20 th april 2011 presentation on greater karachi sewerage
play

20 th April 2011 Presentation On GREATER KARACHI SEWERAGE PLAN - PowerPoint PPT Presentation

20 th April 2011 Presentation On GREATER KARACHI SEWERAGE PLAN (S-III) KW&SB v Karachi with an estimated population of around 22 million is presently facing a severe environmental crisis due to discharge of untreated sewage through


  1. 20 th April 2011

  2. Presentation On GREATER KARACHI SEWERAGE PLAN (S-III) KW&SB

  3. v Karachi with an estimated population of around 22 million is presently facing a severe environmental crisis due to discharge of untreated sewage through natural streams / drains and rivers into the Sea. v Presently, 100% of the total municipal sewage generated is discharged untreated into the costal water of Karachi city. This had converted our coastal belt into a big CESSPOOL & besides difficulties in port operations it causes serious environmental hazards. 29th June 2015 2nd November 2012 KW&SB

  4. KARACHI THE LARGEST METROPOLIS OF PAKISTAN Disposal of Raw Sewage into Sea All the rain water natural streams (nullahs ) and drains are converted into open sewers. The major part of sea beach has become a large sewage pond with stinking odour and blackish color 29th June 2015 KW&SB 2nd November 2012

  5. Lyari River KW&SB

  6. Malir River KW&SB

  7. City Station Nullah KW&SB

  8. Mahmoodabad Drain KW&SB

  9. Current Status of Sewage Treatment in Karachi Total Sewage Generated 470 MGD Present Treatment Nil Direct Discharge into Sea 470 MGD Current Treatment Plant Original Capacity Treatment TP-I 51 MGD Nil TP- II 46 MGD Nil TP-III 54 MGD Nil 2nd November 2012 29th June 2015 KW&SB

  10. What is Required ? Ø Transmission of all Sewage to Treatment Plants for processing before its ultimate disposal into the sea. Ø Development of Treatment Facilities ~ 500 MGD (including 40 MGD Treatment Plant to be constructed by KPT at Mai Kolachi) KW&SB

  11. The Project S-III is geared towards improving environmental & sanitation conditions of Karachi through a well integrated system of collection, treatment and disposal of sewage. The major Works under S-III Consists of: Ø RCC Interceptor along Lyari River 33,320 M Ø RCC Interceptor along Malir River 22,741 M Ø Interconnection of Nullahs & Trunk Sewers Ø Rehabilitation and Enhancement of existing STP – I (100 MGD) & STP-III (180 MGD) Ø Construction of New STP – IV (180 MGD) at Korangi KW&SB

  12. Development Plan Development Plan of S-III Project may be broadly divided into following two components: Ø Sewage Transmission and Ø Sewage Treatment 29th June 2015 KW&SB

  13. A. Sewage Transmission System q Lyari River Interceptor (33,320 Meter) q Malir River Interceptor (22,741 Meter) 29th June 2015 KW&SB

  14. PROPOSED ROUTE MAP TP-I KW&SB

  15. PROPOSED ROUTE MAP TP-III KW&SB

  16. PROPOSED ROUTE MAP TP-IV

  17. B. Sewage Treatment Facilities Sewage Treatment Plant Existing Proposed Unit Treatment Plant 1, Haroonabad SITE 51 100 MGD Treatment Plant 2, Mehmoodabad Sewage 46 MGD Pumping Station Treatment Plant 3, Mauripur 54 180 MGD Treatment Plant 4, Korangi (NEW) - 180 MGD New Treatment Plant 5 at Mai Kolachi - 40 MGD (To be implemented by KPT) Total 151 500 MGD KW&SB 29th June 2015

  18. ADMINISTRATIVE APPROVALS PC-I of the Project was approved by ECNEC at a cost of Rs. 7,982 Million on September 19, 2007 on cost sharing of 50:50 between GoP and GoS. Modified PC-Is for Lyari & Malir River Basins has already been approved by PDWP for onward transmission to CDWP as per following details; Lyari River Basin: Rs. 21,356.788 Million Stage-I Rs. 13,771.768 Million Stage-II Rs. 7,585.020 Million Malir River Basin: Rs. 15,062.815 Million KW&SB 29th June 2015

  19. Implementation Plan of S-III Project S-III Project is planned to be implemented in following Phases: PHASE-I: LYARI RIVER BASIN (280 MGD) Phase-I is subdivided into two Stages: (a) Stage-1 (200 MGD): 1. Sewage Transmission from Gulshan-e-Yaseenabad to Mauripur 2. Complete Rehabilitation and Enhancement of TP-I 3. Rehabilitation of TP-III (b) Stage-2 (80 MGD): 1. Balance Sewage Transmission from Surjani to Gulshan-e-Yaseenabad 2. Enhancement of TP-III PHASE-II: MALIR RIVER BASIN (180 MGD) (a) Sewage Transmission from Quaidabad to TP-IV ( Korangi ) (b) Construction of New STP-IV at Korangi (c) Rising Main from TP-II KW&SB 29th June 2015

  20. CURRENT STATUS OF S-III PROJECT KW&SB 29th June 2015

  21. Design Phase of S-III Project has been completed and also vetted by WS Atkins (U.K). Execution of works of Sewage Transmission and Treatment in Lyari River Basin are in progress. KW&SB 29th June 2015

  22. Lean ¡Concrete Excava&on ¡for ¡River ¡Diversion PICTORIAL S-III PROJECT Base ¡Slab ¡Formwork ¡Fixing Conduit’s ¡Top ¡Slab ¡Concre&ng

  23. Installa&on ¡of ¡PVC ¡Liner ¡in ¡Progress Concre&ng ¡of ¡RCC ¡Conduit PICTORIAL S-III PROJECT RCC ¡Boundary ¡Wall ¡@ ¡TP-­‑III PVC ¡Lined ¡RCC ¡Conduit

  24. Ribs ¡Repairing ¡Works ¡@ ¡TP-­‑I Rehabilita&on ¡of ¡Sedimenta&on ¡Tanks ¡ PICTORIAL S-III PROJECT Sludge ¡removal ¡from ¡Anaerobic ¡Lagoon ¡ @ ¡TP-­‑III Dewatering ¡from ¡Inlet ¡Chamber ¡@ ¡TP-­‑III ¡

  25. Thank ¡You ¡ 29th June 2015 2nd November 2012 KW&SB

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend