27-Apr-16 28-May-16 28-Jun-16 Piping Class IFD 4.259% F AIR COOLER A LAYOUT 0.216147489 PPP LAYOUT 21.615% FFF LAYOUT 0.216147489 AAA SHOP TANKS 9.536% P 28-Mar-16 13-May-16 5-Jun-16 13-Aug-16 21-Oct-16 Foundations Arexxx 9.536% F SHOP TANKS A AIR COOLER 0.826% P 28-Mar-16 31-Mar-16 2-Apr-16 7-Apr-16 13-Apr-16 Foundations Arexxx 0.826% F AIR COOLER A AIR COOLER 11.252% P 24-Oct-16 17-Dec-16 14-Jan-17 6-Apr-17 27-Jun-17 Foundations Arexxx 11.252% F AIR COOLER A SHOP VESSELS 0.000% P 0-Jan-00 30-Dec-25 30-Dec-38 30-Dec-77 30-Dec-16 Foundations Arexxx 0.000% F SHOP VESSELS
  • A
SHOP STRAINERS 0.000% P 0-Jan-00 24-Feb-26 24-Mar-39 16-Jun-78 8-Sep-17 Foundations Arexxx 0.000% F SHOP STRAINERS
  • A
SHOP STRAINERS 0.000% P 0-Jan-00 30-Mar-26 15-May-39 27-Sep-78 9-Feb-18 Foundations Arexxx 0.000% F SHOP STRAINERS
  • A
START DRAFT IFR IFD IFC
slide-38
SLIDE 38

Foundation Drawings Isolated From the Model

slide-39
SLIDE 39

Engineering Status (Week 20)

Engineering Planned Engineering Actual

slide-40
SLIDE 40

Construction Status (Week 20)

Construction Planned Construction Actual

slide-41
SLIDE 41
  • Eng. vs Const. Actual Status (week 20)

Engineering Actual Construction Actual

slide-42
SLIDE 42

Change of sequence Status (week 20)

Engineering Actual Construction Actual Construction Alternative Sequence

slide-43
SLIDE 43

Change of sequence (week 33)

Engineering Actual Construction Actual Construction Alternative Sequence

slide-44
SLIDE 44

Change of sequence (week 41)

Engineering Completed Construction Actual Construction Alternative Sequence

slide-45
SLIDE 45

Change of sequence (week 41)

Planned Construction Actual Construction Construction Alternative Sequence

slide-46
SLIDE 46

Change of sequence (week 54 – Planned Completion Date)

Planned Construction Actual Construction NO DELAY! Construction Alternative Sequence

slide-47
SLIDE 47

learn consult plan

4D Project Controls & Risk Visualisation Reports

slide-48
SLIDE 48

Project Level Report

slide-49
SLIDE 49

Summary: From 2D Schedules to 3D Animation

slide-50
SLIDE 50
  • Visualise build sequences
  • Anticipate interfaces and

conflicts of resources and equipment

  • Rehearse optimal installation

sequences

  • Integrated 4D Project Controls
  • Visualise the impact of change
  • Management of Project Risk

and Change Through Advanced Forensic Animation

  • Illustrate your claims, reports…

Summary