200 kton Water Cherenkov Detector Liner F Feyzi F. Feyzi ANT11 - - PowerPoint PPT Presentation

200 kton water cherenkov detector liner
SMART_READER_LITE
LIVE PREVIEW

200 kton Water Cherenkov Detector Liner F Feyzi F. Feyzi ANT11 - - PowerPoint PPT Presentation

200 kton Water Cherenkov Detector Liner F Feyzi F. Feyzi ANT11 11 October, 2011 Outline Outline Water containment for 200 kton Reasons and background for choices g Interface to other subsystems What have we learned from firms


slide-1
SLIDE 1

200 kton Water Cherenkov Detector Liner

F Feyzi

  • F. Feyzi

ANT11 11 October, 2011

slide-2
SLIDE 2

Outline Outline

  • Water containment for 200 kton
  • Reasons and background for choices

g

  • Interface to other subsystems
  • What have we learned from firms

What have we learned from firms

  • Material considerations

11 October 2011

  • F. Feyzi ANT11

2

slide-3
SLIDE 3

200 kton cavern

  • Located at 4850 ft

level

  • One cavern only

near Yates Shaft

  • Remove rock at

bottom (5117 ft level) to Ross Shaft

  • Access for detector

k t 4850 l work at 4850 only

11 October 2011 3

  • F. Feyzi ANT11
slide-4
SLIDE 4

Definition Definition

  • Vessel is the structural components to resist

water load and support detector components

  • Liner is the water proofing and leak collection

components p Both are needed and integrated

11 October 2011 4

  • F. Feyzi ANT11
slide-5
SLIDE 5

Size Comparison p and Liners

SNO Super-K 4mm SS liner on 350mm i f d t d H 7mm sprayed liner on 300mm shotcrete reinforced concrete and H- beam vessel WCD 100 WCD-200 2 5 mm sheet WCD-100 1.5 mm sheet liner

  • n 350mm

reinforced concrete vessel 2.5 mm sheet liner on 300 mm shotcrete

11 October 2011 5

  • F. Feyzi ANT11
slide-6
SLIDE 6

200 kton Parameters

Physics Physics Volume 200k m3 Sensitive Volume 240k

3

240k m3

11 October 2011 6

  • F. Feyzi ANT11
slide-7
SLIDE 7

General Scope of Liner General Scope of Liner

  • Scope of responsibility:

– On wall is from neat line to water – On floor is from slab to water – Interface and sealing to deck Interface and sealing to deck – Interface to PMT supports

  • Extent of supply:

– Full design of liner – Recommendation of materials (selection is LBNE responsibility) p y) – Construction and installation of liner – QA and leak check – Installation of magnetic compensation coils

11 October 2011 7

  • F. Feyzi ANT11
slide-8
SLIDE 8

Status of Liner Design g

  • 100 kton Conceptual Design with many options was

d b CNA/HHM/SGH (D Db 3150) done by CNA/HHM/SGH (DocDb 3150)

  • 100 kton was evaluated with liner on shotcrete vs liner
  • n concrete vessel
  • n concrete vessel
  • Cost and schedule estimates and peer review done
  • 200 kton cost was scaled from 100 kton
  • 200 kton was re-evaluated as part of conventional

p facilities contract

  • RFI for design and construction 200kton send to

companies responses received companies-responses received

11 October 2011 8

  • F. Feyzi ANT11
slide-9
SLIDE 9

Options Studied

Free Standing Integrated with Rock Pressure Balanced

11 October 2011 9

  • F. Feyzi ANT11
slide-10
SLIDE 10

Free Standing Options

  • Concrete option 1A

– Less costly Walls thicker

  • Steel Option 1B

– Most robust but costliest C t l l i – Walls thicker – Can use metal or polymeric liner – Can use metal or polymeric liner – Magnetic issues more l complex

Not feasible for 200 kton

11 October 2011 10

  • F. Feyzi ANT11
slide-11
SLIDE 11

PMT Supports

St l ith

  • Strong vessel with

steel or concrete allows attachment directly to wall directly to wall

  • Smooth and flat

wall allows good iti position

  • This was our

baseline support design for a steel

  • r concrete vessel

11 October 2011 11

  • F. Feyzi ANT11
slide-12
SLIDE 12

Rock Integrated Options

  • Integrated option 2A

– 35 cm reinforced concrete vessel – Can resist external pressure – Mount PMTs directly to wall

CNA Engineers

11 October 2011 12

  • F. Feyzi ANT11
slide-13
SLIDE 13

Rock Integrated Options

I t t d ti

  • Integrated option

2C

– Liner directly on shotcrete Liner directly on shotcrete – Cavern design team has determined rock motions are very small so this is feasible

CNA Engineers

11 October 2011 13

  • F. Feyzi ANT11
slide-14
SLIDE 14

Wall PMT Deployment

  • T. Benson, P. Robl, PSL

11 October 2011 14

  • F. Feyzi ANT11
slide-15
SLIDE 15

Linear PMT Supports pp

  • Use wire rope

p support for PMT assemblies

  • All wall PMTs
  • All wall PMTs

deployed from deck

  • No attachments and

penetrations on the penetrations on the wall

  • Will require

extensive testing

  • T. Benson, P. Robl, PSL

11 October 2011 15

  • F. Feyzi ANT11
slide-16
SLIDE 16

Wall Liner Construction

  • Concrete vessel in not base option due to cost
  • Shotcrete, ground support and drainage applied to rock
  • Magnetic compensation coils installed

Additi l h t t t th d il

  • Additional shotcrete to smooth and cover coils

– Probably need smoothness about 1 in 10 to15 – One supplier says waviness should not exceed 5 cm

  • Penetrations installed at appropriate time
  • Detector drainage layer installed

Sh li i ll d d ld d

  • Sheet liner installed and welded
  • Leak check

11 October 2011 16

  • F. Feyzi ANT11
slide-17
SLIDE 17

Liner Welding and Leak Check g

  • Liner material will come in large rolls and will be

welded in place

  • Fusion and extrusion weld will both be used

Seams will have an overlap with two fusion welds will

  • Seams will have an overlap with two fusion welds, will

allow for air pressure test of space between welds

  • Fusion welds will mostly be used for attachment points
  • Extrusion welds will be used at penetrations
  • Leak checking by spark method used on liner
  • Other methods may also used (vacuum box, gas, etc.)
  • Conductive liner will facilitate this

11 October 2011 17

  • F. Feyzi ANT11
slide-18
SLIDE 18

Liner Material Choices

  • Baseline:
  • J. Youngblood, & B. Ward

– Liner: 2.5 mm conductive LLDPE Geomembrane – Drainage layer: 8 mm Geocomposite (Geonet)

  • Alternate:

– Liner: 1.5 mm conductive LLDPE Geomembrane

Gundle/SLT Environmental, Inc.

– Drainage layer: Restricted Flow GCL or none

Geosynthetic Clay Liners (GCL's) are composites that combine geotextile outer layers with a core g y

  • f low-permeability sodium

bentonite clay.

11 October 2011 18

  • F. Feyzi ANT11
slide-19
SLIDE 19

Drainage System Drainage System

Separate drainage layers for ground water and

  • Separate drainage layers for ground water and

detector leak water

  • Separate collection, they may or may not be combined

in the sump

  • Static pressure rating and longevity must be sufficient
  • Pressure must not build on liner when detector is
  • Pressure must not build on liner when detector is

empty

  • Sedimentation in drainage layer should also be

i considered

11 October 2011 19

  • F. Feyzi ANT11
slide-20
SLIDE 20

No Drainage Layer Concept And Possibly “Zero Leak” And Possibly Zero Leak

Mi i i ff t f

  • Minimize effects of

leaks by not allowing free flow D t ll t h t

  • Do not collect whatever

does leak

  • Let combine with

d t ll ti groundwater collection

Golder Assoc.

11 October 2011 20

  • F. Feyzi ANT11
slide-21
SLIDE 21

Variations on Rock Integrated Options Options

  • Option A
  • Option B
  • Slip formed concrete under

Option A

– GCL directly under liner – No leak collection O l d t

  • Slip-formed concrete under

liner

  • No leak collection

C t t lik GCL – Only ground water collection

  • Concrete act like GCL ( ? by Farshid)

Golder Assoc.

11 October 2011 21

  • F. Feyzi ANT11
slide-22
SLIDE 22

Estimating L k R t Leak Rates

  • Leakage is, of course,

dependent on size and dependent on size and quantities of defects

  • Must minimize quantity of

penetration

  • 5 defects per hectare is an

achievable number

  • Leak rate will be specified

as a design parameter

Fill rate is about 1m3 per minute

11 October 2011 22

  • F. Feyzi ANT11
slide-23
SLIDE 23

“Leak Free” Design

  • Leak free: It leaks but collect all

leaks

  • This design utilizes a double

lined system to collect all leaks from primary liner from primary liner

  • It is used in hazardous liner

applications and is a well known technology technology

  • This method would be

advantageous in the case we use Gd to allow for full collection and recapture

  • Cost and schedule is the major

j issue with this option

11 October 2011 23

  • F. Feyzi ANT11
slide-24
SLIDE 24

Baseline design design

R 32.5 M min min NOT TO SCALE

11 October 2011 24

  • F. Feyzi ANT11
slide-25
SLIDE 25

Magnetic Compensation Magnetic Compensation

  • Horizontal and

vertical coils

  • Power supplies
  • n deck
  • Passive system

also under evaluation

11 October 2011 25

  • F. Feyzi ANT11
slide-26
SLIDE 26

Wall-Floor Interface (one ibili ) possibility)

R 32.5 M min R 31.65 M NOT TO SCALE 11 October 2011 26

  • F. Feyzi ANT11
slide-27
SLIDE 27

Liner Material Considerations

  • The material of the liner must be compatible

with ultra high purity water for up to 30 years with ultra-high purity water for up to 30 years.

  • LBNE collaboration is responsible for test and

l ti f li t i l f th selection of liner material from those recommended by contractor.

  • Tests have shown that various grades of

commonly used polyethylene sheet liners materials are acceptable.

  • Tests on cold-fluid applied liners have shown

that they do not perform as well and may not b t bl be acceptable.

11 October 2011 27

  • F. Feyzi ANT11
slide-28
SLIDE 28

Close to 50 samples for the liner materials tested

Liner Material Testing

Carlisle coating butyl (PSL VL 008)

Cooley Group RPP‐7845 JWPW05 (PSL VL 001)

  • M. Yeh, S. Hans

11 October 2011 28

  • F. Feyzi ANT11
slide-29
SLIDE 29

List of Good Material

11 October 2011

  • F. Feyzi ANT11

29

  • M. Yeh, S. Hans
slide-30
SLIDE 30

Li e Liner Attachment

11 October 2011 30

  • F. Feyzi ANT11
slide-31
SLIDE 31

Schedule Optimization

  • Construction schedule for the vessel and liner is one of

the most critical components of the overall project

  • schedule. There are two basic approaches for vessel

construction:

– The entire cavern is excavated before the construction of the liner starts, Th t ti f th li i t i t i – The construction of the liner is concurrent, in part or in whole, with cavern excavation.

  • Evaluation of different construction concepts is in

p progress

  • Our baseline approach is for serial construction
  • So far, we have opinions on both sides as to feasibility

So far, we have opinions on both sides as to feasibility

  • f concurrent construction
  • Main issue is possible damage to liner during blasting
  • With 65 m diameter and spiral excavation this may be

With 65 m diameter and spiral excavation this may be possible

11 October 2011 31

  • F. Feyzi ANT11
slide-32
SLIDE 32

Good Things You Learn Good Things You Learn

GSI's Mission is to develop and transfer knowledge, assess and critique geosynthetics, and provide services to th b i ti the member organizations.

IAGI strives to provide a forum for geosynthetics installers t d i t ll ti d t ti t h i d t 11 October 2011

  • F. Feyzi ANT11

32 to advance installation and construction techniques, and to strengthen the knowledge, image and communication within the industry.

slide-33
SLIDE 33

Summary

  • Baseline design is polymeric sheet on smoothened shotcrete

g p y

  • Have cost estimates from two sources that are in reasonable

agreement

  • Alternate designs are under study
  • Alternate designs are under study
  • Developing test and prototype plans for liner and penetrations
  • Material testing is in progress
  • Leak rate estimates will allow us to specify realistic

construction and QA techniques

  • Studying methods of contracting, performance and warranty

Studying methods of contracting, performance and warranty

  • Developing list of vendors for design, manufacturing and

installation Near infinite experience for liners near surface and in nearly horizontal condition. Application to 65 m x 85 m cavern at 1500 m depth is the question. p q

11 October 2011 33

  • F. Feyzi ANT11
slide-34
SLIDE 34

Additional Slides Additional Slides

slide-35
SLIDE 35

Floor Construction Floor Construction

  • Static water load is 800 kN/m2 (16,300 lbs/sq ft)
  • Concentrated mast climber load is about 20 ton in 8 to
  • Concentrated mast climber load is about 20 ton in 8 to

10 spots

  • Liner and drainage layer static rating must be

sufficient

  • A protective layer over liner may be required
  • Penetrations are requited for attachment of PMTs

A l t i t f b t 0 5% i i d

  • A slope to perimeter of about 0.5% is required
  • Magnetic compensation coils are under floor slab, joint

is required to wall coils Thi k ll i 1 t t l f l b il

  • Thickness allowance is 1m total for slab, coils,

drainage and liner

  • Detector water distribution manifolds are above floor

and not in the slab and not in the slab

11 October 2011 35

  • F. Feyzi ANT11
slide-36
SLIDE 36

Mast Climber

11 October 2011 36

  • F. Feyzi ANT11
slide-37
SLIDE 37

PMT Deployment from Deck

  • J. Fowler, Duke Univ.

11 October 2011 37

  • F. Feyzi ANT11
slide-38
SLIDE 38

Polar Deck level 2 Open in front of entrance Detector Deck Polar Crane Open in front of entrance Gondola and perimeter hoist Deck level 1 More from J. Fowler

slide-39
SLIDE 39

Detector Deck

  • J. Fowler, Duke Univ.

11 October 2011 39

  • F. Feyzi ANT11
slide-40
SLIDE 40

Floor and Deck PMTs

P R bl

  • P. Robl

UW

11 October 2011 40

  • J. Thomson

UCD

  • F. Feyzi ANT11
slide-41
SLIDE 41

Free-Standing PMT Supports

  • Modular system

erected from floor

  • 2x 3 arrays of

2x 3 arrays of PMTS attach to structure This is not baseline

  • This is not baseline

due to cist

11 October 2011 41

  • F. Feyzi ANT11
slide-42
SLIDE 42

DayaBay DayaBay

  • Permaflex

(polyurethane) sprayed on

  • Wall moisture and

finish need good control

  • Test results show it is

not appropriate for LBNE

11 October 2011 42

  • F. Feyzi ANT11
slide-43
SLIDE 43

Ring truss and Wall PMTs

11 October 2011 43

  • F. Feyzi ANT11
slide-44
SLIDE 44

Typical Liner Penetration

11 October 2011 44

  • F. Feyzi ANT11