2012 to Present: 2013 2012 Causes of the Failure 3 GROUND WATER - - PowerPoint PPT Presentation

2012 to present
SMART_READER_LITE
LIVE PREVIEW

2012 to Present: 2013 2012 Causes of the Failure 3 GROUND WATER - - PowerPoint PPT Presentation

2012 to Present: 2013 2012 Causes of the Failure 3 GROUND WATER 1 GEOLOGY 2 GEOMETRY Weak soil Steep slope High water table due to increased precipitation 1 GEOLOGY Causes of the Failure: 2 GEOMETRY 11 th St 3 GROUND WATER


slide-1
SLIDE 1
slide-2
SLIDE 2

2012 to Present:

2013 2012

slide-3
SLIDE 3

Causes of the Failure

1 GEOLOGY 2 GEOMETRY 3 GROUND WATER

Weak soil Steep slope High water table due to increased precipitation

slide-4
SLIDE 4
slide-5
SLIDE 5

Causes of the Failure:

SLIP PLANE

1 GEOLOGY 2 GEOMETRY 3 GROUND WATER

GROUND WATER LEVEL

11th St Cherry Lane Sask Cres

slide-6
SLIDE 6

10 Year Average Rainfall - Saskatoon

slide-7
SLIDE 7

Groundwater Levels - Saskatoon

slide-8
SLIDE 8

Status of Slope

Movement Possible

  • Not stable
  • Continued movement toward Sask Cres
slide-9
SLIDE 9

Remediation Options

  • Conceptual only
  • Target: 50% MORE stabilizing force
  • 4 general options evaluated

No Movement

slide-10
SLIDE 10

Option 1

  • Do Nothing
  • Continued movement
  • Risk increases as groundwater increases
  • Slide area will expand in time
slide-11
SLIDE 11

Option 2

  • Address
  • Install dewatering trenches (11th St & Cherry Lane)

3

GROUND WATER

slide-12
SLIDE 12

SLIP PLANE GROUND WATER LEVEL GROUND WATER LEVEL

Option 2

slide-13
SLIDE 13

Option 2

  • Address
  • Install dewatering trenches (11th St & Cherry Lane)
  • Doesn’t meet stability target (only 20%)

3

GROUND WATER

slide-14
SLIDE 14

Option 3:

  • Address AND
  • Flatten the slope
  • Meets 50% stability target

3 GROUND WATER 2 GEOMETRY

FORCES PULLING SLOPE DOWN FORCES HOLDING SLOPE UP

slide-15
SLIDE 15

GROUND WATER LEVEL SLIP PLANE

Option 3:

slide-16
SLIDE 16

Possible Remediation OPTION 3 Affected area

slide-17
SLIDE 17

Option 3:

  • Address AND
  • Flatten the slope
  • Meets 50% stability target
  • Significant disruption to private lots

3 GROUND WATER 2 GEOMETRY

FORCES PULLING SLOPE DOWN FORCES HOLDING SLOPE UP

slide-18
SLIDE 18

Option 4:

  • Address AND
  • “Shear zone replacement”
  • Meets 50% stability target
  • Keeps houses in place

3 GROUND WATER 1 GEOLOGY

FORCES PULLING SLOPE DOWN FORCES HOLDING SLOPE UP

slide-19
SLIDE 19

Option 4:

slide-20
SLIDE 20

Possible Remediation OPTION 4 Affected area

slide-21
SLIDE 21

Possible Remediation OPTION 4:

  • Address AND
  • “Shear zone modification”
  • Meets 50% stability target
  • Keeps houses in place

3 GROUND WATER 1 GEOLOGY

FORCES PULLING SLOPE DOWN FORCES HOLDING SLOPE UP

Option 4:

slide-22
SLIDE 22

Remediation Summary:

OPTION PROS CONS ESTIMATED COST

1) Do Nothing

  • No cost
  • HIGH risk of

continued failure

$0 2) Lower Water Table

  • Minimal

disturbance

  • Lowers “wet year”

risk

  • Does not meet target

stability

$4.5M 3) Re-Grade Slope

(and lower water table)

  • Meets stability

target

  • Reduced long term

risk

  • Significant disruption
  • Removal of structures

$6.5 – 10M 4) Shear Zone Modification

(and lower water table)

  • Meets stability

target

  • Maintains

structures

  • Difficult to construct
  • Costly

$10 – 20M

slide-23
SLIDE 23

Independent Review:

Clifton Associates

  • Independent analysis of the data
  • Purpose: To confirm remediation options
  • Conclusions:
  • Agree on methodology
  • Differing interpretation of data  even less stable
  • Remediation options feasible but may be even more costly

Verified  the problem is large and costly to resolve

slide-24
SLIDE 24

Public Safety

Continues to be primary focus of the

  • Continue detailed monitoring
  • Provide residents with everything we know
  • Evacuation Alert
slide-25
SLIDE 25