200 kton Water Cherenkov Detector Liner
F Feyzi
- F. Feyzi
200 kton Water Cherenkov Detector Liner F Feyzi F. Feyzi ANT11 - - PowerPoint PPT Presentation
200 kton Water Cherenkov Detector Liner F Feyzi F. Feyzi ANT11 11 October, 2011 Outline Outline Water containment for 200 kton Reasons and background for choices g Interface to other subsystems What have we learned from firms
11 October 2011
2
level
near Yates Shaft
bottom (5117 ft level) to Ross Shaft
k t 4850 l work at 4850 only
11 October 2011 3
11 October 2011 4
SNO Super-K 4mm SS liner on 350mm i f d t d H 7mm sprayed liner on 300mm shotcrete reinforced concrete and H- beam vessel WCD 100 WCD-200 2 5 mm sheet WCD-100 1.5 mm sheet liner
reinforced concrete vessel 2.5 mm sheet liner on 300 mm shotcrete
11 October 2011 5
Physics Physics Volume 200k m3 Sensitive Volume 240k
3
240k m3
11 October 2011 6
– On wall is from neat line to water – On floor is from slab to water – Interface and sealing to deck Interface and sealing to deck – Interface to PMT supports
– Full design of liner – Recommendation of materials (selection is LBNE responsibility) p y) – Construction and installation of liner – QA and leak check – Installation of magnetic compensation coils
11 October 2011 7
d b CNA/HHM/SGH (D Db 3150) done by CNA/HHM/SGH (DocDb 3150)
p facilities contract
companies responses received companies-responses received
11 October 2011 8
Free Standing Integrated with Rock Pressure Balanced
11 October 2011 9
– Less costly Walls thicker
– Most robust but costliest C t l l i – Walls thicker – Can use metal or polymeric liner – Can use metal or polymeric liner – Magnetic issues more l complex
Not feasible for 200 kton
11 October 2011 10
St l ith
steel or concrete allows attachment directly to wall directly to wall
wall allows good iti position
baseline support design for a steel
11 October 2011 11
– 35 cm reinforced concrete vessel – Can resist external pressure – Mount PMTs directly to wall
CNA Engineers
11 October 2011 12
– Liner directly on shotcrete Liner directly on shotcrete – Cavern design team has determined rock motions are very small so this is feasible
CNA Engineers
11 October 2011 13
11 October 2011 14
p support for PMT assemblies
deployed from deck
penetrations on the penetrations on the wall
extensive testing
11 October 2011 15
Additi l h t t t th d il
– Probably need smoothness about 1 in 10 to15 – One supplier says waviness should not exceed 5 cm
Sh li i ll d d ld d
11 October 2011 16
welded in place
Seams will have an overlap with two fusion welds will
allow for air pressure test of space between welds
11 October 2011 17
– Liner: 2.5 mm conductive LLDPE Geomembrane – Drainage layer: 8 mm Geocomposite (Geonet)
– Liner: 1.5 mm conductive LLDPE Geomembrane
Gundle/SLT Environmental, Inc.
– Drainage layer: Restricted Flow GCL or none
Geosynthetic Clay Liners (GCL's) are composites that combine geotextile outer layers with a core g y
bentonite clay.
11 October 2011 18
Separate drainage layers for ground water and
detector leak water
in the sump
empty
i considered
11 October 2011 19
Mi i i ff t f
leaks by not allowing free flow D t ll t h t
does leak
d t ll ti groundwater collection
Golder Assoc.
11 October 2011 20
– GCL directly under liner – No leak collection O l d t
liner
C t t lik GCL – Only ground water collection
Golder Assoc.
11 October 2011 21
dependent on size and dependent on size and quantities of defects
penetration
achievable number
as a design parameter
Fill rate is about 1m3 per minute
11 October 2011 22
leaks
lined system to collect all leaks from primary liner from primary liner
applications and is a well known technology technology
advantageous in the case we use Gd to allow for full collection and recapture
j issue with this option
11 October 2011 23
R 32.5 M min min NOT TO SCALE
11 October 2011 24
vertical coils
also under evaluation
11 October 2011 25
R 32.5 M min R 31.65 M NOT TO SCALE 11 October 2011 26
11 October 2011 27
Close to 50 samples for the liner materials tested
Liner Material Testing
Carlisle coating butyl (PSL VL 008)
Cooley Group RPP‐7845 JWPW05 (PSL VL 001)
11 October 2011 28
11 October 2011
29
11 October 2011 30
the most critical components of the overall project
construction:
– The entire cavern is excavated before the construction of the liner starts, Th t ti f th li i t i t i – The construction of the liner is concurrent, in part or in whole, with cavern excavation.
p progress
So far, we have opinions on both sides as to feasibility
With 65 m diameter and spiral excavation this may be possible
11 October 2011 31
GSI's Mission is to develop and transfer knowledge, assess and critique geosynthetics, and provide services to th b i ti the member organizations.
IAGI strives to provide a forum for geosynthetics installers t d i t ll ti d t ti t h i d t 11 October 2011
32 to advance installation and construction techniques, and to strengthen the knowledge, image and communication within the industry.
g p y
agreement
construction and QA techniques
Studying methods of contracting, performance and warranty
installation Near infinite experience for liners near surface and in nearly horizontal condition. Application to 65 m x 85 m cavern at 1500 m depth is the question. p q
11 October 2011 33
10 spots
sufficient
A l t i t f b t 0 5% i i d
is required to wall coils Thi k ll i 1 t t l f l b il
drainage and liner
and not in the slab and not in the slab
11 October 2011 35
11 October 2011 36
11 October 2011 37
Polar Deck level 2 Open in front of entrance Detector Deck Polar Crane Open in front of entrance Gondola and perimeter hoist Deck level 1 More from J. Fowler
11 October 2011 39
P R bl
UW
11 October 2011 40
UCD
erected from floor
2x 3 arrays of PMTS attach to structure This is not baseline
due to cist
11 October 2011 41
(polyurethane) sprayed on
finish need good control
not appropriate for LBNE
11 October 2011 42
11 October 2011 43
11 October 2011 44