SLIDE 1 2017 SPLOST TRANSPORTATION IMPROVEMENT PROGRAM CITIZENS PROJECT SELECTION COMMITTEE AGENDA APRIL 13, 2017
I. Welcome and Introductions II. Approval of Agenda III. Approval of Minutes – March 15, 2017
V. Old Business
- A. Approval of Project Category – Major Roads
- VI. New Business
- A. Presentation of Project Category –Pedestrian Safety
- B. Next Meeting Dates
- VII. Public Comment
- VIII. Adjourn
SLIDE 2 TRANSPORTATION DEPARTMENT
CPSC Meeting April 13, 2017
SLIDE 3 Agenda
- Welcome and Opening Remarks
- Public Comment
- Old Business
- Follow-up and vote on previous category – Major Roads
- New Business
- Presentation of Pedestrian Safety category
- Discussion of Future Meeting Schedule
- Public Comment
- Adjourn
SLIDE 4
SLIDE 5
SLIDE 6
SLIDE 7
SLIDE 8
SLIDE 9
SLIDE 10
Major Roads
* Cost estimate based on preliminary engineering documents ** Cost estimate based on planning level concepts
SR 316 / University Parkway Corridor Improvements Georgia DOT / Gwinnett County Partnership Agreement
SR 316 at Hi-Hope / Progress Center ** SR 316 at Hurricane Trail ** SR 316 at US 29 ** SR 316 at Harbins Road * Total
Gwinnett County $4 million $60 million $64 million Georgia DOT $75 million $40 million $57 million $172 million Total $75 million $40 million $61 million $60 million $236 million
SLIDE 11
Major Roads
SLIDE 12
Major Roads
SLIDE 13
Major Roads
SR 316 / University Parkway at US 29 / SR 8 / Winder Highway
SLIDE 14
Major Roads
SR 316 / University Parkway at Harbins Road
SLIDE 15 Major Roads
Sugarloaf Parkway Extension Phase II
- Improved mobility / cross county connectivity
- Limited access
- Diversion of traffic from other arterials
SLIDE 16 Major Roads
Sugarloaf Parkway Extension Phase II
Open to traffic ADT 73,600 Design year ADT 107,450 (20 years after
SLIDE 17
Major Roads
Project Engineering Right of Way Total Cost
Sugarloaf Parkway, Phase 2A (SR 316 to SR 124) $5,000,000 $22,000,000 $27,000,000 Sugarloaf Parkway, Phase 2B (SR 124 to I-85) $5,500,000 $13,000,000 $18,500,000 Total $10,500,000 $35,000,000 $45,500,000*
* $15.5 million budgeted in 2014 SPLOST
SLIDE 18 Major Roads
I-85 North Widening: Hamilton Mill Road to SR 211 This project would consist of:
- Widening I-85 from Hamilton Mill Road to SR 211 and
addition of one general purpose lane in each direction
- The length of widening is approximately 6.2 miles
within Gwinnett and Barrow counties
- The project also proposes a striping modification of the
14’ Express Lanes buffer to accommodate the third general purpose lane between I-985 to Hamilton Mill Road I-85 North Widening: SR 211 to US 129 This project would consist of:
- Widening I-85 from SR 211 to US 129
- One additional general purpose lane in each direction.
- The length of widening is approximately 10.5 miles
within Barrow and Jackson counties
SLIDE 19 Major Roads
Revive 285, Express Lanes from I-75 to I-85 The project would consist of the construction of two Express Lanes in each direction, on the outside of the existing general purpose travel lanes, with operational improvements and Collector-Distributor (CD) systems at various locations along I-285. Specific operational and CD system improvements currently being considered for the project include:
- One I-285 westbound auxiliary lane between Roswell
Road and Riverside Drive
- I-75 North/I-285 interchange improvements
- I-85 North/I-285 interchange improvements
- I-285 CD lanes from Ashford-Dunwoody Road to SR
141/Peachtree Industrial Boulevard
- I-285 CD lanes from US 23/Buford Highway to I-85
- The Express Lanes will directly connect to Express
Lanes on I-75, I-85 and SR 400
SLIDE 20
Major Roads
Spalding Drive (SR 140 / Holcomb Bridge Road to Winters Chapel Road)
SLIDE 21
Major Roads
Venture Drive from Pleasant Hill Road to Steve Reynolds Boulevard
SLIDE 22
Major Roads
SR 124 / Braselton Highway from Pine Road to County Line
SLIDE 23
Major Roads
Cruse Road (Club Drive to Paden Drive)
SLIDE 24
Major Roads
Killian Hill Road from Church Street to Arcado Road
SLIDE 25
Major Roads
Peachtree Industrial Boulevard (northbound) (Holcomb Bridge Road to Medlock Bridge Road)
SLIDE 26
Major Roads
Pleasant Hill Road
SLIDE 27
Major Roads
Pleasant Hill Road (Howell Ferry Road to Chattahoochee River)
SLIDE 28
Major Roads
SR 124 / Scenic Highway widening from US 78 / SR 10 / West Main Street to Sugarloaf Parkway
SLIDE 29
Major Roads
SR 20 / Buford Drive widening from US 23 / SR 13 / Buford Highway to Peachtree Industrial Boulevard
SLIDE 30
Major Roads
SLIDE 31
Major Roads
Pleasant Hill Road on-ramp at I-85
SLIDE 32
Major Roads
Sugarloaf Parkway from Meadow Church Road to Satellite Boulevard
SLIDE 33
SLIDE 34
SLIDE 35
CPSC Recommendations
SLIDE 36
Request approval of Major Roads Project List
CPSC Recommendations
SLIDE 37 Pedestrian Safety
Sources for Pedestrian Safety Improvements
- City / CID requests
- County staff identified
- Unfunded 2014 SPLOST projects
- Citizen Requests
- Comprehensive Transportation Plan
- Countywide Trails Master Plan
SLIDE 38 Pedestrian Safety
Types of Pedestrian Safety Improvements
- Engineered Sidewalks
- In-house, Gap and Rehabilitation Sidewalks
- Pedestrian Crossings
- Pedestrian Facilities at Intersections
- Multi-use Paths
- Sidewalk Lighting
SLIDE 39 Pedestrian Safety
Design considerations on pedestrian safety projects
- Curb and gutter, grading, drainage, utility relocations, retaining
walls, handrail, right-of-way and easement acquisitions, etc.
- ADA compliance considerations – ramps, cross slope, truncated
domes, etc.
- Pedestrian crossings at intersections – raised islands, countdown
pedestrian signal heads, crosswalks, etc.
- Mid-block pedestrian crossings
- Rectangular Rapid Flashing Beacons (RRFB)
- High-intensity Activated crossWalK beacon (HAWK)
SLIDE 40
Project Name Estimated Cost Future Trails Master Plan Projects $1,500,000 Gap / In House / Rehabilitation $500,000 Infinite Loop $500,000 Mall Boulevard $500,000 McDaniel Farm Park Connector $1,500,000 Norcross to Lilburn Trail $500,000 Pedestrian Crossings $500,000 Street lighting for pedestrians $500,000 Western Gwinnett Bikeway $1,500,000
Pedestrian Safety
SLIDE 41
Pedestrian Safety
Draft Signature Trails Plan of the Countywide Trails Master Plan
SLIDE 42
Pedestrian Safety
SLIDE 43
Pedestrian Safety
SLIDE 44
Pedestrian Safety
Mall Boulevard Complete Street
SLIDE 45
Pedestrian Safety
McDaniel Farm Park Connector
SLIDE 46
Pedestrian Safety
Norcross to Lilburn Trail
SLIDE 47
Pedestrian Safety
Pedestrian crossings and street lighting for pedestrians
SLIDE 48
Pedestrian Safety
Western Gwinnett Bikeway McGinnis Ferry Road Multi-Use Path
SLIDE 49 Sweetwater Road (before and after) North Berkeley Lake Road (before and after)
Pedestrian Safety
SLIDE 50 Pedestrian Safety
CRITERIA POINT SCORE Connectivity (to existing
Connected at Both Ends Connected at One End No Connection 10 5
Worn Path
Well Worn Some Evidence No Evidence 10 5 Proximity to Pedestrian Destinations within ¼ mile within ½ mile > ½ mile
School
10 5
Library
10 5
Park
10 5
Shopping
10 5
Length * (Feet)
< 3,000’ 3,001’ – 6,000’ 6,001’ – 9,000’ 10 5 9,001’ – 12,000’ 12,001 or greater
SLIDE 51
SLIDE 52
SLIDE 53
SLIDE 54
SLIDE 55
SLIDE 56
SLIDE 57
SLIDE 58
SLIDE 59
SLIDE 60
SLIDE 61
SLIDE 62 Next Steps
- Provide any questions or concerns to GCDOT by
April 26, 2017
- Request approval of Pedestrian Safety category at the
meeting on May 3, 2017
SLIDE 63 CPSC Meeting Schedule
Next Meeting (May 3, 2017) (DOT Central)
- Committee vote on Sidewalks and Pedestrian Safety
- Presentation on County / City Joint Projects
Following Meeting (May 18, 2017)
- Committee vote on final recommendations
SLIDE 64
TRANSPORTATION DEPARTMENT
Public Comment