1 Project Update - Overview & Schedule Revilla Uplands Project Overall site review changes after Oct 16 th , 2017 Borough Assembly meeting Vehicle & pedestrian flow ticketing, staging, waiting, New passenger


slide-1
SLIDE 1

1

slide-2
SLIDE 2

Project Update - Overview & Schedule

Integrity ∙ Excellence ∙ Respect

5/7/2018 2

Improve the level of service for all users

  • Pedestrians
  • Cyclists
  • Vehicular traffic

Revilla Uplands Project

  • Overall site review – changes after Oct 16th, 2017 Borough Assembly

meeting

  • Vehicle & pedestrian flow – ticketing, staging, waiting,
  • New passenger waiting facilities and support buildings

Revilla / Gravina Marine Projects

  • Construct two new ferry berths at Revilla and Gravina shuttle ferry

terminals.

  • Refurbish existing Revilla & Gravina ferry berths

Schedule

  • Fall, 2018: Complete design/advertise construction contracts.
  • Fall, 2020: Complete construction.
  • Sequencing of 4 construction phases
slide-3
SLIDE 3

Project Introduction

Integrity ∙ Excellence ∙ Respect

5/7/2018 3

slide-4
SLIDE 4

Gravina Access Funded Projects

5/7/2018 4

slide-5
SLIDE 5

Project Overview – Revilla Uplands

5/7/2018 5

VEHICLE STAGING DROP OFF ZONE TAXI LANES EXIT ENTRY WAITING BUILDING EXIT ENTRY/EXIT NEW FERRY BERTH EXISTING FERRY BERTH

slide-6
SLIDE 6

Phase 1 Construction

5/7/2018 6

Duration - 6 Months Key Elements:

North Tongass Highway Improvements Relocate Emergency Sanitary Sewer Bypass Outfall Repair or Reconstruct Large Drainage Culverts Backup Generator Building New Ferry Berth Bulkhead Temporary Parking Relocate Existing Ticketing Kiosks

slide-7
SLIDE 7

Pedestrian Detours During Construction

5/7/2018 7

slide-8
SLIDE 8

Phase 2 Construction

5/7/2018 8

Duration – 6 Months Key Elements:

North Parking Lot Staging Lanes, North Half of Loading Zone Canopy & Retaining Wall Passenger Waiting Building Foundation & Underground Utilities Equipment Storage Building Demo Existing Restrooms & Setup Temp Porta Potties

slide-9
SLIDE 9

Phase 3 Construction

5/7/2018 9

Duration – 3-4 Months Key Elements:

South Parking Lot Loading Zone Canopies Complete Passenger Waiting Building Site Lighting

slide-10
SLIDE 10

5/7/2018 10

Phase 4 Construction

Duration – 3 Months Key Elements:

Complete Loading Zone & Ferry Exit Lanes Complete Loading Zone Canopies Site Lighting & Cameras

slide-11
SLIDE 11

Wayfinding & Signage

5/7/2018 11

PEDESTRIAN SIGNAGE PLACED NEXT TO KIOSK AND UNDER CANOPIES AS WINDBREAK FEATURES HIGHLY VISABLE VEHICULAR SIGNAGE MONUMENT STYLE WELCOME SIGN “WELCOME TO KETCHIKAN”

slide-12
SLIDE 12

Wayfinding & Signage

5/7/2018 12

FERRY LANES & LOADING ZONES

slide-13
SLIDE 13

Automated Ticketing

5/7/2018 13

  • 1. No ticket needed to travel from Gravina to Revilla.
  • 2. Ticket fee from Revilla to Gravina will cover cost of round trip.
  • 3. Passenger Ferry Tickets may be purchased at credit card kiosks in parking lot.
  • 4. Also at credit card/cash kiosks inside Passenger Waiting Building.
  • 5. Passenger & Vehicle Ferry Tickets may be purchased at credit card kiosks in the ferry

vehicle cueing line.

  • 6. Monthly passes for frequent passengers will still be available.
  • 7. Proximity Cards will be issued for companies/individuals who wish to establish pre-paid

accounts.

  • 8. The proximity cards will allow quick access into the vehicle cueing lanes via a reader co-

located with the ticketing kiosks at the entrance into the lanes. Self reporting will be used to track the number of passengers in the vehicles.

  • 9. Passengers with proximity cards will swipe them on a reader at the top of the bridge.
  • 10. Passengers/vehicles will be randomly checked on the ferry.
slide-14
SLIDE 14

Automated Ticketing Concept

5/7/2018 14

PARKING & FERRY PASSENGER KIOSKS VEHICLE TICKETING KIOSKS & PROX CARD READERS PARKING & FERRY PASSENGER KIOSKS FERRY PASSENGER PROX CARD READER

slide-15
SLIDE 15

Kiosk Systems

5/7/2018 15

Ventek kiosk system (Do not duplicate images)

slide-16
SLIDE 16

Baggage Cart System

5/7/2018 16

slide-17
SLIDE 17

5/7/2018 17

Baggage Cart Circulation

Baggage Loading Baggage Loading

slide-18
SLIDE 18

Support Structures

5/7/2018 18

  • 1. Waiting Building – Provides interior conditioned waiting space and restrooms.

Ticket kiosk located in entry vestibule. Provides luggage staging and support vehicle lane

  • 2. Storage Building – Houses Bobcat snowplow and one tug vehicle. Other site

maintenance items located in building. One ticket kiosk with wayfinding sign located on exterior of building.

  • 3. Generator Building – Houses emergency back up generator
slide-19
SLIDE 19

5/7/2018 19

Buildings & Site Elements

STORAGE BUILDING CANOPIES WAITING BUILDING GENERATOR BUILDING SIGNAGE SIGNAGE

slide-20
SLIDE 20

Waiting Building Roof Options

5/7/2018 20

OPTION A INVERTED ROOF – 14’-0” ROOFLINE NO EXPOSED DOWNSPOUTS OPTION B GABLE ROOF – 11’-0” ROOFLINE

slide-21
SLIDE 21

Waiting Building Roof Options

5/7/2018 21

OPTION A INVERTED ROOF – 14’-0” ROOFLINE NO EXPOSED DOWNSPOUTS OPTION B GABLE ROOF – 11’-0” ROOFLINE

slide-22
SLIDE 22

5/7/2018 22

Inverted roof at 14’ to prevent truck vehicle-structure collisions.

slide-23
SLIDE 23

SUPPORT BUILDINGS

5/7/2018 23

STORAGE BUILDING GENERATOR BUILDING

slide-24
SLIDE 24

Option A Renderings

5/7/2018 24

WAITING BUIDING RENDERINGS – INVERTED ROOF OPTION

slide-25
SLIDE 25

Option B Renderings

5/7/2018 25

WAITING BUIDING RENDERINGS – GABLE ROOF OPTION

slide-26
SLIDE 26

View From Exit Lanes (Opt A)

5/7/2018 26

slide-27
SLIDE 27

5/7/2018 27

Canopy Renderings (Opt A)

slide-28
SLIDE 28

5/7/2018 28

Staging Lanes & Storage Building

RENDERINGS FERRY STAGING ENTRY & STORAGE BUILDING

slide-29
SLIDE 29

Revilla Draft Marine Plan

5/7/2018 29

Revilla Airport Shuttle Ferry Berth

slide-30
SLIDE 30

Gravina Draft Marine Plan

5/7/2018 30

Gravina Airport Shuttle Ferry Berth

ADA RAMP IMPROVEMENTS EXISTING PASSANGER WAITING FACILITY

slide-31
SLIDE 31

Gravina Walkway Improvements

5/7/2018 31

slide-32
SLIDE 32

Gravina Walkway Improvements

5/7/2018 32

slide-33
SLIDE 33

Gravina Walkway Improvements

5/7/2018 33

slide-34
SLIDE 34

Project Website