40 megawatt distributed generation contracts program
play

40 Megawatt Distributed Generation Contracts Program Results & - PowerPoint PPT Presentation

40 Megawatt Distributed Generation Contracts Program Results & Next Steps Office of Energy Resources August 20, 2012 2011 and 2012 Results 5 megawatts allocated in December 2011. 5 megawatts allocated in April 2012. 5


  1. 40 Megawatt Distributed Generation Contracts Program – Results & Next Steps Office of Energy Resources August 20, 2012

  2. 2011 and 2012 Results  5 megawatts allocated in December 2011.  5 megawatts allocated in April 2012.  5 megawatts allocated in July 2012. Notifications of applicants selected will occur soon.  Additional megawatts will be allocated in October.  Through the first three rounds of the DGC program, a total of 38.88 megawatts of applications have been received.

  3. Approved 2011 and 2012 Ceiling Prices Target Capacity Ceiling Price Class Nameplate for Class (cents/kWh) PV (10-150 kW) 0.5 MW 33.35 PV (151-500 kW) 1.0 MW 31.60 PV (501-5000 kW) 2.0 MW 28.95 Wind (1.5 MW) 1.5 MW 13.35

  4. First 2 Rounds of the DGC Program  6 projects awarded contracts from the first two rounds. Projects included:  1.5 MW wind turbine project in North Kingstown.  500 kilowatt solar project in Middletown.  1 MW solar project in Westerly (Municipal).  2 MW solar project in West Greenwich.  2.34 MW solar project in North Kingstown.  3.71 MW solar project in East Providence (Municipal).

  5. DGC Ceiling Prices for Projects Approved  0.1335 cents per kWh for Wind  0.316 cents per kWh for Medium Solar  0.265 cents per kWh for Large Solar  0.265 cents per kWh for Large Solar  0.23699 cents per kWh for Large Solar  0.239 cents per kWh for Large Solar

  6. Solar Ceiling Prices 0.35 0.3 h W 0.25 r k 0.2 Solar Ceiling e p Prices 0.15 e ric 0.1 P 0.05 0 1 2 3 4 5 Applications These are the prices through the first two rounds of the DGC program. Only 1 wind turbine project has been submitted for a DGC contract in the first three rounds of the program.

  7. Next Steps  The 2013 DGC program will allocate 10 megawatts for renewable energy projects.  There will be three standard contract enrollments during the program year.  Any adjustments in the ceiling prices or megawatt carve outs need to be submitted to the Public Utility Commission by October 15 th .

  8. Comments/Questions

  9. Contact Information Chris Kearns Programming Services Officer christopher.kearns@energy.ri.gov 401-574-9113

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.