20 th April 2011 Presentation On GREATER KARACHI SEWERAGE PLAN - - PowerPoint PPT Presentation

20 th april 2011 presentation on greater karachi sewerage
SMART_READER_LITE
LIVE PREVIEW

20 th April 2011 Presentation On GREATER KARACHI SEWERAGE PLAN - - PowerPoint PPT Presentation

20 th April 2011 Presentation On GREATER KARACHI SEWERAGE PLAN (S-III) KW&SB v Karachi with an estimated population of around 22 million is presently facing a severe environmental crisis due to discharge of untreated sewage through


slide-1
SLIDE 1

20th April 2011

slide-2
SLIDE 2

Presentation On GREATER KARACHI SEWERAGE PLAN (S-III)

KW&SB

slide-3
SLIDE 3

2nd November 2012 29th June 2015

v Karachi with an estimated population of

around 22 million is presently facing a severe environmental crisis due to discharge of untreated sewage through natural streams / drains and rivers into the Sea.

v Presently, 100% of the total municipal

sewage generated is discharged untreated into the costal water of Karachi city. This had converted our coastal belt into a big CESSPOOL & besides difficulties in port operations it causes serious environmental hazards.

KW&SB

slide-4
SLIDE 4

KARACHI

THE LARGEST METROPOLIS OF PAKISTAN

Disposal of Raw Sewage into Sea

All the rain water natural streams (nullahs ) and drains are converted into

  • pen sewers. The major part of sea beach has become a large sewage

pond with stinking odour and blackish color

2nd November 2012 29th June 2015 KW&SB

slide-5
SLIDE 5

Lyari River

KW&SB

slide-6
SLIDE 6

Malir River

KW&SB

slide-7
SLIDE 7

City Station Nullah

KW&SB

slide-8
SLIDE 8

Mahmoodabad Drain

KW&SB

slide-9
SLIDE 9

Current Status of Sewage Treatment in Karachi

Treatment Plant Original Capacity Current Treatment TP-I 51 MGD Nil TP- II 46 MGD Nil TP-III 54 MGD Nil

Total Sewage Generated 470 MGD Present Treatment Nil Direct Discharge into Sea 470 MGD

2nd November 2012 29th June 2015 KW&SB

slide-10
SLIDE 10

Ø Transmission of all Sewage to Treatment Plants for processing before its ultimate disposal into the sea. Ø Development of Treatment Facilities ~ 500 MGD (including 40 MGD Treatment Plant to be constructed by KPT at Mai Kolachi)

What is Required ?

KW&SB

slide-11
SLIDE 11

S-III is geared towards improving environmental & sanitation conditions of Karachi through a well integrated system of collection, treatment and disposal of sewage. The major Works under S-III Consists of: Ø RCC Interceptor along Lyari River 33,320 M Ø RCC Interceptor along Malir River 22,741 M Ø Interconnection of Nullahs & Trunk Sewers Ø Rehabilitation and Enhancement of existing STP – I (100 MGD) & STP-III (180 MGD) Ø Construction of New STP – IV (180 MGD) at Korangi

The Project

KW&SB

slide-12
SLIDE 12
slide-13
SLIDE 13

Development Plan of S-III Project may be broadly divided into following two components: Ø Sewage Transmission and Ø Sewage Treatment

Development Plan

29th June 2015 KW&SB

slide-14
SLIDE 14
  • A. Sewage Transmission System

q Lyari River Interceptor (33,320 Meter) q Malir River Interceptor (22,741 Meter)

29th June 2015 KW&SB

slide-15
SLIDE 15

PROPOSED ROUTE MAP TP-I

KW&SB

slide-16
SLIDE 16

PROPOSED ROUTE MAP TP-III

KW&SB

slide-17
SLIDE 17

PROPOSED ROUTE MAP TP-IV

slide-18
SLIDE 18

Sewage Treatment Plant Existing Proposed Unit Treatment Plant 1, Haroonabad SITE 51 100 MGD Treatment Plant 2, Mehmoodabad 46

Sewage Pumping Station

MGD Treatment Plant 3, Mauripur 54 180 MGD Treatment Plant 4, Korangi (NEW)

  • 180

MGD New Treatment Plant 5 at Mai Kolachi (To be implemented by KPT)

  • 40

MGD

Total 151 500 MGD

  • B. Sewage Treatment Facilities

29th June 2015 KW&SB

slide-19
SLIDE 19

ADMINISTRATIVE APPROVALS

PC-I of the Project was approved by ECNEC at a cost of

  • Rs. 7,982 Million on September 19, 2007 on cost sharing of

50:50 between GoP and GoS. Modified PC-Is for Lyari & Malir River Basins has already been approved by PDWP for onward transmission to CDWP as per following details; Lyari River Basin: Rs. 21,356.788 Million Stage-I Rs. 13,771.768 Million

Stage-II Rs. 7,585.020 Million

Malir River Basin: Rs. 15,062.815 Million

29th June 2015 KW&SB

slide-20
SLIDE 20

Implementation Plan of S-III Project

29th June 2015

S-III Project is planned to be implemented in following Phases: PHASE-I: LYARI RIVER BASIN (280 MGD) Phase-I is subdivided into two Stages: (a) Stage-1 (200 MGD):

  • 1. Sewage Transmission from Gulshan-e-Yaseenabad to

Mauripur

  • 2. Complete Rehabilitation and Enhancement of TP-I
  • 3. Rehabilitation of TP-III

(b) Stage-2 (80 MGD):

  • 1. Balance Sewage Transmission from Surjani to

Gulshan-e-Yaseenabad

  • 2. Enhancement of TP-III

PHASE-II: MALIR RIVER BASIN (180 MGD) (a) Sewage Transmission from Quaidabad to TP-IV (Korangi) (b) Construction of New STP-IV at Korangi (c) Rising Main from TP-II

KW&SB

slide-21
SLIDE 21

CURRENT STATUS OF S-III PROJECT

29th June 2015 KW&SB

slide-22
SLIDE 22

29th June 2015

Design Phase of S-III Project has been completed and also vetted by WS Atkins (U.K). Execution of works of Sewage Transmission and Treatment in Lyari River Basin are in progress.

KW&SB

slide-23
SLIDE 23

Excava&on ¡for ¡River ¡Diversion Lean ¡Concrete Conduit’s ¡Top ¡Slab ¡Concre&ng Base ¡Slab ¡Formwork ¡Fixing

PICTORIAL S-III PROJECT

slide-24
SLIDE 24

PICTORIAL S-III PROJECT

Installa&on ¡of ¡PVC ¡Liner ¡in ¡Progress Concre&ng ¡of ¡RCC ¡Conduit PVC ¡Lined ¡RCC ¡Conduit RCC ¡Boundary ¡Wall ¡@ ¡TP-­‑III

slide-25
SLIDE 25

PICTORIAL S-III PROJECT

Ribs ¡Repairing ¡Works ¡@ ¡TP-­‑I Sludge ¡removal ¡from ¡Anaerobic ¡Lagoon ¡ @ ¡TP-­‑III Dewatering ¡from ¡Inlet ¡Chamber ¡@ ¡TP-­‑III ¡ Rehabilita&on ¡of ¡Sedimenta&on ¡Tanks ¡

slide-26
SLIDE 26

2nd November 2012 29th June 2015 KW&SB

Thank ¡You ¡