1 presentation agenda
play

1 Presentation Agenda Presenters Organization Chart Project Scope - PowerPoint PPT Presentation

1 Presentation Agenda Presenters Organization Chart Project Scope Challenges & Key Milestones Project Approach Similar Projects/Lessons Learned Summary Q & A 2 Our Presenters Jorge Ortiz, PE Senior


  1. 1

  2. Presentation Agenda  Presenters  Organization Chart  Project Scope  Challenges & Key Milestones  Project Approach  Similar Projects/Lessons Learned  Summary  Q & A 2

  3. Our Presenters Jorge Ortiz, PE • Senior Project Engineer • 32 Years of Experience • Advanced MOT/FDOT QC Manager • Former Broward County HC&ED Employee • Roland Barros, CGC • Project Administrator • 18 Years of Experience • State Certified General Contractor • Final Estimates Levels 1 & 2 • Advanced MOT/FDOT QC Manager • Mark Moshier, PE • EVP/Principal in Charge • 39 Years of Experience • Former FDOT D6 Construction Engineer • 3

  4. The K&S Team 4

  5. Project Scope  Complete CEI services including Contract Administration and Materials Testing for:  Widening, Reconstruction , Drainage, Milling & Resurfacing of Pembroke Road from Dykes Road to Silver Shores Blvd  New Dedicated 4 ft. Bike Lane on each Side with 2 ft. Buffer from Travel Lanes  Four - 11 ft. Travel Lanes and new 17.5 ft. Median  Landscape with Irrigation System  10 ft. Precast Concrete Wall in various Locations on Both Sides 5

  6. Challenges and Key Milestones  Multi-Agency Coordination (CIGP Funding)  Broward County Hwy Construction & Engineering Division  City of Pembroke Pines - (25%)  City of Miramar - (25%)  Florida Department of Transportation (FDOT) - (50%)  Broward County Transit (BCT)  South Broward Drainage District (SBDD)  Silver Shores Elementary – Safe Ingress/Egress in Phase III  Major Drainage Construction – Phase II & III (Major Phases)  Maintenance of Traffic – Six Phases  Construction of 10 ft. High Precast Concrete Wall  Impacts to Existing Trees on South side  FPL Powerline  Public Involvement – Silver Shores Community, Silver Shores Park, Memorial Hospital Miramar 6

  7. Challenges and Key Milestones  Length Reconstruction = 2539 LF  Length M&R = 3450 LF  Contract Time = 480 Da  Contractor responsible for preparing and permitting MOT Plans  Construction of 10 ft. Precast Wall will be need coordination w/FPL, to be constructed in Ph I & Ph III  Coordination with Broward County Transit on Bus Stops- Arethia Douglas  Access to Silver Shores Elementary and Park must be Maintained  Landscape and Irrigation System to be constructed in Ph IV  New Roadway Lighting and Two Signalized Intersections 7

  8. Challenges and Key Milestones  Drainage construction will be the Controlling Item of Work  Drainage Structures in Close Proximity to WM’s & FM  Coordination w/ SBDD – Outfall to Silver Shores Lakes  Subsoil Excavation = 28,372 CY (Pay Item 120-4)  Embankment = 34, 271 CY (Pay Item 120-6)  Daily Survey Control will be Critical to Ensure Proper Quantity Tracking and Payments to Contractor 8

  9. Challenges and Key Milestones Silver Shores Elementary School Principal Jonathan Leff Silver Shores Park 9

  10. Project Approach  Pre-Construction Activities – Setup prior to Contractor’s NTP  Management of Meetings – Progress (Weekly or Bi-weekly) & Coordination meetings  Safety – Workzone, MOT, Pedestrians  Decision Making Process/RFI – Quick Turnaround Time  Conflict Resolution- Resolve at Lowest Level Possible  Project Scheduling – Baseline, Updates and Two Week Look Ahead  Closeout of Project – Within 30 Days  Complete Streets Implementation – Broward Complete Streets Guidelines 10

  11. Similar Projects/ Lessons Learned SR A1A Oakland Park Blvd to Flamingo Ave Completion: August 2017  Complete Streets Project with designated Bike Lanes, Decorative Sidewalks and Pedestrian Lighting  Multiple Agency Coordination  Extensive Drainage Installation/Multiple MOT Phases  Daily Public Involvement Outreach 11

  12. Similar Projects/ Lessons Learned NW 52 nd St/NW 102 nd Ave Completion: August 2017  Residential Neighborhood with Elementary School  Drainage w/ Multiple MOT Phases  Extensive Utility Coordination  Bike Lanes, Decorative Cross Walks and Rapid Flashing Beacons 12

  13. Summary  Highly Experienced Team w/ Similar Project Experience in Broward County – Acting as Extension of Staff  Past Familiarity w/ the Project – Previous Apparent Low Bidder in 2012 as a Design/Build Project  Same Team working on SR A1A will be Assigned to this Project- No Learning Curve!  Senior Project Engineer Previously Worked at Broward County HC&E Division  Extensive Experience Working w/ Requirements of FDOT Funded Projects  Team has Strong Public Involvement Skills – Understand How to Communicate w/ Stakeholders  Our References Are Excellent! 13

  14. Summary WE EXCEED OUR CLIENTS EXPECTATIONS! WE WANT TO BE YOUR PEMBROKE ROAD CEI TEAM! 14

  15. 15

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend