2008 NYISO COMPREHENSIVE RELIABILITY PLAN
NPCC Governmental/Regulatory Affairs Advisory Group Saratoga Springs, NY September 23, 2008
John P. Buechler
NYISO Executive Regulatory Policy Advisor
2008 NYISO COMPREHENSIVE RELIABILITY PLAN John P. Buechler NYISO - - PowerPoint PPT Presentation
2008 NYISO COMPREHENSIVE RELIABILITY PLAN John P. Buechler NYISO Executive Regulatory Policy Advisor NPCC Governmental/Regulatory Affairs Advisory Group Saratoga Springs, NY September 23, 2008 NYISO NYISO s s NYISO NYISO
NPCC Governmental/Regulatory Affairs Advisory Group Saratoga Springs, NY September 23, 2008
John P. Buechler
NYISO Executive Regulatory Policy Advisor
2
3
be added
applicable criteria
Demand-Side)
whether they meet identified needs
the event market-based solutions not forthcoming)
Requests for Solutions
(Market-based & Regulatory)
Comprehensive Reliability Plan (CRP) Reliability Needs Assessment (RNA)
4
Board Approval of Plan Market-Based Responses
Regulated Responses
NYISO Formulates Comprehensive Reliability Plan (CRP) NYISO to Publicize Reliability Needs Assessment NYISO Performs Reliability Needs Assessment (RNA) NYISO Evaluates Market-Based Responses, Regulated Responses and TO Updates To Determine Whether They Will Meet the Identified Reliability Needs NYISO Issues Request for Solutions “Gap” Solutions by TOs
No viable/timely market or regulated solution to an identified need
Board Approval of Plan
5
6
The Comprehensive
The NYISO Board of
7
be needed over the 10-year study period in order for the New York Control Area (NYCA) to comply with all applicable reliability criteria.
based and regulated solutions to the reliability needs identified in the RNA.
solutions, together with implementation of Transmission Owner planned upgrades to the bulk power system, meet or exceed reliability requirements through 2017.
regulated backstop solution or a alternative regulated solution to address the reliability needs.
8
affect the plan, including:
facilities,
impact of the forward capacity markets in those regions,
environmental factors,
its planned auctions of emission allowances, and
State’s Energy Efficiency Portfolio Standard (EEPS) .
9
10
A C E F I J H B D G K
Empire Generation Project
(Zone F - 635 MW)
Gas Turbine NRG Astoria Repowering
(Zone J - 520 MW)
Simple Cycle GT Indian Point
(Zone H - 300 MW)
Combined Cycle Bergen
(Zone J - 550 MW)
Demand-Side Management
(Special Case Resources)
300 MW -- Zones F,G,H,I, and J 125 MW -- Zones G,H, and J
Transmission
PJM – Zone J
Controllable AC Transmission –VFT Linden VFT (300 MW) Back-to-Back HVDC, AC Line HTP (660 MW) Back-to-Back HVDC, AC Line Harbor Cable (550 MW)
11
500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Planning Horizon Year MW Market Solutions Cumulative Need
12
rather than Zone G.
submitted Individually
13
CRP 2008 NYCA Resources As Percent of NYCA Peak Load With TO Updated Plans, Responsible TO Backstop Solutions of 2,350 MW, and Poletti in Service in 2009 Current Installed Capacity Requirement is 115%
60.00% 67.25% 74.50% 81.75% 89.00% 96.25% 103.50% 110.75% 118.00% 125.25% 132.50% 139.75% 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Planning Horizon Year Resource Margin as a % of the Peak Load External Resource of 3280 Regulated Back Stop Special Case Resources NYCA Generating Capacity
14
1200 MW 500kv DC line from Edic to Rock Tavern
New 540 MW CC plant at existing Lovett Station
15
16
which include transmission upgrades, such as the addition of capacitor banks at the Millwood Substation and the installation of the Con Edison M29 project.
resources from the 3,380 MW of merchant generation and transmission projects that have been proposed for New York.
17
18
NYISO will continue to track progress – quarterly
monitoring
Con Edison M29 transmission project, capacitor banks
at Millwood substation, firm capacity in conjunction with UDRs, planned non-bulk power system projects
All planned generator additions are natural gas
19
Northeast Coordinated System Plan to address
resource adequacy on a regional basis
e.g., long term contracts, forward capacity markets,
new capacity zone in lower Hudson Valley
Forward Capacity Market development discussions
NYISO to continue studies of potential impacts in 2009
RNA
20
The New York Independent System Operator (NYISO) is a not The New York Independent System Operator (NYISO) is a not-
for-
profit corporation that began operations in 1999. The NYISO operates ates New York New York’ ’s bulk electricity grid, administers the state s bulk electricity grid, administers the state’ ’s wholesale s wholesale electricity markets, and performs comprehensive reliability plan electricity markets, and performs comprehensive reliability planning for ning for the state the state’ ’s bulk electricity system. s bulk electricity system.
__________________________________________________________ __________________________________________________________